HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1433-2023
Submission Date : 23-08-2023 06:16:14 PM
Applicant Type : Company
Project Type: NEW




SUMMIT TERRACRAFT PVT. LTD
AMEYA ONE, GOLF COURSE ROAD, DLF CITY PHASE - V, SECTOR - 42, GURUGRAM. 122002
01242571477
9910160554 (Number Shared by Promoter in Public)
contact@summitterracraft.in
Https://abcxyz.in/
XXXX289G
U45309DL2017PTC310415
 
 


 
 


 
 


 
 







SAPPHIRE RESIDENCES
SECTOR 15 PART 2
GURGAON
GURUGRAM
01242571477
9958429537 (Number Shared by Promoter in Public)
contact@summtterracraft.in
AMIT
01242571477
9958429537 (Number Shared by Promoter in Public)
contact@summtterracraft.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
115623624-08-2023470500BANK OF BARODAHRERA Gurugram
215633905-01-202447856BANK OF BARODAHRERA Gurugram







2.44687 (Acre)
1.84
1.84
2.44687 (Acre)
Licence No. 77 of 2023 dated 10.04.2023
No
Address     GURUGRAM
Address     GURUGRAM
Address     GURUGRAM
Address     GURUGRAM
Address     GURUGRAM
Annexure-B- COLLABORATOR
BEFORE GRANT OF LICENCE
Yes
COLLABORATION AGREEMENT (ATTACHED)
No
Yes
Yes







11309.04 Lakhs
510.0 Lakhs
7648.77 Lakhs
572.71 Lakhs
2577.56 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0.8190
3CONSTRUCTION OF ROADS0.5785
4PAVEMENTS0.410
5PARKS AND PLAYGROUNDS0.3838
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
13COMMUNITYCENTRE0.2552
Total2.4465




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSNHAINo
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS57.54AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM211.10AS PER PROJECT REPORT
3STORM WATER DRAINAGE19.31AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM0YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL37.05AS PER PROJECT REPORT
6STREET LIGHTING3.76AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS3.81AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15MAINTENANCE CHARGES40.14AS PER PROJECT REPORT


05-12-2023 (date)
05-12-2023 (date)
01-04-2024
30-04-2029
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings116.124581
Apartment/Shops/Other Buildings117.395581
Apartment/Shops/Other Buildings18.63211





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments439.80439.80439.80439.80
Shops0000
Plots0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments439.80439.80439.80439.80
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments420.68420.68420.68420.68
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments286.83286.83286.83286.83
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments286.83286.83286.83286.83
Shops0000
Plots0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments152.98
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements2.882.882.88
Water Supply System11.1111.1111.11
Sewerage treatment & garbage disposal1.951.951.95
Electricity Supply System000
Storm Water Drainage1.021.021.02
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements2.882.882.882.88
Water Supply System11.1111.1111.1111.11
Sewerage treatment & garbage disposal1.951.951.951.95
Electricity Supply System0000
Storm Water Drainage1.021.021.021.02
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements2.882.882.882.88
Water Supply System11.1111.1111.1111.11
Sewerage treatment & garbage disposal1.951.951.951.95
Electricity Supply System0000
Storm Water Drainage1.021.021.021.02
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Street Lighting0.750.750.750.75

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements2.882.882.882.88
Water Supply System11.1111.1111.1111.11
Sewerage treatment & garbage disposal1.951.951.951.95
Electricity Supply System0000
Storm Water Drainage1.021.021.021.02
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Street Lighting0.76

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements2.882.882.882.88
Water Supply System11.1111.1111.1111.12
Sewerage treatment & garbage disposal1.951.951.951.95
Electricity Supply System0000
Storm Water Drainage1.021.021.020.95
Parks and Playgrounds0.950.950.950.96
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements2.82
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0












