| 12-Sep-2022 |
Proceedings dated 12.09.2022
Sh.
Shashank Sharma, Associate Engineer Executive briefed
about the facts of the project.
Sh.
Anurag Srivastava (GM) is present on behalf of the promoter.
Approved as recommended above and subject to
compliance of conditions of registration if any in respect of the earlier registered Phase as
well as non-receipt of any objections as per above. This is further without
prejudice to the rights of allottees to seek compensation for variations in the
plans under section 12,14 and 18 of the Act, 2016. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |
| 30-Aug-2022 |
Proceedings dated 30.08.2022
Ms.
Geeta Rathee Singh, Sr. Legal Officer and Sh. Shashank Sharma, Associate
Engineer Executive briefed about the facts of the
project.
Sh.
Anurag Srivastava (GM), Sh. Sharad Goyal (AR) and Sh. Prabhjot Singh (AR) are present
on behalf of the promoter.
The
compliance of the directions of the Authority dated 17.08.2022 regarding
publication of the notice in at least one English and one Hindi newspaper (having
good circulation in Gurugram) is not yet made by the promoter. One more
opportunity is being given to the promoter for doing the needful before the
application is considered.
The matter to come up on 12.09.2022. |
ADJOURNMENT |
--- |
| 17-Aug-2022 |
Proceedings dated 17.08.2022
Ms.
Geeta Rathee Singh, Sr. Legal Officer and Sh. Shashank Sharma, Associate
Engineer Executive briefed about the facts of the
project.
Sh.
Anurag Srivastava (GM) and Sh. Sukh Pal (Executive Legal Deptt.) are present on
behalf of the promoter.
The
public notice for objections if any for the changes made in the approved
building plan was published in The Tribune and Human India newspapers. It is
noticed that the public notice needs to be published in at least one Hindi
Newspaper with a proper insignia of the Authority. Further the Engineering
Executive is directed to obtain a specific report from the registry if any
response is received in response to the above advertisements.
The matter to come up on 30.08.2022. |
OBJECTION |
--- |
| 27-Jul-2022 |
Proceedings dated 27.07.2022
Sh.
Shashank Sharma, Associate Engineer Executive briefed
about the facts of the project.
Sh. Ajay Kumar
(AR) is present on the behalf of promoter.
The AR has submitted the consent of more than 2/3rd
allottees in the registry of the Authority for change/addition/alteration in
the building plans. The AR further submits that the revised building plans were
approved by DTCP after inviting the
objections from all the allottees only and construction of additional floor is
in progress. However, the same shall be completed as per the date of completion
indicated at the time of registration of old license area while the above
application is for registration of additional licensed are measuring 0.74375
necessitating additions/alterations even in respect of the already approved
building plans. The AR further confirms that there is no reduction in the green
area or common areas and rather the same are getting increased in revised
building plans. The Authority has adopted a practice of issuing a public notice
for information of all concerned in cases involving additions/alteration of
approved building plans wherein 3rd party rights have been created
so that any interested persons may like to inspect the copies of consents
submitted by the promoter along with other relevant documents. The branch is
directed to ensure supply of public notice to the promoter for its publication in
two newspapers (one Hindi and one English).
The matter to come up on 17.08.2022. |
ADJOURNMENT |
--- |
| 25-Jul-2022 |
Due to administrative work of the Authority, the matter is adjourned to 27.07.2022 |
ADJOURNMENT |
--- |
| 28-Feb-2022 |
Proceedings dated: 28.02.2022
Ms. Jyoti Yadav, Coordinator Planning
Branch briefed about the facts of the project.
Sh. Ajay Kumar (AM) is present on the
behalf of the promoter.
A reference to DTCP for approval of the requisite building
plan without the consent of the existing allottees has been made and the requisite
clarification is still awaited. A reminder to DTCP for early clarification in
the matter be issued and the matter be submitted after clarification is received from
DTCP. |
SINE DIE |
--- |
| 07-Feb-2022 |
Proceedings dated 07.02.2022
Sh. Ajay Kumar (AM) was present on the
behalf of the promoter. The AR of the promoter is directed to attend the
deficiencies before the next date of hearing.
The matter to come up on 28.02.2022 |
ADJOURNMENT |
--- |
| 24-Jan-2022 |
Proceedings
dated 24.01.2022
Sh.
