Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
ORCHID IVY- 2 M-Block, Sector-51, Gurugram GURUGRAM Gurgaon M/s ORCHID INFRASTRUCTURE DEVELOPERS PVT. LTD.
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/646/378/2022/121 DATED 13.12.2022 RERA-GRG-1141-2022 08-Sep-2022 06-Sep-2022 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Not Yet -- First Hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/646/378/2022/121 DATED 13.12.2022 03-Jan-2023 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
21-Nov-2022 Approved as proposed. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
15-Nov-2022 Proceedings dated 15.11.2022 Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Dhruv Gupta (Managing Director) Sh. Ajay Goel (Director), Sh. Arun Nijhawan (Sr. VP) and Sh. Keshav Gupta (Legal Associate) are present on behalf of the promoter. The AR submits that after removing deficiencies, the requisite documents and DPI stands submitted in the Authority on 03.10.2022 but the concerned Planning Executive is not aware about the same who is directed to link up and put up the matter within three days along with details of any deficit document which still remains to be supplied.  The matter to come up on 21.11.2022.   (Sanjeev Kumar Arora) Member, HARERA, Gurugram   (Ashok Sangwan) Member, HARERA, Gurugram     (Vijay Kumar Goyal) Member, HARERA, Gurugram ADJOURNMENT View Order
14-Nov-2022 The matter is adjourned for 15.11.2022.  ADJOURNMENT View Order
12-Oct-2022 The matter was considered and it was decided to adjourned the same for 14.11.2022. Matter to come up on 14.11.2022. ADJOURNMENT View Order
10-Oct-2022 The matter is adjourned for 12.10.2022. OBJECTION ---
03-Oct-2022 Proceedings dated 03.10.2022 : Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed the facts of the case. Sh. Dhruv Gupta, Sh. Ajay Goel (Director), Sh. Arun Nijhawan (Director) and Sh. Keshav Gupta are present on behalf of the promoter. The legal capacity papers as have been submitted earlier needs to be perused by the Members. The matter to come up on 10.10.2022.       (Sanjeev Kumar Arora) Member, HARERA, Gurugram     (Ashok Sangwan) Member, HARERA, Gurugram       (Dr. K.K. Khandelwal) Chairman, HARERA, Gurugram EXAMINATION BY AUTHORITY View Order
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
04-Oct-2022 Proceedings dated 03.10.2022 : Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed the facts of the case. Sh. Dhruv Gupta, Sh. Ajay Goel (Director), Sh. Arun Nijhawan (Director) and Sh. Keshav Gupta are present on behalf of the promoter. The legal capacity papers as have been submitted earlier needs to be perused by the Members. The matter to come up on 10.10.2022.       (Sanjeev Kumar Arora) Member, HARERA, Gurugram     (Ashok Sangwan) Member, HARERA, Gurugram       (Dr. K.K. Khandelwal) Chairman, HARERA, Gurugram Not Yet