Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
SS STRADA SECTOR -84, GURUGRAM GURUGRAM Manesar SS GROUP PRIVATE LIMITED
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/717/449/2023/61 DATED 15.05.2023 RERA-GRG-1266-2023 02-Mar-2023 01-Mar-2023 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 16-Mar-2023 Online 1st deficiency notice
First hearing fixed View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/717/449/2023/61 DATED 15.05.2023 20-Jun-2023 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
15-May-2023 Sh. Sumeet, Engineering Officer and Ms. Asha Chartered Accountant briefed about the facts of the case. Ms. Himani (AR), Sh. Sunil Shekhawat (AR), Sh. Ashok Singh Jaunapuria (AR) and Sh. Manoj Shukla (AR) are present on behalf of the promoter. The authority decides to grant the registration of project “SS Strada” subject to submission of deficit fee Rs. 36,33,435/- for RC no. 65 of 2021 as per condition imposed at the time of issuance of registration certificate that the promoter shall pay deficit fee. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
01-May-2023 Due to administrative work, the matter is adjourned to 15.05.2023. ADJOURNMENT View Order
24-Apr-2023 Sh. Sumeet, Engineering Officer and Ms. Asha Chartered Accountant briefed about the facts of the case. Ms. Himani (AR) is present on behalf of the promoter.  It is observed that  the following compliances with respect to the conditional registration certificate issued for the land on which the present project is proposed to be built (RC No. – 65 of 2021 Project Name SS Linden) are pending: a)       Deposit of deficit fee b)       4(2)(l)(D) report of the year 2021-22 The applicant is directed to clarify the above issues within the next three days. Concerned Planning Executive to submit a clear report before the next date of hearing. The matter to come up on 01.05.2023. ADJOURNMENT View Order
17-Apr-2023 Ms. Asha Chartered Accountant briefed about the facts of the case. Ms. Himani (AR) is present on behalf of the promoter. The Authority directed the promoter to submit the pending QPR and 4(2)(l)(D). The matter to come up on 24.04.2023. ADJOURNMENT View Order
03-Apr-2023 Sh. Sumeet, Engineering Officer and Ms. Asha Chartered Accountant briefed about the facts of the case. Ms. Himani Sharma (AR) is present on behalf of the promoter and states that the reply with regard to the deficiencies already conveyed will be submitted within two days. The matter is adjourned and to come up on 17.04.2023. ADJOURNMENT View Order
20-Mar-2023 Sh. Sumeet, Engineering Officer and Ms. Asha Chartered Accountant briefed about the facts of the case. Ms. Himani (AR) is present on behalf of the promoter and submits that detailed reply along with deficit documents have been submitted today. The office to examine the same and to put before the next date of hearing. The matter to come up on 03.04.2023. EXAMINATION BY AUTHORITY View Order