HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1639-2024
Submission Date : 22-07-2024 03:29:32 PM
Applicant Type : Company
Project Type: NEW




DLF HOME DEVELOPERS LIMITED
2ND FLOOR, ARJUN MARG, DLF SHOPPING MALL, DLF CITY PHASE 1, GURUGRAM
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in
https://www.dlf.in
XXXX037H
U74899HR1995PLC082458
 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 







ALAMEDA CENTRAL
SECTOR 73
KADIPUR ST
GURUGRAM
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in
SUNIL ARORA
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
152371026-06-2024766400ICICI BANK (GURGAON)HRERA Gurugram
252116009-09-2022723883ICICI BANK (GURGAON)HRERA Gurugram







3.156 (Acre)
1.50
1.50
3.156 (Acre)
237 of 2023 dated 03.11.2023 and 139 of 2022 dated 09.09.2022
Yes







7870 Lakhs
2702 Lakhs
0 Lakhs
2265 Lakhs
2903 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 1.086
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 1.110
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0.45
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0.060
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0.040
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
13OPENAREA 0.410
Total3.156




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDAYes
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS340.75AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM117.92AS PER PROJECT REPORT
3STORM WATER DRAINAGE114.61AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM413.95AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL119.87AS PER PROJECT REPORT
6STREET LIGHTING49.52AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15EARTH WORKS119.87AS PER PROJECT REPORT
16SEWERAGE SYSTEM227.17AS PER PROJECT REPORT
17UGT107.88AS PER PROJECT REPORT
18RAINWATER HARVESTING 86.31AS PER PROJECT REPORT
19PARKING AND PARKS567.15AS PER PROJECT REPORT


06-11-2023 (date)
18-01-2024 (date)
01-04-2023
08-09-2027
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 136.15 15
2 88.20 10
3 86.436 17
Total42


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System41.27
Sewerage treatment & garbage disposal0
Electricity Supply System82.79
Storm Water Drainage40.11
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Earth Work77.12
Rain Water Harvesting30.21
Sewage System101.50

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Earth0
Earth Work00
Earth Works0

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements000
Water Supply System000
Sewerage treatment & garbage disposal000
Electricity Supply System000
Storm Water Drainage000
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000
Earth Works00
Rainwater harvesting00
Sewerage system00

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0085.1985.19
Water Supply System0029.4847.17
Sewerage treatment & garbage disposal0029.9729.97
Electricity Supply System00103.49124.19
Storm Water Drainage0045.8428.65
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Rainwater harvesting0021.5834.52
Earth Works035.966.79
Sewerage system0056.7968.88
UGT26.9726.97
Street lighting24.76
Parking and Parks283.58

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements170.370
Water Supply System00
Sewerage treatment & garbage disposal59.930
Electricity Supply System103.490
Storm Water Drainage00
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other00
Parking and Parks283.58
Street lighting24.76
UGT53.94












Yes
No
ICICI BANK LIMITED 9A, CONNAUGHT PLACE NEW DELHI - 110 001
000705053446
ICIC0000007
110229002
0007
Mr. Puneet Rakheja(H.No. 386, Sector 31, Faridabad, Haryana 121003) 3. Mr. Pankaj KumarJain (C701, Apex Acacia Valley, Sector 3, Ghaziabad, Uttar Pradesh201010) 4. Mr. Saurabh Kumar Gupta (1116, Vikas Kunj, Vikaspuri,Delhi 110018) 5. Mr. Gaurav Arora (A-33, Near Mehfil Banquet HallMahendru Enclave, GT Karnal Road, Delhi 110009) 6. Ms. SandhyaSingla (Neelanchal Apartments, Plot No. 3, Sector 4, Dwarka, Delhi110075) 7. Mr. Ashok Nanda (A255, Surya Nagar, Chander Nagar,Ghaziabad. Uttar Pradesh 201011) 8. Mr. Rajeev Singhal (Flat No. 14,Tower No. 4, Raj Nagar Extension, Signature Homes, Ghaziabad, UttarPradesh 201001) 9. Mr. Sujeet Kumar Sinha (C-061, DLF New TownHeights, IMT Manesar, Sector 91, Gurgaon, Haryana 122505) 10. Mr.Pankaj Kumar (A3, Rajcottage 1/18, Rajendra Nagar, Ghaziabad, UttarPradesh 201005)
YEs











Yes
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
No
Yes
Yes
Yes
No
No
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENCE 237 OF 2023ALREADY BEEN OBTAINED03-11-2023
II. LAYOUT PLANALREADY BEEN OBTAINED06-11-2023
III. ACS IIALREADY BEEN OBTAINED18-01-2024
IV. SPE REVISEDALREADY BEEN OBTAINED30-08-2024
V. LICENSE 139 OF 2022ALREADY BEEN OBTAINED09-09-2022
VI. ACS IALREADY BEEN OBTAINED14-11-2022








Yes


Yes


As per RERA Act







THE ARBOUR
25.087
1137
0
1137
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
35591937165358256
Cost of the apartments33734835294039821
Cost of the infrastructure000
Others costs185711871318435


2954 Lakhs
523015.40 Lakhs
0 Lakhs
715.92 Lakhs
No
31-03-2030
31-03-2030




THE GRAND ENCLAVE
10.77
0
76
0
76
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
851385132437
Cost of the apartments000
Cost of the infrastructure5700570014
Others costs281328132423


