05-Aug-2024 |
Ar. Neeraj Gautam,
Associate Architectural Executive and Sh. Ashish Dubey, Chartered Accountant
briefed about the facts of the project.
Sh. Pradeep Garg (AR) is present on
behalf of the promoter.
Approved as proposed subject to the
above compliances. The certificate shall be issued only after the compliances
are done. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
29-Jul-2024 |
Ar. Neeraj Gautam,
Associate Architectural Executive and Sh. Ashish Dubey, Chartered Accountant
briefed about the facts of the project.
Sh. Pradeep Garg (AR) and Sh. Narender
Singh (AR) are present on behalf of the promoter.
The confirmation of sanction of plans
is awaited from DTP Gurugram. The AR of the promoter is directed to rectify the
remaining deficiencies.
The matter to come up on 05.08.2024.
|
ADJOURNMENT |
View Order |
15-Jul-2024 |
Ar. Neeraj Gautam, Associate
Architectural Executive and Sh. Ashish Dubey, Chartered Accountant briefed
about the facts of the project.
Sh. Pradeep Garg (AR) is present on behalf of
the promoter.
A confirmation regarding approval of plans by
DTP Gurugram shall be sought through email. Further the AR to rectify other
deficiencies including NOC from the lender w.r.t. creation of 3rd
party rights. The office to check the status of compliances of earlier
registration as well as submission of QPR and annual audited financial
statement.
The matter to come up on 29.07.2024. |
ADJOURNMENT |
View Order |
01-Jul-2024 |
The matter is adjourned and to come up on 15.07.2024. |
EXAMINATION BY AUTHORITY |
View Order |