Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
Green Valley 2 Revenue Estate of Village Sohna, Sector-6, Gururgram GURUGRAM Sohna LION INFRADEVELOPERS LLP
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/805/537/2024/32 DATED 01.04.2024 RERA-GRG-1513-2023 08-Jan-2024 06-Jan-2024 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 01-Feb-2024 HARERA/GGM/RPIN/697 DISPATCHED
First hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/805/537/2024/32 DATED 01.04.2024 03-Jun-2024 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
01-Apr-2024 Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Brijender Singh Lohia (Promoter), Sh. Jatin Lohia (Promoter), Ms. Simran Ved (AR) Sh. Kush Kumar (AR) are present. Approved as proposed subject to submission of 25 lakhs BG/DD for obtaining the requisite access permission and including land diversion within road berm from the competent authority in a time period of 4 months failing which the BG/DD is liable to be forfeited besides legal consequences.  The necessary corrections in form A to H and DPI shall be made.  APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS ---
18-Mar-2024 Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Om Prakash Singh (Advocate), Sh. Jatin Lohia (Promoter) and Sh. Bijender Singh Lohia (Promoters) are present. The promoter seeks one week time for submission of approval of PWD authority for road access permission and diversion of forest land falling within PWD road berm. The matter to come up on 01.04.2024. ADJOURNMENT ---
11-Mar-2024 Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Vinay Shukla (Advocate), Ms. Simran Ved (Architect) and Sh. Kush Kumar (AR) are present on behalf of the promoter. The AR of the promoter states that the pending deficiencies will be submitted. The matter to come up on 18.03.2024.  ADJOURNMENT ---
04-Mar-2024 Ms. Deepika (Planning Executive) briefed about the facts of the case. Sh. Vinay Shukla (AR), Sh. Subham Tyagi (AR), Ms. Simran Ved (AR) and Sh. Sunil Kumar Singh (Accounts Head) are present on behalf of the promoter. The AR is submitting the deficit documents today. Office to examine the same. The matter to come up on 11.03.2024.  ADJOURNMENT ---
29-Jan-2024 Ar. Neeraj Gautam (Associate Architectural Executive) and Sh. M. L. Sardana (Accountant) briefed about the facts of the case. The application submitted by the promoter has been scrutinized by the concerned official, but the deficiency notice has not been dispatched till date. Therefore, in view of the same the matter is adjourned, and the concerned official is directed to dispatch the notice. The next date of hearing will be conveyed after submission of reply of deficiencies. EXAMINATION BY AUTHORITY ---