13TH FLOOR DR.GOPAL DAS BHAWAN, 28 BARAKHAMBA ROAD NEW DELHI 110001
01244908200
9810899381 (Number Shared by Promoter in Public)
compliance@signatureglobal.in
https://www.signatureglobal.in/
XXXX807M
U70100DL2000PTC104787
SIGNATURE GLOBAL PRIME
VILLAGE KADARPUR, SECTOR 63AGURUGRAM-MANESAR URBAN COMPLEX,DIST.GURUGRAM, HARYANA
SOHNA
GURUGRAM
01244908200
9810899381 (Number Shared by Promoter in Public)
compliance@signatureglobal.in
SANJAY KUMAR VASHNEY
01244908200
9810899381 (Number Shared by Promoter in Public)
compliance@signatureglobal.in
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
592213
19-08-2021
172377
HDFC BANK
HRERA Gurugram
2
592214
19-08-2022
70130
HDFC BANK
HRERA Gurugram
5.74375 (Acre)
2.25
2.25
5.74375 (Acre)
40 of 2020 dated 11/12/2020 and 69 of 2019 dated 26/06/2019
Yes
21446.19 Lakhs
378.5 Lakhs
11575 Lakhs
1237.09 Lakhs
8709.92 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0.1900
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0.7300
3
CONSTRUCTION OF ROADS
1.2
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
1.012
6
GREEN BELTS
0
7
VEHICLE PARKINGS
2.32
8
ELECTRICITY SUB-STATION
0.056
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
13
SECTORROAD
0.14335
14
COMMUNITYCENTREANDANGANWADI
0.0924
Total
5.74375
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
GMDA
Yes
WATER SUPPLY
GMDA
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
GMDA
Yes
STORM WATER DRAINAGE
HSVP
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
91.84
SUBMITTED TO HUDA
2
WATER SUPPLY SYSTEM
230.33
SUBMITTED TO HUDA
3
STORM WATER DRAINAGE
51.35
SUBMITTED TO HUDA
4
ELECTRICITY SUPPLY SYSTEM
0
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
137.70
SUBMITTED TO HUDA
6
STREET LIGHTING
8.81
SUBMITTED TO HUDA
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
3.34
SUBMITTED TO HUDA
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
MAINTENANCE CHARGES FOR TEN YEARS
121.47
SUBMITTED TO HUDA
25-08-2021 (date)
26-08-2021 (date)
01-09-2021
31-08-2025
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
0
103
Total
103
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
573.54
196
1
Apartment/Shops/Other Buildings
590.66
194
2
Apartment/Shops/Other Buildings
578.13
191
1
Apartment/Shops/Other Buildings
577.41
195
1
Apartment/Shops/Other Buildings
645.46
41
1
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
3622.41
Shops
332.71
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
15.3
15.3
Water Supply System
38.4
38.4
Sewerage treatment & garbage disposal
21.8
21.8
Electricity Supply System
0
0
Storm Water Drainage
8.5
8.5
Parks and Playgrounds
0.5
0.5
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
Street Lighting
1.5
1.5
Maintenance charges for ten years
0
20.24
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
15.3
15.3
15.3
15.3
Water Supply System
38.4
38.4
38.4
38.4
Sewerage treatment & garbage disposal
21.8
21.8
21.8
21.8
Electricity Supply System
0
0
0
0
Storm Water Drainage
8.5
8.5
8.5
8.5
Parks and Playgrounds
0.5
0.5
0.5
0.5
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Street Lighting
1.5
1.5
1.5
1.5
Maintenance charges for ten years
20.24
20.24
20.24
20.24
Yes
No
YES BANK LTD.,56, JANPATH, CONNAUGHT PLACE, DELHI
013672500000111
YESB000136
110532031
000136
Ravi Aggarwal & Devender Aggarwal
Address: 34, Road No.61, West Punjabi Bagh Delhi 110026
Attached
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO. 40 OF 2020
ALREADY BEEN OBTAINED
10-12-2025
II. LICENSE NO.69 OF 2019
ALREADY BEEN OBTAINED
26-06-2019
Yes
Yes
Attached
SIGNATURE GLOBAL SCO 36 SOHNA
5.21875
0
84
0
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
6328.05
6328.05
0
Cost of the apartments
0
0
0
Cost of the infrastructure
310.72
310.72
0
Others costs
6017.33
6017.33
0
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
01-04-2022
30-06-2023
GOLF GREENS-79
5.9125
934
0
0
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
16816.27
16816.27
6620.91
Cost of the apartments
10290
10290
2725.72
Cost of the infrastructure
910.0
910.0
494.5
Others costs
5616.27
5616.27
3400.69
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
23-06-2020
31-07-2024
THE MILLENIIA-GROUP HOUSING COLONY
9.7015625
1148
0
1142
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
22804
22804
0
Cost of the apartments
17374
17374
0
Cost of the infrastructure
0
0
0
Others costs
5430
5430
0
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
26-10-2017
20-08-2021
SIGANTURE GLOBAL PRIME
5.0
788
0
0
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
14785.71
14785.71
5881.02
Cost of the apartments
9625.0
9625.0
4153.45
Cost of the infrastructure
1237.09
1237.09
0
Others costs
3923.62
3923.62
1727.57
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
01-11-2019
31-10-2023
SIGNATURE GLOBAL PROXIMA 1
5.0
720
0
0
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
14069.02
14069.02
7182.17
Cost of the apartments
8904.40
8904.40
4787.57
Cost of the infrastructure
1180.24
1108.24
0
Others costs
4056.38
4056.38
2394.6
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
01-01-2020
31-12-2023
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: