01-Apr-2024 |
Sh.
Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about
the facts of the project.
Sh.
Deepak Sharma (AR) and Sh. Pratik Gautam (AR) are present on behalf of the
promoter.
The
AR of the promoter states that standard design in respect of the SCO site stand
approved by DTCP and also states that the approval of building plans in respect
of individual SCO plots has also been obtained from DTP and the same is being
submitted in the authority today. Therefore, the AR of the promoter request for
consideration of application for registration of commercial plotted colony with
built up commercial floors/shops on commercial plots as there are only two SCO
plots over which 10 commercial floors/shops will be constructed.
In
view of the above, the authority decides to grant the registration of the
project for commercial plotted colony with built up commercial floors/shops as
per approved building plans by concerned authority. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
18-Mar-2024 |
Sh.
Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about
the facts of the project.
Sh. Deepak Sharma (AR) and Sh. Akash Gupta (AR) are present on behalf of
the promoter.
The
AR of the promoter states that the requisite NOC from the financial institution
i.e. M/s Piramal Trusteeship Pvt. Ltd. regarding creation of 3rd
party rights have been obtained and are submitted today along with other
deficit documents. The AR also states that standard design in respect of the
SCO site stand approved by DTCP and request for consideration of application
for registration of commercial floors/shops on commercial plots as per standard
design approval.
In
view of the above, the promoter is directed to submit the approval of building
plans in respect of individual SCO plots before consideration of application
for registration of commercial floors/shops on commercial plots.
The
matter to come up on 01.04.2024. |
ADJOURNMENT |
View Order |
11-Mar-2024 |
Sh. Sumeet,
Engineering Officer and Ms. Suruchi Pandey, Chartered Accountant briefed about
the facts of the project.
Sh. Deepak Sharma
(AR) and Sh. Akash Gupta (AR) are present on behalf of the promoter.
The AR of the
promoter states that reply to the deficiencies pointed out by the authority will
be submitted within two days.
The matter is
adjourned and to come up on 18.03.2024. |
EXAMINATION BY AUTHORITY |
View Order |