10-Jul-2023 |
Ms. Deepika, Planning Executive and Mrs.
Asha, Chartered Accountant briefed about the facts of the project.
Sh. Himani Sharma (AR) is present on behalf
of the promoter.
As proposed, The
promoter shall submit BG/DD/Cheque amounting to Rs. 25 lakhs as a security
amount for submission of approved service plans and estimates within three
months. The Authority decided to grant the registration certificate subject to
submission of above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
03-Jul-2023 |
Proceedings dated: 03.07.2023
Ms. Deepika,
Planning Executive and Mrs. Asha, Chartered Accountant briefed about the facts
of the project.
Sh. Ashok Jaunapuria
(AR), Sh. Manoj Shukla (AR) and Sh. Himani Sharma (AR) are present on behalf of
the promoter. The AR submits that the approval of revised layout plan has been
granted by DGTCP on 25.02.2023 on the basis of policy instructions issued by
PSTCP Memo no. Misc-2295/2021/1775 dated 25/01/2021.
However, it is noticed that subsequent to the above directions, the ACS TCP has
issued a final policy guidelines vide memo no. Misc.
862/2023/7/1/2023-2tcp/11689-91 dated 24.04.2023 and
that it is to ascertain as to whether the case of promoter is covered in
3.2.1 (i) and (ii) as revision of layout plan has been necessitated due to
grant of additional license measuring 6.8468 acres bearing license no. 41 of
2023 dated 21.02.2023 and not requiring prior consent
of 2/3rd allottees or not ?
The AR to submit a copy of the layout plan duly
showing the changes made in the earlier approved layout plan in tabular form
duly marked in distinct colors, and the office to examine and put up separately
on the file vis a vis above policy provision of the government. In meanwhile
the applicant promoter to also rectify the remaining deficiencies
The matter to come up on 10.07.2023. |
ADJOURNMENT |
View Order |
19-Jun-2023 |
Ms. Deepika, Planning
Executive and Mrs. Asha, Chartered Accountant briefed about the facts of the
project.
Ms. Himani (AR) and Sh. Manoj Shukla (AR) are
present on behalf of the promoter. Reply submitted on 15.06.2023 which needs to
be examined by the authority. The
matter to come up on 03.07.2023. |
EXAMINATION BY AUTHORITY |
View Order |