12-Sep-2022 |
Ar. Neeraj Gautam, Associate Architectural Executive
and Ms. Asha, Chartered Accountant briefed about the facts of the case.
Sh. Manish Kumar Gupta (SVP) and Sh. Nikhil Golni
(AGM) are present on the behalf of the promoter. The AR of the promoter is
directed to submit a CA certificate and an authenticated copy of report from
MCA site regarding transfer of shareholding and present status of shareholding of the promoter
and submission of DD amounting to Rs. 25 lakhs as a guarantee regarding
submission of approved service plans and estimates within a month subject to
which the Authority decides to grant registration. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |
05-Sep-2022 |
Ms. Neeraj Gautam, Architectural Executive and Ms.
Asha, Chartered Accountant briefed about the facts of the case.
Sh. Manish Kumar Gupta (VP), Sh. Nikhil Golani (AGM)
and Sh. Narendra Kumar (Manager) are present on the behalf of the promoter.
The approved copy of service plan estimates is yet to received
from DTCP although the same have been approved in principle and the promoter
applicant has made compliance of its conditions. Further the final BIP
permission has been granted by DTCP on 28.07.2022 and a copy of same already
stand submitted in the Authority. The issue of license still in the name of landowners
and an arrangement of sharing of revenue with the licensee land owners has been
made which is to be examined and that the licensee landowner is not an
applicant promoter in the application for registration.
The matter to come up on 12.09.2022. |
ADJOURNMENT |
--- |
17-Aug-2022 |
Proceedings dated 17.08.2022
Ms. Geeta Rathee Singh, Sr. Legal Officer and Ms.
Asha, Chartered Accountant briefed about the facts of the case.
Sh. Surender Kumar (RERA Officer) is present on the
behalf of the promoter and request for a short adjournment for submission of
deficient documents. The request is allowed.
The matter to come up on 05.09.2022. |
ADJOURNMENT |
--- |
08-Aug-2022 |
Proceedings dated 08.08.2022
Ar. Neeraj Gautam (Associate Architectural Executive)
briefed about the facts of the case.
Sh. Nikhil Gulani (AGM), Sh. Narender Kumar (Dy
Manager) and Sh. Nasim Ahmed (DGM Liaison) are present on the behalf of the
promoter.
The AR submits that internal approval of CE HSVP has
been granted and the promoter is in process of submission of BG required in
lieu of approval of service plan and estimates. The AR is advised to submit the
requisite BG with DTCP and to submit the receipt in the Authority.
The matter to come up on 17.08.2022. |
ADJOURNMENT |
--- |
27-Jul-2022 |
Ar. Neeraj Gautam (Associate Architectural Executive)
briefed the facts of the case.
None is present on behalf of the promoter.
The AR of the promoter submitted a request for
adjournment of hearing to 01.08.2022 in the Authority vide Dak ID 38517 dated
25.07.2022. ‘
The matter to come up on 08.08.2022. |
ADJOURNMENT |
--- |
25-Jul-2022 |
Due to administrative work of the Authority, the
matter could not be heard.
The hearing is adjourned to 27.07.2022 |
ADJOURNMENT |
--- |
18-Jul-2022 |
Proceedings dated 18.07.2022
Ar. Neeraj Gautam, Associate Architectural Executive,
briefed the facts of the case.
None is present on the behalf of the promoter.
The AR of the promoter has requested for an
adjournment of one week through e-mail dated 18.07.2022.
The matter to come up on 25.07.2022.Vijay Goyal (Member)KK Khandelwal (Chairman) |
ADJOURNMENT |
--- |
04-Jul-2022 |
Ar. Neeraj Gautam, Associate Architectural Executive,
briefed the facts of the case.
Sh. Nikhil Golani, Sh. Manish Gupta, Sh. Nasim Ahmed and Sh. Narender Kumar are present
on the behalf of the promoter.
The promoter has received the in- principle approval
for change in
beneficial interest from DTCP, Haryana
dated 03.06.2022 and the final approval is still awaited. The promoter has
submitted an affidavit in the Authority stating that they have submitted all
compliances to DTCP as mentioned in in-principle approval for BIP permission.
The applications for the approvals for service plans and estimates, non-
emcumbrance certificate and electrical load availability connection have been
made in the respective departments and the final approvals are yet to be
obtained.
The AR of the promoter is
directed to submit the deficit documents as listed above in the Authority
before the next date of hearing.
The matter to
come up on 18.07.2022 |
EXAMINATION BY AUTHORITY |
--- |