HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1666-2024
Submission Date : 07-06-2024 11:53:34 AM
Applicant Type : Company
Project Type: NEW




CORONA REALTORS PRIVATE LIMITED
S - 550/51 SCHOOL BLOCK SHAKARPUR EAST DELHI DELHI 110092
01244561500
9810818355 (Number Shared by Promoter in Public)
legal@parasbuildtech.com
https://theflorettenqlaveparas.com/
XXXX573G
U45201DL2005PTC135674
 
 


 
 


 
 







THE FLORETT ENQLAVE
SECTOR 59
GURGAON
GURUGRAM
01244561500
8800765212 (Number Shared by Promoter in Public)
legal@parasbuildtech.com
REENA GULATI
01244561500
8800765212 (Number Shared by Promoter in Public)
reena.gulati@parasbuildtech.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
16271607-06-2024467420ICICI BANKHRERA Gurugram
250573428-06-202470356ICICI BANK HRERA Gurugram







6.225 (Acre)
2.64
1.98
6.225 (Acre)
License No. 89 of 2022 granted by Town and Country Planning Department, Government of Haryana
No
Address     304 KANCHAN HOUSE KARAMPURA COMMERCIAL COMPLEX NEW DELHI 110015
Address     305 3RD FLOOR KANCHAN HOUSE KARAMPURA COMMERCIAL COMPLEX NEW DELHI 110015
Address     C-4 1ST FLOOR MALIVIYA NAGAR NEW DELHI 110017
Address     C-4 1ST FLOOR MALIVIYA NAGAR NEW DELHI 110017
Annexure-B- COLLABORATOR
YES
Yes
COLLABORATION AGREEMENT NO. 6862 DATED 26.08.2021
No
Yes
Yes







22112.53 Lakhs
2184.56 Lakhs
11173.38 Lakhs
285.73 Lakhs
8468.36 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS2.2147
3CONSTRUCTION OF ROADS0
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total2.2147




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDANo
WATER SUPPLYGMDANo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALGMDANo
STORM WATER DRAINAGEGMDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS0SUBMITTED TO HUDA
2WATER SUPPLY SYSTEM0SUBMITTED TO HUDA
3STORM WATER DRAINAGE0SUBMITTED TO HUDA
4ELECTRICITY SUPPLY SYSTEM0SUBMITTED TO HUDA
5SEWAGE TREATMENT & GARBAGE DISPOSAL0SUBMITTED TO HUDA
6STREET LIGHTING0SUBMITTED TO HUDA
7SECURITY AND FIRE FIGHTING0SUBMITTED TO HUDA
8PLAYGROUNDS AND PARKS0SUBMITTED TO HUDA
9CLUB HOUSE/COMMUNITY CENTRE0SUBMITTED TO HUDA
10SHOPPING AREA0SUBMITTED TO HUDA
11RENEWABLE ENERGY SYSTEM0SUBMITTED TO HUDA
12SCHOOL0SUBMITTED TO HUDA
13HOSPITAL/DISPENSARY0SUBMITTED TO HUDA
14ANY OTHER0SUBMITTED TO HUDA


08-07-2022 (date)
25-04-2024 (date)
01-08-2024
31-01-2029
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings84.0813244
Apartment/Shops/Other Buildings47.853311
Apartment/Shops/Other Buildings60.1162
Apartment/Shops/Other Buildings61.3231
Apartment/Shops/Other Buildings41.8162
Apartment/Shops/Other Buildings49.2431
Apartment/Shops/Other Buildings59.92217





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1712.142210.15
Shops00
Plots00

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1512.621722.63885.821747.94
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1054.50986.81986.81110.76
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments110.76110.76110.76113.85
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments110.76110.7636.92
Shops000
Plots000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter (2028)
Apr-JuneJuly-SepOct-DecJan-Mar












Yes
No
ICICI BANK LTD, OFFICE NUMBER 11, TIMES TOWER, M G ROAD, GURGAON, HARYANA 122001
777705114304
ICIC0001143
1100229199
1143
Mr. Kunal Rishi, # Q-702,Paras Quartier, Gwal Pahari, Gurugram & Mr. Narender











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
No
Yes
Yes
Yes
No
No
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO 89 OF 2022ALREADY BEEN OBTAINED07-07-2022
II. LAYOUT PLAN APPROVALALREADY BEEN OBTAINED08-07-2022
III. ZONINGALREADY BEEN OBTAINED18-11-2022
IV. BUILDING PLANSALREADY BEEN OBTAINED25-04-2024
V. SERVICE PLAND AND ESTIMATESALREADY BEEN OBTAINED02-12-2022








