Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
---|---|---|---|---|
DDJAY Residential Plotted Colony | Sector-89, Gurugram Manesar Urban Complex, Gurugram, Haryana. | GURUGRAM | Harsaru ST | Adhikaansh Realtors Private Limited ,Aawam Residency Private Limited |
Project Registration Number | Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks | Details of Project(Form A-H) |
---|---|---|---|---|---|---|---|---|---|---|---|---|
GGM/500/232/2021/68 DATED 25.10.2021 | RERA-GRG-920-2021 | 08-Sep-2021 | 07-Sep-2021 | APPROVED AND CERTIFICATE UPLOADED | NOT REQUIRED | Yes | 18-Sep-2021 | HARERA/GGM/RPIN/374 | Notice handed over to the AR | First hearing | View Form(A-H) |
Project Registration Number | Uploading Date | Remarks | View Certificate |
---|---|---|---|
GGM/500/232/2021/68 DATED 25.10.2021 | 13-Apr-2022 | RC Approved and Certificate Uploaded |
Date of Hearing | Proceedings of the day | Status | Order |
---|---|---|---|
25-Oct-2021 | Ms. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Sh. Abhijeet Singh (AR), Sh. Manik Sharma (AR) and Sh. Vineet Maheshwari (AR) were present on the behalf of the promoter. After detailed scrutiny, it was found that license no. 32 of 2021 dated 03.07.2021 was issued in favour of M/s Adhikaansh Realtors Pvt. Ltd. in collaboration with M/s Aawam Residency Pvt. Ltd. but as per the license land schedule, M/s Adhikaansh Realtors Pvt. Ltd. has the land ownership of 32.431 acres and M/s Aawam Residency Pvt. Ltd. has land ownership of 19.8437 acres. Also, it was found that as per the collaboration agreement dated 12.07.2021, clause 3 regarding consideration and MoA dated 28.09.2021, M/s Aawam Residency Pvt. Ltd. shall be entitled to allocation of 2140 sq. yards per acre of land owned by M/s Aawam Residency Pvt. Ltd. in the affordable plotted residential colony under DDJAY ( being an area of 42465.625 sq. yards in the form of residential plotted area) and 1,03,397.465 sq. yards will be developed and sold by M/s Adhikaansh Realtors Pvt. Ltd. also, M/s Adhikaansh Realtors Pvt. Ltd. shall be responsible for developing all the common facilities and infrastructure of the whole licensed colony. Therefore, it is found that while issuing license no. 32 of 2021 by Director, Town and Country Planning, Haryana, a clerical error regarding name of collaborator has occurred which needs to be amended by DTCP, Haryana within two months. The AR has applied for the construction water NOC in the competent authority, the final approval is still awaited. The AR has assured to submit the corrected online DPI within a week. The authority has decided to grant the registration to the promoter subject to submission of HUDA construction water NOC and a copy of amended/ corrected copy of license from DTCP, Haryana within two months from the date of grant of registration failing which the promoter shall be liable for legal action against the promoter under Real Estate (Regulation and Development) Act, 2016. | APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS | --- |
19-Oct-2021 | Proceedings dated 19.10.2021 Ms. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Sh. Abhijeet Singh (AR) and Sh. Manik Sharma (AR) were present on the behalf of the promoter. The reply to the deficiencies notice has been submitted today only i.e. 19.10.2021 along with requisite documents and is being scrutinised. The matter to come up on 25.10.2021. | ADJOURNMENT | --- |
12-Oct-2021 | Proceedings dated 12.10.2021 Sh. Abhijeet Singh (AR) and Sh. Manik Sharma (AR) were present on the behalf of the promoter. Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. The AR is directed to attend the deficiencies before the next date of hearing. The matter to come up on 19.10.2021 | ADJOURNMENT | --- |
05-Oct-2021 | Proceedings dated 05.10.2021 Sh. Abhijeet Singh (AR) and Sh. Manik Sharma were present on the behalf of the promoter. Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. The AR is directed to submit the reply to the deficiencies in the authority immediately. The reply be scrutinized by the concerned within this week. The matter to come up on 12.10.2021. | EXAMINATION BY AUTHORITY | --- |