27-Oct-2021 |
Sh. Rahul Sharma (Manager) was present on the behalf
of the promoter.
Ar. Neeraj Gautam, Associate Architectural Executive
briefed the facts about the case. The promoter has made requisite corrections
in online DPI and REP-I (Part A-H). The promoter has applied for the approvals
of service plans and estimates, zoning plan and power line shifting in the
concerned departments, and the final approvals are still awaited.
The authority decides to grant registration to the
promoter subject to the submission of approved zoning plan, power line shifting
NOC and approved service plans and estimates in the authority within three
months from the date of grant of registration. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |
26-Oct-2021 |
THE MATTER IS ADJOURNED FOR 27.10.2021 |
ADJOURNMENT |
--- |
12-Oct-2021 |
Proceedings dated 12.10.2021
Sh. Rahul Sharma (Manager) was present on the behalf
of the promoter.
Ar. Neeraj Gautam, Associate Architectural Executive
briefed the facts about the case. The AR is directed to attend the deficiencies
before the next date of hearing.
The matter to come up on 26.10.2021 |
ADJOURNMENT |
--- |
21-Sep-2021 |
Rahul Sharma (Manager) was present on the behalf of the promoter. The case was discussed at length. The AR was directed to attend the deficiencies before the next date of hearing.Matter to come up on 12.10.2021 |
EXAMINATION BY AUTHORITY |
--- |