7350.00 Lakhs
12770.81 Lakhs
0 Lakhs
2450 Lakhs
No
31-08-2026
31-08-2026




ARCADE 68
2.00
0
16
0
16
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
250234851829
Cost of the apartments626153734
Cost of the infrastructure1501500
Others costs172617981795


1041 Lakhs
6376 Lakhs
0 Lakhs
1950 Lakhs
No
10-11-2027
10-11-2027




GARDEN CITY CENTRAL
8.0396
0
122
0
122
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
2223120839865
Cost of the apartments160842922871
Cost of the infrastructure2703500
Others costs34574416994


6219 Lakhs
19246 Lakhs
0 Lakhs
18009 Lakhs
No
24-08-2024
24-08-2024




INDEPENDENT FLOORS DLF CITY PH-IV (G)
0.8314
44
0
44
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
747286744345
Cost of the apartments477157954127
Cost of the infrastructure000
Others costs27012879218


14136 Lakhs
3271 Lakhs
0 Lakhs
6088 Lakhs
No
14-11-2024
14-11-2024




INDEPENDENT FLOORS ALAMEDA
2.78
116
29
116
29
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
176601941614180
Cost of the apartments135061625211116
Cost of the infrastructure000
Others costs210231643064


34999 Lakhs
13676 Lakhs
0 Lakhs
16247 Lakhs
No
24-11-2024
24-11-2024




CENTRAL AVENUE
6.65
0
60
0
60
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
20502045310
Cost of the apartments166016553
Cost of the infrastructure000
Others costs390390307


7034 Lakhs
4535 Lakhs
0 Lakhs
2413 Lakhs
No
30-09-2025
30-09-2025




CENTRAL 67
8.6987
0
75
0
75
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
217722082614234
Cost of the apartments000
Cost of the infrastructure73006227101
Others costs000


3268 Lakhs
68368 Lakhs
0 Lakhs
14436 Lakhs
No
31-12-2027
31-12-2027




INDEPENDENT FLOOR DLF CITY (H)
0.9726
52
0
52
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
619567361872
Cost of the apartments592164511594
Cost of the infrastructure000
Others costs274285278


8536 Lakhs
11510 Lakhs
0 Lakhs
4248 Lakhs
No
15-12-2024
15-12-2024




CENTRAL 74
3.325
0
8
0
8
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
577957792654
Cost of the apartments000
Cost of the infrastructure3003000
Others costs315131512648


0 Lakhs
0 Lakhs
0 Lakhs
2667 Lakhs
No
06-09-2028
06-09-2028










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 11-06-2024 View Document
2 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 11-06-2024 View Document
3 ZONING PLAN 11-06-2024 View Document
4 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 11-06-2024 View Document
5 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 11-06-2024 View Document
6 DEMARCATION PLAN 11-06-2024 View Document
7 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 11-06-2024 View Document
8 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 16-07-2024 View Document
9 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 16-07-2024 View Document
10 CORRECTION IN NAME OF THE LICENSE NO. 237 OF 2023 (0.175) ACRES 21-01-2025 View Document
11 JAMABANDI BEGUMPUR KHATOLA 2018-19 (002) 21-01-2025 View Document
12 SITE PLAN & CALCULATIONS 21-01-2025 View Document
13 NEC 21-01-2025 View Document
14 PERT CHART 21-01-2025 View Document
15 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 21-01-2025 View Document
16 SCO TYPE A 21-01-2025 View Document
17 JAMABANDI BEGUMPUR KHATOLA 2018-19 21-01-2025 View Document
18 LICENSE NO 139 OF 2022 21-01-2025 View Document
19 SCO PUBLIC TOILET BLOCK 21-01-2025 View Document
20 APPROVAL OF STANDARD DESIGN 21-01-2025 View Document
21 ROAD LAYOUT 21-01-2025 View Document
22 SEWAGE LAYOUT PLAN 21-01-2025 View Document
23 SCO TYPE B 21-01-2025 View Document
24 SEWERAGE-SPE 0.175 21-01-2025 View Document
25 AKS SHIZRA 21-01-2025 View Document
26 SCO TYPE C 21-01-2025 View Document
27 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 21-01-2025 View Document
28 DOMESTIC & FIREFIGHTING LAYOUT 21-01-2025 View Document
29 BANK UNDERTAKING 21-01-2025 View Document
30 TITLE SEARCH REPORT_MERGED 21-01-2025 View Document
31 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 21-01-2025 View Document
32 ESTIMATED COST OF PROJECT_ALAMEDA CENTRAL (002) 21-01-2025 View Document
33 PROJECT COST INCURRED_DRAFT CERTIFICATE 21-01-2025 View Document
34 SPE OF 2.98125 ACRES-ALMEDA CENTRAL 21-01-2025 View Document
35 FLUSHING & IRRIGATION SUPPLY LAYOUT 21-01-2025 View Document
36 STORMWATER LAYOUT PLAN 21-01-2025 View Document
37 SPE OF 2.98125 ACRES-ALAMEDA CENTRAL 21-01-2025 View Document
38 DOMESTIC WATER SUPPLY-SPE 0.175 21-01-2025 View Document
39 RECYLED WATER SUPPLY-SPE 0.175 21-01-2025 View Document
40 ROAD-SPE 0.175 21-01-2025 View Document
41 STROM WATER-SPE 0.175 21-01-2025 View Document
42 APPROVAL LETTER & ESTIMATES-SPE 0.175 21-01-2025 View Document
43 FINAL ESTIMATE BOOLKET-SPE 0.175 21-01-2025 View Document