Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
Green Oaks Sector 70 A Gurugram GURUGRAM Gurgaon COUNTRYWIDE PROMOTERS PRIVATE LIMITED
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/503/235/2021/71 DATED 27.10.2021 RERA-GRG-928-2021 08-Sep-2021 07-Sep-2021 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 16-Sep-2021 By Hand First Deficiency Notice
Project listed for First hearing on 21.09.2021 View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/503/235/2021/71 DATED 27.10.2021 19-Apr-2022 RC Approved and Certificate Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
27-Oct-2021 Sh. Rahul Sharma (Manager) was present on the behalf of the promoter. Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. The promoter has made requisite corrections in online DPI and REP-I (Part A-H). The promoter has applied for the approvals of service plans and estimates, zoning plan and power line shifting in the concerned departments, and the final approvals are still awaited. The authority decides to grant registration to the promoter subject to the submission of approved zoning plan, power line shifting NOC and approved service plans and estimates in the authority within three months from the date of grant of registration. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS ---
26-Oct-2021 THE MATTER IS ADJOURNED FOR 27.10.2021 ADJOURNMENT ---
12-Oct-2021 Proceedings dated 12.10.2021 Sh. Rahul Sharma (Manager) was present on the behalf of the promoter. Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. The AR is directed to attend the deficiencies before the next date of hearing. The matter to come up on 26.10.2021 ADJOURNMENT ---
21-Sep-2021 Rahul Sharma (Manager) was present on the behalf of the promoter. The case was discussed at length. The AR was directed to attend the deficiencies before the next date of hearing.Matter to come up on 12.10.2021 EXAMINATION BY AUTHORITY ---