HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1513-2023
Submission Date : 06-01-2024 03:16:31 PM
Applicant Type : Firm
Project Type: NEW


LION INFRADEVELOPERS LLP
LION INFRADEVELOPERS LLP, SECOND FLOOR,TOWER B, UNIT NO TSF-01 TO TSF 08, OCUS TECHNOPOLIES, GOLF COURSE ROAD, SECTOR-54, GURGAON, HARYANA, 122002
01244047134
9311487848 (Number Shared by Promoter in Public)
legal@lioninfra.com
AAC1940
AAFFL2924B













GREEN VALLEY 2
REVENUE ESTATE OF VILLAGE SOHNA, SECTOR-6, GURURGRAM
SOHNA
GURUGRAM
01244047134
9311487848 (Number Shared by Promoter in Public)
legal@lioninfra.com
JAI PRAKASH
9144491444
7428396627 (Number Shared by Promoter in Public)
mep@lionininfra.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
134615402-01-20241000KOTAK MAHINDRA BANKHRERA Gurugram
236415502-01-20241115454KOTAK MAHINDRA BANKHRERA Gurugram







12.5 (Acre)
N/A
0
12.5 (Acre)
188 of 2023
No
Address     PLOT NO. 10, 3RD FLOOR, LOCAL SHOPPING COMPLEX, B-1, VASANT KUNJ, DELHI-110070
Address     VILLAGE DAMDAMA, TEHSIL SOHNA, GURGAON
Address     FRAM-55, RAOD-2, SILVER OAK MARG, GHITORNI, GADAIPUR, SOUTH DELHI-110030
Address     FARM NO. 30, SILVER OAK FARM, GHITORNI, NEW DELHI- 110030
Annexure-B- COLLABORATOR (ANNEXURE-B)
AGREEMENTS WERE MADE BEFORE THE GRANT OF LICENSE
Yes
LION INFRADEVELOPERS LLP(COLLABORATOR/DEVELOPER) HAS ENTERED INTO COLLABORATION AGREEMENT WITH NITIKA PROPMART PVT. LTD, SMT. SUKHPALLI W/O SH. SATBIR SINGH, SH. JATIN LOHIA S /O SH. RAVINDER SINGH LOHIA, SH. M.R. LOHIA S /O SH. PHOOL SINGH LOHIA AND SMT. SATYAWATI W /O SH. M.R. LOHIA FOR THE PURPOSE OF DEVELOPING A RESIDENT PLOTTED COLONY IN THE REVENUE ESTATE OF VILLAGE SOHNA, SECTOR - 6, SOHNA, DIST. GURUGRAM. ALL THE AGREEMENTS ARE REGISTERED WITH THE CONCERNED REVENUE DEPARTMENT. THE IMPORTANT CLAUSES OF THE SAID COLLABORATION AGREEMENTS ARE: 1. COLLABORATION AGREEMENT OF LION INFRADEVELOPERS WITH NITIKA PROPMART PRIVATE LIMITED AND JATIN LOHIA - CLAUSE NO. 1,2 AND 10. 2. COLLABORATION AGREEMENT OF LION INFRADEVELOPERS LLP WITH M.R LOHIA - 1,2 AND 10 3. ASSIGNMENT AGREEMENT OF LIONINFRADEVELOPERS LLP WITH SUKHPALI (CONFIRMING PARTY) AND NITIKA PROPMART PRIVATE LIMITED- CLAUSE NO. 2,3,5 AND 8
No
Yes
Yes







9008.25 Lakhs
3395.93 Lakhs
0 Lakhs
1120.20 Lakhs
4492.12 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD6.819
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS2.7562
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0.9490
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0.1142
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.1112
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES1.2504
12ANY OTHER0.50
Total12.5




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSPWD-APPLIEDNo
WATER SUPPLYHSVPYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEHSVPYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS253.52SUBMITTED TO HUDA
2WATER SUPPLY SYSTEM236.27SUBMITTED TO HUDA
3STORM WATER DRAINAGE98.90SUBMITTED TO HUDA
4ELECTRICITY SUPPLY SYSTEM0SUBMITTED TO HUDA
5SEWAGE TREATMENT & GARBAGE DISPOSAL158.94SUBMITTED TO HUDA
6STREET LIGHTING47.96SUBMITTED TO HUDA
7SECURITY AND FIRE FIGHTING0AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS10.37SUBMITTED TO HUDA
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER314.24SUBMITTED TO HUDA