Yes


Yes


As per HARERA







PARAS FLORETT, SECTOR 59, GURUGRAM
6.225
0
101
0
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
6926.456926.455371.90
Cost of the apartments000
Cost of the infrastructure1530.631530.63392.00
Others costs5395.825395.8225.01


0 Lakhs
0 Lakhs
6000 Lakhs
4900 Lakhs
No
31-03-2027
31-03-2027




FLORETT CENTRAL
0.249
39
0
0
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
2381.92381.90
Cost of the apartments616.70616.700
Cost of the infrastructure128.85128.850
Others costs632.96632.960


0 Lakhs
0 Lakhs
6000 Lakhs
4900 Lakhs
No
06-11-2023
30-06-2027










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES
2WALL FINISHING DETAILSOBD/ACRYLIC DISTEMPER
3KITCHEN DETAILSVITRIFIED TILES, DADO UP TO 2' ABOVE COUNTER AND OBD/ACRYLIC DISTEMPER
4BATHROOM FITTINGSPREMIUM QUALITY CP & SANITARY
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESALUMINIUM / SKIN DOOR
7GLASS WORKNA
8ELECTRIC FITTINGSISI MARK
9CONDUCTING AND WIRING DETAILSISI MARK
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSSTANDARD LIFT
13EXTERNAL GLAZINGSUPVC/ALUMINIUM
13.1WINDOWS/GLAZINGSUPVC/ALUMINIUM
14DOORSLAMINATED WOODEN DOOR
14.1MAIN DOORSLAMINATED WOODEN DOOR
14.2INTERNAL DOORSLAMINATED / SKIN DOOR
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSOBD/ACRYLIC DISTEMPER
1 . 3 CEILINGOBD/ACRYLIC DISTEMPER
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOOR"VITRIFIED TILES / LAMINATED WOODEN FLOORING"
2 . 2 WALLSOBD/ACRYLIC DISTEMPER
2 . 3 CEILINGOBD/ACRYLIC DISTEMPER
2 . 4 MODULAR WARDROBESN.A.
3 . MASTER TOILET
3 . 1 FLOORMATT FINISH TILES
3 . 2 WALLSTILES & OBD/ ACRYLIC DISTEMPER COMBINATION
3 . 3 CEILINGMR BOARD CEILING
3 . 4 COUNTERSN.A
3 . 5 SANITARY WARE/CP FITTINGSN.A.
3 . 6 FITTING/FIXTURESN.A
4 . BED ROOMS
4 . 1 FLOOR"VITRIFIED TILES / LAMINATED WOODEN FLOORING"
4 . 2 WALLSOBD/ACRYLIC DISTEMPER
4 . 3 CEILINGOBD/ACRYLIC DISTEMPER
4 . 4 WARDROBESN.A
5 . TOILET
5 . 1 FLOORMATT FINISH TILES
5 . 2 WALLSTILES & OBD/ ACRYLIC DISTEMPER COMBINATION
5 . 3 CEILINGMR BOARD CEILING
5 . 4 COUNTERSN.A.
5 . 5 SANITARY WARE/CP FITTINGSN.A
5 . 6 FIXTURESN.A
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILES
6 . 2 WALLSOBD/ACRYLIC DISTEMPER
6 . 3 CEILINGOBD/ACRYLIC DISTEMPER
6 . 4 COUNTERSN.A
6 . 5 FIXTURESN.A
6 . 6 KITCHEN APPLIANCESN.A
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD06-06-2024 View Document
2IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN03-06-2024 View Document
3COPY OF LICENSE ALONG WITH SCHEDULE OF LAND03-06-2024 View Document
4SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN03-06-2024 View Document
5ZONING PLAN03-06-2024 View Document
6IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN03-06-2024 View Document
7BUILDING PLAN- A2304-09-2024 View Document
8BUILDING PLAN- A2204-09-2024 View Document
9BUILDING PLAN- C1104-09-2024 View Document
10BUILDING PLAN- A4404-09-2024 View Document
11LOI04-09-2024 View Document
12BUILDING PLAN- A1304-09-2024 View Document
13BUILDING PLAN- A4004-09-2024 View Document
14BUILDING PLAN- C304-09-2024 View Document
15BUILDING PLAN- C804-09-2024 View Document
16BUILDING PLAN- H104-09-2024 View Document
17CONSENT TO ESTABLISH04-09-2024 View Document
18DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.04-09-2024 View Document
