Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
SAPPHIRE RESIDENCES Sector 15 Part 2 GURUGRAM Gurgaon Summit Terracraft Pvt. Ltd
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/784/516/2024/11 DATED 07.02.2024 RERA-GRG-1433-2023 25-Aug-2023 23-Aug-2023 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 06-Sep-2023 BY HAND AND THROUGH MAIL BY HAND AND THROUGH MAIL
First hearing fixed View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/784/516/2024/11 DATED 07.02.2024 12-Jun-2024 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
07-Feb-2024 Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Sanjay Gupta (AR) and Sh. Akshat Gupta (AR) are present on behalf of the promoter. The AR of the promoter states that the mining permission will be obtained before starting excavation work and access to the project is from HSVP internal road and prior road access permission is required if the access is from sector road. So far, as the issue regarding the irrevocable clause in the Collaboration agreement, it was stated by the AR that in terms of Clause 3(b) of the Collaboration agreement, an irrevocable GPA has been signed simultaneously with the Collaboration agreement and As per Para 22 of GPA it has been clearly stated that the said that “the present Power of Attorney is irrevocable and the Executant shall ratify all acts, deeds, and things done in pursuance of the General Power of Attorney including the appointment of further Attorney(s)” and in respect of Land title search report, it is submitted by the AR of the promoter that no further Jamabandi after 1996-1997 have been generated. Further, DTCP has granted the license after ascertaining the title of land as well as the collaboration agreement and GPA alongwith other requisite approvals. Further, minor correction in allottees related draft documents will be done within two days. Approved as proposed. The registration certificate shall be issued after the submission of above deficiencies. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
05-Feb-2024 The matter is adjourned to 07.02.2024 at 03:30 PM. ADJOURNMENT View Order
22-Jan-2024 Sh. Shashank Sharma, Associate Engineer Executive and Mr. M.L Sardana, Accountant briefed about the facts of the case. Sh. Akshat Gupta (AR), Sh. Deepak Gupta (AR) and Sh. Sanjay Gupta (AR) are present on behalf of the promoter. The AR of the promoter seeks two weeks to submit the deficit documents. Request is allowed. The matter to come up on 05.02.2024 ADJOURNMENT View Order
08-Jan-2024 Sh. Ashish Kush, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Akshat Gupta (AR) Sh. Tushar Bahmani (AR) are present on behalf of the promoter. The AR of the promoter requests for two weeks’ time to submit the deficit documents.  The request is allowed. The matter to come up on 22.01.2024. ADJOURNMENT View Order
11-Sep-2023 Sh. Ashish Kush, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. No reply has been submitted by the promoter company till 06.09.2023 against the deficiencies conveyed by the authority through notice dated 06.09.2023. Therefore, in view of the same the matter is adjourned, and the next date of hearing will be conveyed after submission of reply of deficiencies already conveyed. Further, if no response is received from the promoter within next 4 week’s time, in that case the concerned official to put up the matter on file for issuance of show cause notice as to why their application for registration of project may not be rejected following the due procedure under the Act of 2016. EXAMINATION BY AUTHORITY View Order