07-Feb-2024 |
Sh. Ashish Kush, Planning Executive
briefed about the facts of the case.
Sh. Sanjay Gupta (AR) and Sh.
Akshat Gupta (AR) are present on behalf of the promoter.
The AR of the promoter states that
the mining permission will be obtained before starting excavation work and
access to the project is from HSVP internal road and prior road access
permission is required if the access is from sector road. So far, as the issue regarding
the irrevocable clause in the Collaboration agreement, it was stated by the AR
that in terms of Clause 3(b) of the Collaboration agreement, an irrevocable GPA
has been signed simultaneously with the Collaboration agreement and As per Para
22 of GPA it has been clearly stated that the said that “the present Power of
Attorney is irrevocable and the Executant shall ratify all acts, deeds, and
things done in pursuance of the General Power of Attorney including the
appointment of further Attorney(s)” and in respect of Land title search report,
it is submitted by the AR of the promoter that no further Jamabandi after
1996-1997 have been generated. Further, DTCP has granted the license after
ascertaining the title of land as well as the collaboration agreement and GPA
alongwith other requisite approvals. Further, minor correction in allottees
related draft documents will be done within two days.
Approved as proposed.
The registration certificate shall
be issued after the submission of above deficiencies. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
05-Feb-2024 |
The matter is adjourned to 07.02.2024 at 03:30 PM. |
ADJOURNMENT |
View Order |
22-Jan-2024 |
Sh. Shashank Sharma, Associate Engineer
Executive and Mr. M.L Sardana,
Accountant briefed about the facts of the case.
Sh. Akshat Gupta
(AR), Sh. Deepak Gupta (AR) and Sh. Sanjay Gupta (AR) are present on behalf of
the promoter.
The AR of the
promoter seeks two weeks to submit the deficit documents. Request is allowed.
The matter to
come up on 05.02.2024 |
ADJOURNMENT |
View Order |
08-Jan-2024 |
Sh. Ashish Kush, Planning
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
case.
Sh. Akshat Gupta (AR) Sh.
Tushar Bahmani (AR) are present on behalf of the promoter.
The AR of the promoter requests
for two weeks’ time to submit the deficit documents. The request is allowed.
The matter to come up on
22.01.2024. |
ADJOURNMENT |
View Order |
11-Sep-2023 |
Sh. Ashish Kush, Planning
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
case.
No reply has been submitted by the
promoter company till 06.09.2023 against the deficiencies conveyed by the
authority through notice dated 06.09.2023. Therefore, in view of the same the
matter is adjourned, and the next date of hearing will be conveyed after
submission of reply of deficiencies already conveyed.
Further, if no response is received
from the promoter within next 4 week’s time, in that case the concerned
official to put up the matter on file for issuance of show cause notice as to
why their application for registration of project may not be rejected following
the due procedure under the Act of 2016. |
EXAMINATION BY AUTHORITY |
View Order |