19BUILDING PLAN- A904-09-2024 View Document
20BUILDING PLAN- A3804-09-2024 View Document
21BUILDING PLAN- A3904-09-2024 View Document
22LC-IV-B-BILATERAL04-09-2024 View Document
23BUILDING PLAN- A3604-09-2024 View Document
24BUILDING PLAN- C604-09-2024 View Document
25CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT04-09-2024 View Document
26BUILDING PLAN- A1504-09-2024 View Document
27BUILDING PLAN- F604-09-2024 View Document
28NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT04-09-2024 View Document
29BANK UNDERTAKING04-09-2024 View Document
30BUILDING PLAN- A704-09-2024 View Document
31BUILDING PLAN- A1904-09-2024 View Document
32BUILDING PLAN- A2004-09-2024 View Document
33BUILDING PLAN- A2504-09-2024 View Document
34BUILDING PLAN- A2704-09-2024 View Document
35BUILDING PLAN- A3404-09-2024 View Document
36BUILDING PLAN- C504-09-2024 View Document
37BUILDING PLAN- E104-09-2024 View Document
38BUILDING PLAN- A1804-09-2024 View Document
39BUILDING PLAN- A2904-09-2024 View Document
40BUILDING PLAN- A3204-09-2024 View Document
41BUILDING PLAN- A3304-09-2024 View Document
42BUILDING PLAN- A3104-09-2024 View Document
43FLUSHING WATER LAYOUT04-09-2024 View Document
44SEWERAGE LAYOUT04-09-2024 View Document
45BUILDING PLAN- A304-09-2024 View Document
46BUILDING PLAN- A1104-09-2024 View Document
47BUILDING PLAN- A4204-09-2024 View Document
48BUILDING PLAN- A4304-09-2024 View Document
49CARPET AREA DETAILS04-09-2024 View Document
50ROAD LAYOUT04-09-2024 View Document
51BUILDING PLAN- G204-09-2024 View Document
52BUILDING PLAN- A1004-09-2024 View Document
53BUILDING PLAN- A2604-09-2024 View Document
54BUILDING PLAN- A2804-09-2024 View Document
55BUILDING PLAN- A3004-09-2024 View Document
56BUILDING PLAN- G104-09-2024 View Document
57SERVICE PLAN ESTIMATES-APPROVAL04-09-2024 View Document
58BUILDING PLAN- A1604-09-2024 View Document
59BUILDING PLAN- C704-09-2024 View Document
60APPROVED LAYOUT PLAN04-09-2024 View Document
61BUILDING PLAN- A804-09-2024 View Document
62BUILDING PLAN- C104-09-2024 View Document
63BUILDING PLAN- C904-09-2024 View Document
64BUILDING PLAN- A1404-09-2024 View Document
65BUILDING PLAN- F104-09-2024 View Document
66BUILDING PLAN- A104-09-2024 View Document
67BUILDING PLAN- A204-09-2024 View Document
68DRAINAGE LAYOUT04-09-2024 View Document
69BUILDING PLAN- A404-09-2024 View Document
70BUILDING PLAN- C204-09-2024 View Document
71BUILDING PLAN- A504-09-2024 View Document
72BUILDING PLAN- A604-09-2024 View Document
73BUILDING PLAN- A1204-09-2024 View Document
74DOMESTIC WATER LAYOUT04-09-2024 View Document
75BUILDING PLAN- A1704-09-2024 View Document
76BUILDING PLAN- A2104-09-2024 View Document
77BUILDING PLAN- A2404-09-2024 View Document
78BUILDING PLAN- A3504-09-2024 View Document
79BUILDING PLAN- A3704-09-2024 View Document
80BUILDING PLAN- A4104-09-2024 View Document
81BUILDING PLAN- F704-09-2024 View Document
82BUILDING PLAN- C404-09-2024 View Document
83BUILDING PLAN- C1004-09-2024 View Document
84BUILDING PLAN- D104-09-2024 View Document
85BUILDING PLAN- D204-09-2024 View Document
86BUILDING PLAN- F204-09-2024 View Document
87BUILDING PLAN- F304-09-2024 View Document
88BUILDING PLAN- F504-09-2024 View Document
89BUILDING PLAN- F404-09-2024 View Document
90DEMARCATION PLAN04-09-2024 View Document
91LC-IV04-09-2024 View Document