9999485956 (Number Shared by Promoter in Public)
adhikaanshrealtors@gmail.com
ROHIT MEHTA
9999318874
9999318874 (Number Shared by Promoter in Public)
rohit.mehta@smartworlddevelopers.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
512896
06-09-2021
2411750
ICICI BANK
HRERA Gurugram
2
512897
06-09-2021
2157900
ICICI BANK,
HRERA Gurugram
52.275 (Acre)
N.A.
0
52.275 (Acre)
32 of 2021 dated 03.07.2021
No
Address UNIT NO. SB/C/2L/OFFICE/017A, M3M URBANA, SECTOR-67, GURUGRAM, HARYANA-122102
Address UNIT NO. SB/C/2L/OFFICE/017A, M3M URBANA, SECTOR-67, GURUGRAM, HARYANA-122102
Annexure-B- BY THE TERMS AND CONDITIONS OF THE COLLABORATION AGREEMENT NO. 3871 DATED 11-02-2021 AND ADDENDUM TO THE COLLABORATION AGREEMENT 1870 DATED 12.07.2021 ATTACHED AS ANNEXURE A-5
COLLABORATION AGREEMENT & GPA EXECUTED BEFORE GRANT OF LICENCE BY DTCP
Yes
ANNEXED IN FOLDER-A ANNEXURE A-5
No
Yes
No
53328.28 Lakhs
37610.00 Lakhs
0 Lakhs
6035.50 Lakhs
9682.78 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
26.932
3
CONSTRUCTION OF ROADS
11.4981
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
3.921
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
5.232
12
ANY OTHER
0.1224
13
COMMERCIAL USE
1.173
14
SEWERAGE TREATMENT PLANT
0.370
15
MILK OR VEGETABLE BOOTH
0.0135
16
UNDEFINED USE
3.013
Total
52.275
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
GMDA
Yes
WATER SUPPLY
GMDA
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
GMDA
Yes
STORM WATER DRAINAGE
GMDA
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
2420
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
294
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
459
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
352
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
628
AS PER PROJECT REPORT
6
STREET LIGHTING
201
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
16
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
238
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
0
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
0
AS PER PROJECT REPORT
15
STP
144
AS PER PROJECT REPORT
16
UNDERGROUND WATER TANK
199
AS PER PROJECT REPORT
17
RAIN WATER HARVESTING
30
AS PER PROJECT REPORT
18
ELECTRICAL SUB STATION
775
AS PER PROJECT REPORT
19
BOUNDARY WALL LANDSCAPE
279
AS PER PROJECT REPORT
03-07-2021 (date)
03-07-2021 (date)
01-09-2021
31-10-2024
Plot Area(In Square Meter)
Number of plots in the project
108988.38
930
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
EDC
1523.7
IDC
571.2
Land Cost
37610.0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
Shops
0
0
Plots
0
0
Other Cost
97.9
54.8
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
0
0
0
0
Other Cost
58.4
85.90
181.9
128.5
EDC
1038.3
987.2
IDC
571.2
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
0
0
0
0
Other Cost
153.4
134.6
172.3
90.8
EDC
942.2
897.1
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
Shops
0
0
0
Plots
0
0
0
Other Cost
180.0
154.41
EDC
852.0
806.91
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
121.00
121.00
Water Supply System
0
14.71
Sewerage treatment & garbage disposal
0
31.42
Electricity Supply System
0
0
Storm Water Drainage
0
22.97
Parks and Playgrounds
0
11.91
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
Boundary Wall
27.88
27.88
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
121.00
169.39
241.99
241.99
Water Supply System
14.71
20.60
20.60
29.43
Sewerage treatment & garbage disposal
31.42
43.99
62.84
62.84
Electricity Supply System
17.59
24.63
35.18
42.22
Storm Water Drainage
22.97
32.16
32.16
45.95
Parks and Playgrounds
11.91
14.30
16.68
23.83
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Rain Water
1.50
3.00
3.00
Electrical sub station
77.48
77.48
77.48
Boundary Wall
27.88
41.82
41.82
55.77
Underground tank
19.87
19.87
STP
14.40
14.40
Street Light
20.06
20.06
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
362.99
266.19
241.99
193.59
Water Supply System
35.31
44.14
44.14
29.43
Sewerage treatment & garbage disposal
94.26
75.41
75.41
62.84
Electricity Supply System
52.77
52.77
42.22
35.18
Storm Water Drainage
55.14
68.92
68.92
45.95
Parks and Playgrounds
23.83
23.83
35.74
35.74
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Rain Water
4.50
4.50
6.00
3.00
Street Light
20.06
20.06
20.06
40.11
Boundary Wall
27.88
27.88
Firefighting services
2.84
2.84
Security
1.25
1.25
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
169.39
169.39
Water Supply System
20.60
20.60
Sewerage treatment & garbage disposal
43.99
43.99
Electricity Supply System
24.63
24.63
Storm Water Drainage
32.16
32.16
Parks and Playgrounds
23.83
16.68
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
STP
57.60
57.60
Under Ground Water Tank
79.50
79.50
Rain water
3.00
1.50
Electrical sub station
309.94
232.45
Firefighting services
2.84
2.84
Security
1.25
1.25
Street Light
40.11
20.06
No
No
ICICI BANK LIMITED, BRANCH SECTOR 54, SUNCITY, GURGAON, HARYANA -122003
777705008987
ICIC0000399
110229060
000399
1. Harshwardhan Prasad-D1104 GPL Eden Heights, Darbaripur Road, Sector 70, Badshahpur, Gurgaon, Haryana 1221012.
2. Naman Gupta- 704, Om Terrace, New City Light, China Gate, Surat, New Citylight, Surat, Surat City, Surat, Svr College, Gujarat, 395007
Yes
Yes
Yes
Yes
No
No
No
No
No
No
No
Yes
No
Yes
Yes
Yes
Yes
Yes
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENCE
ALREADY BEEN OBTAINED
03-07-2021
II. ZONING PLAN APPROVAL
ALREADY BEEN OBTAINED
13-08-2021
III. LAYOUT PLAN APPROVAL
ALREADY BEEN OBTAINED
03-07-2021
IV. FOREST NOC
ALREADY BEEN OBTAINED
24-03-2021
V. ARAVALI
ALREADY BEEN OBTAINED
13-04-2021
No
No
N.A.
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT