17-Aug-2022 |
Proceedings
dated: 17.08.2022
Ms.
Geeta Rathee Singh, Sr. Legal Officer and Ms. Prachi Singh, Planning Executive briefed
about the facts of the project.
Sh.
Anish Dham (AVP), Sh. Ketan Nanda (AVP) and Sh. Abhinav Saxena (DM) are present
on behalf of the promoter.
In
view of the above recommendations, the Authority decides to grant registration. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
08-Aug-2022 |
Proceedings dated: 08.08.2022Ar. Neeraj Gautam, Architectural Executive briefed about the facts of the project.Sh. Ketan Nanda (AVP), Sh. Anish Dham (AVP), Abhinav Saxena (DM), Sh. Tarun Yadav (DGM) Sh. KabirKapoor (GM) and Sh. Abhinav Sharwan (Manager) are present on behalf of the promoter.One week time is granted for checking of the documents submitted today in response to the deficienciesconveyed earlier.The matter to come up on 17.08.2022. |
ADJOURNMENT |
--- |
25-Jul-2022 |
Due to the administrative work of the authority, the matter is adjourned for 27.07.2022. |
ADJOURNMENT |
View Order |
11-Jul-2022 |
Ms. Prachi Singh, Planning Executive briefed about the facts of the project.Sh. Anish Dham (A.V.P) and Abhinav Saxena (AR) are present on behalf of the promoter.The Authority directed the promoter to submit the approved building plan along with the deficit documentsand requisite corrections.The AR of the promoter seeks two weeks’ time for rectification.The matter to come up on 25.07.2022. |
ADJOURNMENT |
View Order |
04-Jul-2022 |
The matter is adjourned to 11.07.2022. |
ADJOURNMENT |
--- |
20-Jun-2022 |
Coram is incomplete. The matter is adjourned to 04.07.2022. |