Yes
No
STATE BANK OF INDIA. MCB GURGAON, PLOT NO. 91, IDC, 1ST FLOOR, MG ROAD. GURUGRAM, HARYANA. 122001
42382950385
SBIN0050933
110002777
SBIN00050933
Akshat Gupta, #Ameya One, Golf course road, DLF City, Phase-V, Sector-42, Gurugram
Yes











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENCE NO. 77 OF 2023ALREADY BEEN OBTAINED10-04-2023
II. ZONINGALREADY BEEN OBTAINED11-04-2023
III. BUILDING PLANALREADY BEEN OBTAINED05-12-2023
IV. ECALREADY BEEN OBTAINED29-08-2023








Yes


Yes


As per RERA norms













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEIMPORTED MARBLE / VETRIFIED TILE
2WALL FINISHING DETAILSPANT / CLADD ING / PANELLING
3KITCHEN DETAILSTILES
4BATHROOM FITTINGSSTAINLESS STEEL
5WOOD WORK ETCSEASON/AL HARDWOOD FRAMES
6DOORS AND WINDOS FRAMESSEASON/AL HARDWOOD FRAMES & VEENER FINISH SHUTTER
7GLASS WORK6MM TOUGHENED GLASS
8ELECTRIC FITTINGSBECPALT / POLYCAB OR EQUIVALENT
9CONDUCTING AND WIRING DETAILSBECPALT / POLYCAB OR EQUIVALENT
10CUPBOARD DETAILSN/A
11WATER STORAGEOHT/ UGT
12LIFT DETAILSJOHNSON CONTROL OR EQUIVALENT
13EXTERNAL GLAZINGSVEENER FINISH LAQURED POLISH
13.1WINDOWS/GLAZINGSALUMINIUM WITH 6MM TOUGHENED GLASS
14DOORSVEENER FINISH LAQURED POLISH
14.1MAIN DOORSVEENER FINISH LAQURED POLISH
14.2INTERNAL DOORSVEENER/ LAMINATED DOOR
15AIR CONDITIONINGN/A
16ELECTRICAL FITTINGSPHILIPS OR EQUIVALENT
17CNG PIPE LINEPROVISION
18PROVISION OF WIFI AND BROADBAND FACILITYPROVIDED
19EXTERNAL FINISHING/COLOUR SCHEMEPAINT
20INTERNAL FINISHINGPAINT / CLADDING / PANELLING
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORIMPORTED MARBLE / VETRIFIED TILE
1 . 2 WALLSPLASTIC EMULSION
1 . 3 CEILINGOIL BOND DISTEMPER
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOORING
2 . 2 WALLSPLASTIC EMULSION
2 . 3 CEILINGOIL BOND DISTEMPER
2 . 4 MODULAR WARDROBESPLY / WOODEN
3 . MASTER TOILET
3 . 1 FLOORANTI SKID TILES
3 . 2 WALLSCERAMIC TILES
3 . 3 CEILINGOIL BOND DISTEMPER
3 . 4 COUNTERSPAINTED SHUTTER
3 . 5 SANITARY WARE/CP FITTINGSSTAINLESS STEEL
3 . 6 FITTING/FIXTURES1
4 . BED ROOMS
4 . 1 FLOORLAMINATED WOODEN FLOORING
4 . 2 WALLSPLASTIC EMULSION
4 . 3 CEILINGOIL BOND DISTEMPER
4 . 4 WARDROBESPLY / WOODEN
5 . TOILET
5 . 1 FLOORANTI SKID TILES
5 . 2 WALLSCERAMIC TILES
5 . 3 CEILINGOIL BOND DISTEMPER
5 . 4 COUNTERSPAINTED SHUTTER
5 . 5 SANITARY WARE/CP FITTINGSYES
5 . 6 FIXTURESYES
6 . KITCHEN
6 . 1 FLOORANTI SKID TILES
6 . 2 WALLSCERAMIC TILES/ PAINT
6 . 3 CEILINGOIL BOND DISTEMPER
6 . 4 COUNTERSYES
6 . 5 FIXTURESYES
6 . 6 KITCHEN APPLIANCESN/A
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORTILES
7 . 2 WALLS & CEILINGOIL BOND DISTEMPER
7 . 3 TOILETOIL BOND DISTEMPER
7 . 4 BALCONYOIL BOND DISTEMPER
8 . SIT-OUTS
8 . 1 FLOORTILES
8 . 2 WALLS & CEILINGOIL BOND DISTEMPER
8 . 3 RAILINGSIRON PAINTED
8 . 4 FIXTURESYES