15-09-2023 (date)
NA (date)
01-04-2024
31-03-2028
Plot Area(In Square Meter)Number of plots in the project
129.75155
10557
125.251
135.751
119.218
142.202


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots607.38

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments000
Shops000
Plots251.41173.16173.16

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots299.06173.16299.06173.16

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots922.27173.16299.061115.00

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots299.06173.161123.09346.31

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments00
Shops00
Plots2407.620




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements12.6812.6812.68
Water Supply System11.8111.8111.81
Sewerage treatment & garbage disposal7.957.957.95
Electricity Supply System2.402.402.40
Storm Water Drainage4.954.954.95
Parks and Playgrounds0.520.520.52
Clubhouse/community centres000
Shopping area000
Other000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements12.6812.6812.6812.68
Water Supply System11.8111.8111.8111.81
Sewerage treatment & garbage disposal7.957.957.957.95
Electricity Supply System2.402.402.402.40
Storm Water Drainage4.954.954.954.95
Parks and Playgrounds0.520.520.520.52
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements12.6812.6812.6812.68
Water Supply System11.8111.8111.8111.81
Sewerage treatment & garbage disposal7.957.957.957.95
Electricity Supply System2.402.402.402.40
Storm Water Drainage4.954.954.954.95
Parks and Playgrounds0.520.520.520.52
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements12.6812.6812.6825.35
Water Supply System11.8111.8111.8123.63
Sewerage treatment & garbage disposal7.957.957.9515.89
Electricity Supply System2.402.402.404.80
Storm Water Drainage4.954.9540959.89
Parks and Playgrounds0.520.520.521.04
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements50.700
Water Supply System47.250
Sewerage treatment & garbage disposal31.790
Electricity Supply System9.590
Storm Water Drainage19.780
Parks and Playgrounds2.070
Clubhouse/community centres00
Shopping area00
Other00
Maintainance of Road267.100












Yes
Yes
KOTAK MAHINDRA BANK LTD., G-1 AND G-2, ATM-1, VIPUL PLAZA, SUNCITY, SECTOR 54, GURGAON-122002
4449307010
KKBK0004265
110485125
004265
Mr. Jatin Lohia, (Designated Partner) Farm No. 30, Silver Oak Farms, Ghitorni, Delhi-110030
Attached











Yes
Yes
Yes
No
No
No
No
No
No
No


Yes
Yes
Yes
Yes
Yes
No
Yes
No
Statutory Approvals Statutory Approvals StatusDate
I. SERVICE PLAN ESTIMATESALREADY BEEN OBTAINED02-02-2024
II. POWER LINE SHIFTING NOCALREADY BEEN OBTAINED20-06-2023
III. LICENSE FROM DTCPALREADY BEEN OBTAINED15-09-2023
IV. ZONING PLAN APPROVALALREADY BEEN OBTAINED08-12-2023
V. LOIALREADY BEEN OBTAINED04-07-2023
VI. LC-IVALREADY BEEN OBTAINED15-09-2023
VII. FOREST NOCALREADY BEEN OBTAINED27-07-2023
VIII. ELECTRICAL LOAD ASSURANCEALREADY BEEN OBTAINED03-11-2023
IX. SEWERAGE ASSURANCEALREADY BEEN OBTAINED30-11-2023
X. DRINKING WATER ASSURANCEALREADY BEEN OBTAINED30-11-2023
XI. STORM WATER ASSURANCEALREADY BEEN OBTAINED05-03-2024
XII. CONSTRUCTION WATER ASSURANCEALREADY BEEN OBTAINED07-03-2024








Yes


Yes









GREEN VALLEY, SEC 35, SOHNA, GURUGRAM, HARYANA
12.41875
0
208
0
51
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
5318.1903035.57
Cost of the apartments000
Cost of the infrastructure1048.710808.90
Others costs2207.480973.71


