Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
THE MERIDIAN Sector-89, village hayatpur, gurugram GURUGRAM MRG INFRABUILD PVT. LTD.
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-1050-2022 07-Apr-2022 07-Apr-2022 EXTENSION APPROVED NOT REQUIRED Yes 29-Mar-2022 HARERA/GGM/EPIN/18 Notice dispatched to AR
first hearing
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
26-Dec-2022 Sh. Shashank Sharma, Associate Engineer Executive briefed the facts about the case. Sh. Naveen Aggarwal (CS) and Sh. Chamangeet Monga (Asstt. Manager) are present on behalf of the promoter. Keeping in view the fact that now the service plans and estimates have been approved, the Authority decides, taking a lenient view, to impose a penalty of Rs. 2.50 lakh which shall be deposited in the Authority within a period of 30 days. The AR of the promoter further submitted that the promoter has already deposited Rs. 10 lakh on account of guarantee to submit the service plans and estimates within next 3 months of grant of extension of registration. Now, that the requisite compliance has already been made, the amount of Rs. 10 lakh may be returned after deduction of the penalty amount of Rs. 2.50 lakh. Approved for grant of extension of registration under section 6 of the Act, 2016 on the above conditions.  EXTENSION APPROVED View Order
19-Dec-2022 The AR of the promoter is directed to remove the deficiencies. The matter to come up on 03.01.2023 ADJOURNMENT View Order
05-Dec-2022 The authorized representative of the promoter is advised to rectify the deficiencies and submit the deficit fee within a week along with the deficit documents apart from the filing of information in REP-I A to H format and online detailed project information. Further, if any promoter has an issue regarding the calculation of the fee, then the same shall be re-conciled with the concerned official and be submitted in the Authority, otherwise their matter will not be heard on next date of hearing i.e., 19.12.2022. The matter to come up on 19.12.2022.       (Sanjeev Kumar Arora)                                                                                                   (Ashok Sangwan) Member, HARERA, Gurugram                                                                        Member, HARERA, Gurugram       (Vijay Kumar Goyal)                                                                                           (Dr. K.K Khandelwal) Member, HARERA, Gurugram                                                                    Chairman, HARERA, Gurugram OBJECTION View Order
21-Nov-2022 Proceedings dated 21.11.2022 Sh. Shashank Sharma, Associate Engineer Executive briefed the facts about the case. Sh. Navin Aggarwal (AR) and Sh. ChamanGeet Monga (AR) is present on behalf of the promoter. The matter to come up on 05.12.2022.     (Sanjeev Kumar Arora)                                                                                                   (Ashok Sangwan) Member, HARERA, Gurugram                                                                        Member, HARERA, Gurugram       (Vijay Kumar Goyal)                                                                                           (Dr. K.K Khandelwal) Member, HARERA, Gurugram                                                                    Chairman, HARERA, Gurugram ADJOURNMENT View Order
27-Oct-2022 The promoter is directed to rectify the deficiencies and submit the deficit fee if any. The matter is adjourned for 21.11.2022. ADJOURNMENT View Order
12-Oct-2022 Sh. Shashank Sharma, Associate Engineer Executive briefed the facts about the case. The AR of the promoter has submitted that the project was launched as per the old building plans and the revised building plans were approved by DTCP later on 16.12.2019. The Authority has adopted a practice of issuing a public notice for information of all concerned in cases involving additions/alteration of approved building plans wherein 3rd party rights have been created so that any interested persons may like to have information submitted by the promoter along with other relevant documents. Accordingly, a public notice be issued in this matter in two newspapers i.e., one Hindi and one English (having good circulation in Gurugram) for filing objections. if any. The cost of that public notice is to be borne by the promoter.The matter to come up on 27.10.2022 ADJOURNMENT View Order
10-Oct-2022 The matter is adjourned for 12.10.2022. OBJECTION View Order
