Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
---|---|---|---|---|
THE NATION | SECTOR 95, VILLAGE- WAZIRPUR | GURUGRAM | Harsaru ST | JMS Infra reality Pvt Ltd |
Project Registration Number | Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks | Details of Project(Form A-H) |
---|---|---|---|---|---|---|---|---|---|---|---|---|
GGM/745/477/2023/89 DATED 11.09.2023 | RERA-GRG-1389-2023 | 01-Jun-2023 | 01-Jun-2023 | APPROVED AND CERTIFICATE UPLOADED | NOT REQUIRED | Yes | 04-Jul-2023 | HARERA/GGM/RPIN/624 | DISPATCHED | First hearing | View Form(A-H) |
Project Registration Number | Uploading Date | Remarks | View Certificate |
---|---|---|---|
GGM/745/477/2023/89 DATED 11.09.2023 | 12-Jan-2024 | This registration certificate supersedes the earlier registration no. 36 of 2023 dated 02.02.2023 granted for the part of land of the present application. Now onwards QPRs shall be based on A-H information in REP-I for the whole project. |
Date of Hearing | Proceedings of the day | Status | Order |
---|---|---|---|
11-Sep-2023 | Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered Accountant) briefed about the facts of the case. Sh. Yudhveer Singh (AR) and Sh. Vipul Kumar Dahiya (AR) are present on the behalf of the promoter. Since, the layout plan and zoning plan of the project are revised pursuant to the grant of additional license by DTCP in view of the policy circulated by Government vide memo no. Misc-862/2023/7/1/2023-2TCP/11689-91 dated 24.04.2023. Moreover, the promoter has submitted the consent of 2/3rd allottees and in reference to public notice issued by the Authority, no objection is received. Therefore, the Authority decides to grant registration as proposed. The Registration Certificate be issue after submission of remaining documents. Further this is without prejudice to the rights of the present allottees under section 12, 14 and 18(1) of the Act which shall continue to be governed by the BBAs signed with individual allottees. | APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS | --- |
17-Jul-2023 | Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered Accountant) briefed about the facts of the case. Sh. Vipul Kumar Dahiya (AR) and Sh. Yudhveer Singh (AR) are present on the behalf of the promoter. The AR of the promoter applicant requested for time to comply with the deficiencies. The Authority granted two months’ time for compliance of the deficiencies which have already been pointed out failing which the application shall stand rejected. The matter to come up on 18.09.2023 | ADJOURNMENT | View Order |
26-Jun-2023 | Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Sanjeet Kumar and Sh. Vipul Kumar Dahiya are present on the behalf of the promoter. The deficiencies in the application, if any, be conveyed to the promoter. The matter to come up on 17.07.2023 | ADJOURNMENT | View Order |