MICROTEK SUCCESS HUB VILLAGE WAZIRPUR SECTOR 95-A GURUGRAM GURUGRAM Harsaru ST MICROTEK URBANDEVELOPERS PVT. LTD.
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/714/446/2023/58 DATED 08.05.2023 RERA-GRG-1295-2023 30-Jan-2023 29-Jan-2023 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 07-Feb-2023 Online/By hand Deficiency notice
First hearing fixed View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/714/446/2023/58 DATED 08.05.2023 22-Jun-2023 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
08-May-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Naveen Singla (CA) and Sh. Navin Jain (Advocate) are present on behalf of the promoter. Approved as proposed. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
01-May-2023 Due to administrative work, the matter is adjourned to 08.05.2023. ADJOURNMENT View Order
10-Apr-2023 Sh. Sumeet, Engineer Executive and Ms. Asha, Chartered Accountant briefed about the facts of the project. A request for adjournment has been received vide letter dated 06.04.2023. The matter to come up on 01.05.2023. ADJOURNMENT View Order
29-Mar-2023 Proceedings dated: 29.03.2023. Sh. Sumeet, Engineer Executive and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Naveen Singla (CA) is present on behalf of the promoter. The AR submits that additional and deficit documents have been submitted on 24.03.2023 and office to examine the same and to put up updated status. The AR further requests two weeks time for submission of approved architectural control sheet. The matter to come up on 10.04.2023.  ADJOURNMENT View Order
27-Mar-2023 The matter is adjourned to 29.03.2023. ADJOURNMENT View Order
27-Feb-2023 Sh. Sumeet, Engineer Executive and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Naveen Singla (CA)  is present on behalf of the promoter. The AR of the promoter seeks one months time to comply with the deficiencies pointed out . The matter to come up on 27.03.2023. ADJOURNMENT View Order
13-Feb-2023 Ms. Asha, Chartered Accountant briefed about the facts of the project. None is present on behalf of the promoter. The promoter is directed to rectify the deficiencies before the next date of hearing. The matter to come up on 27.02.2023. EXAMINATION BY AUTHORITY View Order