12-Sep-2022 Sh. Shashank Sharma, Associate Engineer Executive briefed the facts about the case. Sh. Vivek Mudgil (AGM) is present on behalf of the promoter. The promoter has already been granted more than 10 opportunities and still failed to rectify the deficiencies. The Authority here by decides to issue show cause notice to the promoter as why this application for grant of extension of registration of the project shall not be rejected for the want of  approved service plans and estimates and granted an opportunity under rule 6 of the Haryana Rules, 2017 to rectify the defects i.e. submission  of service plans and estimates within a period of 30 days from the date of issuance of communication regarding such defects i.e. today 12.09.2022 and further provides and opportunity of being heard in the matter on 17.10.2022 at 2.00 PM in the office of the Authority under section 6 of the Act, 2016. The matter to come up on 17.10.2022.   ADJOURNMENT View Order
22-Aug-2022 Proceedings dated 22.08.2022 Ms. Geeta Rathee Singh, Sr. L.O. and Sh. Shashank Sharma, Associate Engineer Executive briefed the facts about the case. Sh. Vivek Mudgil (AGM) is present on behalf of the promoter and states that the requisite deficit  documents have been submitted today in the registry of the Authority and accordingly office to examine the same along with status of submission of compliances under 4(2)(l)(D) as well as updated QPRs. The matter to come up on 12.09.2022. ADJOURNMENT View Order
01-Aug-2022 Proceedings dated 01.08.2022 Sh. Shashank Sharma, Associate Engineer Executive briefed the facts about the case. Sh. Vivek Mudgil (AGM) is present on behalf of the promoter. The AR submits that the application for license renewal is under consideration of DTCP and approval is expected in next 15 days and hence requests for adjournment of its submission along with other deficit documents. The matter to come up on 22.08.2022. OBJECTION View Order
11-Jul-2022 Ms. Anjana (Company Secretary) is present on the behalf of the promoter.  The AR submits that the promoter has applied for renewal of license to DTCP along with the requisite fee and renewal is expected shortly. Further, the requisite Bank undertaking and other documents shall also be submitted shortly. The AR is advised to submit the latest status of construction at the site duly certified by supervising Architect/Engineer and the milestones to complete the remaining works. The AR is also advised to submit the details of installments already received and the schedule of balance installments and to justify if the same is in consonance with development works which has already been completed. The CA of the Authority is required to examine the annual accounts statements under section 4(2)(l)(D) submitted in the Authority. The matter to come up on 01.08.2022. ADJOURNMENT View Order
27-Jun-2022 Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Ms. Anjana (Company Secretary) is present on the behalf of the promoter. The promoter is directed to submit the deficit documents in the Authority before the next date of hearing. The matter to come up on 11.07.2022 ADJOURNMENT View Order
15-Jun-2022 The Coram is incomplete. The matter to come up on 27.06.2022 ADJOURNMENT ---
06-Jun-2022 The matter to come up on 15.06.2022 OBJECTION ---
25-May-2022 Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Ms. Anjana (Company Secretary) is present on the behalf of the promoter. On scrutiny of various replies submitted by the promoter, it is noted that there are still deficiencies pending in the application. The AR of the promoter is directed to submit the deficit documents in the Authority before the next date of hearing. Neither the QPR nor the 4(2)(l)(D) annual audit reports of the project have been received from the promoter. The license has also expired. The promoter has been given 5 hearings to rectify the deficiencies and to submit the deficient documents. 1.       The promoter is directed to submit the complete details of QPR submitted along with annual audit reports and if there is any deficiency or delay in submission, the same be also submitted in next one week along with details of bank accounts maintained by the promoter and balance available therein. 2.       The Authority decided to conduct compliance audit in respect of requirements of section 4(2)(l)(D) and requirement of section 11 and the audit report should also provide details of withdrawals whether these are as per the provisions of law. 3.       Copy be endorsed to CA of the Authority for taking further action. 4.     The Engineering Executive shall visit the site and submit detailed report about the construction status of the project. Both CA and EE to be present at the time of next hearing. The matter to come up on 06.06.2022. ADJOURNMENT View Order
16-May-2022 Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. No one is present on the behalf of the promoter. The AR of the promoter has submitted a request via e- mail dated 16.05.2022 to postpone the hearing for two days. The authority decides to grant registration to the promoter. The matter to come up on 25.05.2022 ADJOURNMENT ---