Sr. No.Document DescriptionDate of Document UploadView Document
1COPY OF LICENSE ALONG WITH SCHEDULE OF LAND23-08-2023 View Document
2ASSURANCE FOR SEWER CONNECTION09-02-2024 ------
3ELEVATION TOWER -209-02-2024 ------
4STILT PARKING LEVEL 3 WITH AREA DETAILS09-02-2024 ------
5COMMUNITY BUILDING09-02-2024 ------
6LC-V09-02-2024 ------
7DEMARCATION PLAN09-02-2024 View Document
8DHBVN ASSURANCE09-02-2024 ------
9ASSURANCE OF SUPPLY OF POTABLE WATER09-02-2024 ------
10SECTIONS TOWER-109-02-2024 ------
11COLLABORATION AGREEMENT & GPA09-02-2024 ------
12FLOOR PLAN WITH AREA DETAIL TOWER -209-02-2024 ------
13ASSURANCE STP TREATED WATER FOR CONSTRUCTION09-02-2024 ------
14FIRE SCHEME APPROVAL09-02-2024 ------
15DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.09-02-2024 View Document
16DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD09-02-2024 View Document
17REVENUE DOCUMENTS09-02-2024 ------
18UPPER & TERRACE FLOOR PLAN WITH AREA CALC TOWER -109-02-2024 ------
19UPPER & TERRACE WITH AREA DETAILS TOWER -209-02-2024 ------
20IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN09-02-2024 View Document
21NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT16-02-2024 View Document
22ALL LEVEL PLAN ELEVATION SECTIONS WITH AREA DETAILS(EWS)09-02-2024 ------
23LC-IV & IV-A09-02-2024 ------
24LOI09-02-2024 ------
25PARKING LEVEL-1 WITH DETAILS09-02-2024 ------
26SITE PLAN & AREA CALCULATION09-02-2024 ------
27AFFIDAVIT 42LD09-02-2024 ------
28BR III09-02-2024 ------
29ROAD LAYOUT09-02-2024 ------
30SECTIONS TOWER-209-02-2024 ------
31AIRPORT HEIGHT CLEARANCE NOC09-02-2024 ------
32ASSURANCE DRINKING WATER09-02-2024 ------
33ASSURANCE FOR STORM WATER DRAINAGE09-02-2024 ------
34DRAINAGE LAYOUT09-02-2024 ------
35ELEVATIONS TOWER-109-02-2024 ------
36ENVIRONMENT CLEARANCE09-02-2024 ------
37FOREST NOC09-02-2024 ------
38GREEN AREA & OPEN PARKING AREA DETAIL09-02-2024 ------
39NON ENCUMBRANCE CERTIFICATE09-02-2024 ------
40SEWERAGE LAYOUT09-02-2024 ------
41SITE PLAN WITH MORGAGE AREA DETAILS09-02-2024 ------
42SITE PLAN WITH SERVICES09-02-2024 ------
43SPE APPROVAL LETTER09-02-2024 ------
44STILT PARKING LEVEL 2 WITH AREA DETAILS09-02-2024 ------
45TYPICAL & UPPER FLOOR PLAN WITH AREA CALC TOWER-109-02-2024 ------
46WATER SUPPLY LAYOUT09-02-2024 ------
47ZONING PLAN09-02-2024 View Document
48IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN09-02-2024 View Document