8988.94 Lakhs
28.70 Lakhs
0 Lakhs
0 Lakhs
No
19-02-2024
26-06-2023










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD29-12-2023 View Document
2TREE CUTTING AFFIDAVIT03-01-2024 ------
3COPY OF LICENSE ALONG WITH SCHEDULE OF LAND29-12-2023 View Document
4DEMARCATION PLAN05-01-2024 View Document
5SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN29-12-2023 View Document
6CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT29-12-2023 View Document
7IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN30-12-2023 View Document
8A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS30-12-2023 View Document
9SEWAGE ASSURANCE06-01-2024 ------
10ZONING PLAN05-01-2024 View Document
11DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.03-01-2024 View Document
12BANK DECLARATION03-01-2024 ------
13DRINKING WATER ASSURANCE06-01-2024 ------
14FINANCIALS06-01-2024 ------
15ESTIMATE 11KV LINE APPROVED27-05-2024 ------
16APPROVED DEMARCATION_ZONING LETTER_08.12.202327-05-2024 ------
17APPROVED PLOTTED ZONING _12.50 ACRS28-05-2024 ------
18MUTATION28-05-2024 ------
19GPA_NITIKA TO LID_27.03.202328-05-2024 ------
20SPE_APPROVED LETTER_02.02.2024-SUPPERSEED28-05-2024 ------
21COLLABORATION AGREEMENT 127-05-2024 ------
22GPA DATED 15.03.202327-05-2024 ------
23SPA DATED 15.03.202328-05-2024 ------
24ARAVALLI NOC27-05-2024 ------
25SALE DEED-VASIKA NO. 7352 DATED 17.02.202028-05-2024 ------
26COLLABORATION AGREEMENT -228-05-2024 ------
27COLLABORATION NITIKA+SUKHPALI_201328-05-2024 ------
28APPROVED ASSURANCE OF CONSTRUCTION WATER_07.03.202427-05-2024 ------
29ASSURANCE OF STORM WATER_ 06 SOHNA_05.03.202427-05-2024 ------
30DRINKING WATER ASSURANCE_06 SOHNA27-05-2024 ------
31ELECTRICAL LOAD ASSURENCE_SEC-06 SOHNA27-05-2024 ------
32SEWERAGE ASSURANCE_06 SOHNA27-05-2024 ------
33APPROVED BLOCK DEMARCATION_12.50 ACRS28-05-2024 ------
34APPROVED DEMARCATION_ZONING LETTER28-05-2024 ------
35COLLABORATION AGREEMENT -128-05-2024 ------
36GPA28-05-2024 ------
37SPA_NITIKA TO LID_27.03.202328-05-2024 ------
38GPA_201328-05-2024 ------
39SPA DEED_SUKHPALI TO LID28-05-2024 ------
40DRO NOC28-05-2024 ------
41FOREST NOC28-05-2024 ------
42IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN28-05-2024 View Document
43AKSH SHIJRA28-05-2024 ------
44JAMABANDI28-05-2024 ------
45LC-IV28-05-2024 ------
46LOI28-05-2024 ------
47SALE DEED-VASIKA NO. 962 DATED 02.06.201028-05-2024 ------
48SALE DEED-VASIKA NO. 2547 DATED 22.03.200428-05-2024 ------
49SALE DEED-VASIKA NO. 7351 DATED 17.02.202028-05-2024 ------
50NON ENCUMBRANCE CERTIFICATE28-05-2024 ------
51ROAD ACCESS28-05-2024 ------
52PROJECT LOCATION ON FDP28-05-2024 ------
53SPE_FLUSHING-IRRIGATION28-05-2024 ------
54SPE_ROADS28-05-2024 ------
55SPE_SEWER LINE28-05-2024 ------
56SPE_STORM WATER LINE28-05-2024 ------
57SPE_WATER SUPPLY28-05-2024 ------
58TITLE SEARCH REPORT28-05-2024 ------
59APPROVED DEMARCATION_ZONING LETTER_08.12.202328-05-2024 ------
60BR FOR AUTHORISING BANK AC OPERATIONS30-05-2024 ------
61SPE_APPROVED LETTER_02.02.202428-05-2024 ------
62APPROVED COMMERCIAL ZONING_0.50 ACRS28-05-2024 ------
63CASH FLOW STATEMENT OF THE PROPOSED PROJECT30-05-2024 View Document
64PROJECT REPORT30-05-2024 ------
65NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT30-05-2024 View Document
66PERT CHART/PROGRESS REPORT30-05-2024 ------