04-May-2022 Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Ms. Anjana (CS) was present on the behalf of the promoter. The promoter be issued a notice for violating the provision of section 4 by not adhering to the declared date of completion of the project as per section 4(2)(l)(c) of the Real Estate (Regulation and Development) Act, 2016. The promoter is directed to fulfill the deficiencies in the application before the next date of hearing.                                                                                                                               The matter to come up on 16.05.2022 ADJOURNMENT View Order
26-Apr-2022 The matter is adjourned to 04.05.2022 ADJOURNMENT ---
13-Apr-2022 Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. No one was present on behalf of the promoter. A request from the promoter for more time to submit deficit documents to the authority is received through e- mail. The matter is adjourned to 26.04.2022 EXAMINATION BY AUTHORITY ---
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
23-Nov-2022 Proceedings dated 21.11.2022 Sh. Shashank Sharma, Associate Engineer Executive briefed the facts about the case. Sh. Navin Aggarwal (AR) and Sh. ChamanGeet Monga (AR) is present on behalf of the promoter. The matter to come up on 05.12.2022.     (Sanjeev Kumar Arora)                                                                                                   (Ashok Sangwan) Member, HARERA, Gurugram                                                                        Member, HARERA, Gurugram       (Vijay Kumar Goyal)                                                                                           (Dr. K.K Khandelwal) Member, HARERA, Gurugram                                                                    Chairman, HARERA, Gurugram Not Yet
04-Oct-2022 Sh. Shashank Sharma, Associate Engineer Executive briefed the facts about the case. Sh. Vivek Mudgil (AGM) is present on behalf of the promoter. The promoter has already been granted more than 10 opportunities and still failed to rectify the deficiencies. The Authority here by decides to issue show cause notice to the promoter as why this application for grant of extension of registration of the project shall not be rejected for the want of  approved service plans and estimates and granted an opportunity under rule 6 of the Haryana Rules, 2017 to rectify the defects i.e. submission  of service plans and estimates within a period of 30 days from the date of issuance of communication regarding such defects i.e. today 12.09.2022 and further provides and opportunity of being heard in the matter on 17.10.2022 at 2.00 PM in the office of the Authority under section 6 of the Act, 2016. The matter to come up on 17.10.2022. The promoter has submitted the request for earlier hearing so matter is relisted for dated 10.10.2022.   Not Yet
13-Jul-2022 Ms. Anjana (Company Secretary) is present on the behalf of the promoter.  The AR submits that the promoter has applied for renewal of license to DTCP along with the requisite fee and renewal is expected shortly. Further, the requisite Bank undertaking and other documents shall also be submitted shortly. The AR is advised to submit the latest status of construction at the site duly certified by supervising Architect/Engineer and the milestones to complete the remaining works. The AR is also advised to submit the details of installments already received and the schedule of balance installments and to justify if the same is in consonance with development works which has already been completed. The CA of the Authority is required to examine the annual accounts statements under section 4(2)(l)(D) submitted in the Authority. The matter to come up on 01.08.2022. Not Yet
26-May-2022 Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Ms. Anjana (Company Secretary) is present on the behalf of the promoter. On scrutiny of various replies submitted by the promoter, it is noted that there are still deficiencies pending in the application. The AR of the promoter is directed to submit the deficit documents in the Authority before the next date of hearing. Neither the QPR nor the 4(2)(l)(D) annual audit reports of the project have been received from the promoter. The license has also expired. The promoter has been given 5 hearings to rectify the deficiencies and to submit the deficient documents. 1.       The promoter is directed to submit the complete details of QPR submitted along with annual audit reports and if there is any deficiency or delay in submission, the same be also submitted in next one week along with details of bank accounts maintained by the promoter and balance available therein. 2.       The Authority decided to conduct compliance audit in respect of requirements of section 4(2)(l)(D) and requirement of section 11 and the audit report should also provide details of withdrawals whether these are as per the provisions of law. 3.       Copy be endorsed to CA of the Authority for taking further action. 4.     The Engineering Executive shall visit the site and submit detailed report about the construction status of the project. Both CA and EE to be present at the time of next hearing. The matter to come up on 06.06.2022. Not Yet