Ajay Kumar (AM) was present on the behalf of the promoter. The AR of the promoter is directed to attend the
deficiencies before the next date of hearing.
The matter to come up on 07.02.2022 |
ADJOURNMENT |
--- |
| 10-Jan-2022 |
Proceedings
dated 10.01.2022
Sh.
Ajay Kumar (AM) was present on the behalf of the promoter. Ar. Neeraj Gautam
briefed the facts of the case. The AR of the promoter is directed to attend the
deficiencies before the next date of hearing.
The matter to come up on 24.01.2022 |
ADJOURNMENT |
--- |
| 03-Jan-2022 |
Proceedings
dated 03.01.2022
Amid COVID
19 and omicron pandemic, the hearing couldn’t be held on the fixed date. Some planning
executives are found omicron infected. Therefore, the hearing will be held
through video conferencing in the next week.
The matter
is adjourned to 10.01.2022 |
ADJOURNMENT |
--- |
| 20-Dec-2021 |
Proceedings dated 20.12.2021 Sh. Ajay Kumar (AM) was present on the behalf of the
promoter.
The AR of the promoter is directed to attend the deficiencies before the next date of hearing.
The matter to come up on 03.01.2022 |
ADJOURNMENT |
--- |
| 09-Nov-2021 |
Proceedings dated 09.11.2021
Sh. Ajay Kumar (AM) was present on the behalf of the
promoter.
The AR of the promoter is directed to deposit the
deficit documents in the authority
before the next date of hearing.
The matter to come up on 20.12.2021 |
ADJOURNMENT |
--- |
| 02-Nov-2021 |
The matter will be heard 09.11.2021. |
ADJOURNMENT |
--- |
| 19-Oct-2021 |
Proceedings dated 19.10.2021
Sh. Ajay Kumar (AM) was present on the behalf of the
promoter.
Ar. Neeraj Gautam, Associate Architectural Executive
briefed the facts about the case.
The AR has submitted the reply to the observations of
the last Authority meeting including a copy of structural stability certificate
submitted at the time of approval of the revised building plans. Further he
submits that no objections for the above revision was received by the promoter
company after issuing public notice to this effect. However, a confirmation
issued by concerned STP regarding objections, if any, has not been submitted.
Further the AR has not submitted details of changes which have occurred in the
existing/old, licensed area w.r.t. provision of green area, provision of
amenities, variation in height of buildings and provision of public health
services and upgradations proposed therein if any. The said details be
submitted in a tabular form duly authenticated by the authorised
representative. The online DPI also needs to be submitted along with its hard
copy along with other deficit documents. The AR assures to give the requisite
details in a weeks’ time. The reply submitted today be also checked in
meanwhile.
The matter to come up on 02.11.2021. |
ADJOURNMENT |
--- |
| 05-Oct-2021 |
Proceedings dated 05.10.2021
Sh. Ajay Kumar (AM) was present on the behalf of the
promoter.
Ar. Neeraj Gautam, Associate Architectural Executive
briefed the facts about the case.
The AR is directed to submit the structural stability
certificate with respect to the revised layout, details of objections by
allotees received regarding the revision of layout plan and comparative impact
on common areas before and after the revision of layout along with deficit
documents before the next hearing.
The matter to come up on 19.10.2021. |
ADJOURNMENT |
--- |
| 27-Sep-2021 |
Proceedings dated 21.09.2021Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Sh. Ajay Kumar(Assistant Manager) is present on behalf of the promoter. The AR is directed to submit the deficit documents in the authority before next hearing. The matter to come up on 27.09.2021 |
ADJOURNMENT |
--- |
| 21-Sep-2021 |
Proceedings dated 21.09.2021Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Sh. Ajay Kumar(Assistant Manager) is present on behalf of the promoter. The AR is directed to submit the deficit documents in the authority before next hearing. The matter to come up on 27.09.2021 |
ADJOURNMENT |
--- |
| 07-Sep-2021 |
Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case.Sh. Ajay Kumar(Assistant Manager) is present on behalf of the promoter requests two weeks’ time to rectify the deficiencies already conveyed by the Authority vide Notice dated 01.09.2021. The case is adjourned to 21.09.2021. |
EXAMINATION BY AUTHORITY |
--- |