04-Mar-2024 |
Sh.
Ashish Kush, Planning Executive briefed about the facts of the case.
Sh.
Abhijit Joshi (AR), Ms. Preeti Bhandari (AR) and Sh. Jatin (Legal Executive)
are present on behalf of the promoter.
The
promoter has submitted two BG vide no. 0037NDDG00065324 dated 23.02.2024 and
0037NDDG00065424 dated 23.02.2024 amounting to Rs. 25 lakh each as a
security amount for submission of revised approval of service plans and
estimates and revised fire scheme approval within three months as the requisite
changes (minor in nature) have made with the prior consent of more than 2/3rd
allottees. The approval of service plan & estimates and Fire Scheme already
stands obtained in respect of earlier plans and revisions have been
necessitated due to minor changes in structure & design as per table placed
in file.
The
AR of the promoter states that a public notice to this effect is published in 5
prominent newspapers on 09.12.2023 and confirmed by DTCP vide letter no. ZP-716-/PA(DK)/2024/5030
dated 09.02.2024 that there was no objection received regarding the same.
Further, the application is made 3 months back only. Hence, the Authority may
exempt from re-publication of notice. Further, it is noted that DTCP has
approved the above plans in pursuance to policy after submission of required
documents.
In
view of above, the Authority decides in-principally to grant registration
subject to issuance of one week public notice in two newspapers (1 English and
1 Hindi) to inform about approval of above revised plan and invite objections towards
the consent submitted by the promoter, if any. If no objection is received
within a week, the registration certificate shall be issued as proposed above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |