Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
Not Yet Approved/Certificate Not Uploaded Yet RERA-GRG-1639-2024 22-Jul-2024 22-Jul-2024 APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS NOT REQUIRED Yes 09-Aug-2024 BY HAND Deficiency Notice
First hearing View Form(A-H)
Project Listing Details
Date of Hearing Proceedings of the day Status Order
18-Nov-2024 Sh. Sumeet, Engineering Officer briefed about the facts of the project. Sh. Anish Dham (AR), Sh. Kabir Kapoor (AR) and Sh. Nitin Gupta (AR) are present on behalf of the promoter. The AR of the promoter clarifies that 0.175 acres area has been got migrated from earlier license area (license no. 88 of 2010) as the said area/pocket was reserved for UD (undetermined use) and CC in respect of the said license already stand obtained in the year 2013. The requisite consent of 2/3rd allotees has been submitted in the authority and no objection in respect of the public notice issued by the Authority has been received. No plots or saleable area is approved/shown in the additional licensed area.  In view of the same, the addendum to the earlier RC no. 107 of 2022 is approved as proposed subject to corrections in online A-H form & DPI and this shall be without prejudice the rights of the existing allotees under section 14 of the Act.  APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
28-Oct-2024 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Anish Dham (AR), Sh. Kabir Kapoor (AR) and Sh. Nitin Gupta (AR) are present on behalf of the promoter. The AR of the promoter states that they have obtained the additional license no. 237 of 2023 dated 03.11.2023 for area measuring 0.175 acres in addition to earlier license no. 139 of 2022 dated 09.09.2022 for area admeasuring 2.98125 acres, thereby forming total area admeasuring 3.156 acres for development of commercial plotted colony. Accordingly, layout plan has been revised and approved by DTCP, Haryana. The earlier licensed area is already registered with the authority and the promoter requests to grant an amendment in the earlier registration due to grant of additional license instead of granting separate registration for additional licensed area as the additional area is very small (i.e., 0.175 acres) and there are only two plots added in revised layout plan and that too demarcated on earlier licensed land. Further, the promoter has submitted the consent of 2/3rd allottees of the project for revision in the existing layout plan. A two weeks public notice be issued in three newspapers (One Hindi and Two English) of wide circulation for inviting objections if any regarding revision in layout plan. Meanwhile, the office to process the request for amendment in earlier registration. The matter to come up on 18.11.2024. ADJOURNMENT View Order
30-Sep-2024 The matter is adjourned and to come up on 28.10.2024. ADJOURNMENT View Order
09-Sep-2024 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh.  Anish Dham (AR), Sh. Ketan Nanda (AR) and Sh. Nitin Gupta (AR) are resent on behalf of the promoter. The AR to submit the requisite consent of 2/3rd allottees and thereafter a public notice for objections if any be issued. The matter to come up on 30.09.2024.  ADJOURNMENT View Order
12-Aug-2024 The matter is adjourned and to come up on 09.09.2024. EXAMINATION BY AUTHORITY View Order