21-Sep-2021 |
Proceedings Dated: 21.09.2021
Sh. Rahul Sharma is present on behalf of the promoter.
An
application regarding registration of plotted colony project namely “102 Eden Estate II”
situated at sector 102 & 102A, Gurugram being developed by M/s Countrywide
Promoters Pvt Ltd was submitted on 13.07.2021 under
section 4 of Real Estate (Regulation and Development), Act 2016.
This
application for registration is part of the plotted residential colony which
has been licensed vide 3 nos. licenses issued in favour of various license
holders in collaboration with M/s Countrywide Promoters Pvt Ltd.
1. License
no. 58 of 2010 dated 03.08.2010 for 108.068 acres valid upto 02.08.2025.
2. License
no. 45 of 2011 dated 17.05.2011 for 18.606 acres valid upto 15.05.2024 issued
in favour of various landowners in collaboration
of M/s Countrywide Promoters Pvt Ltd.
3.
License no. 41 of 2021
dated 23.07.2021 for 7.031 acres issued in favour of Merit Marketing Pvt Ltd,
Sunglow Overseas Pvt Ltd, BPT Ltd, Saraswati Kunj Infrastructure Pvt Ltd,
Eventual Builders Pvt Ltd in collaboration of M/s Countrywide Promoters Pvt
Ltd.
The promoter has already obtained registration of
project named as “102 Eden Estate” for an area admeasuring 126.674 acres vide
RC no. 31 of 2020 from HARERA, Gurugram falling under license no. 58 of 2010
and 45 of 2011.
After obtaining registration, the promoter has
obtained the additional license for 7.031 acres.
The present
application pertains to 80 residential plots forming additional license no. 41
of 2021 admeasuring 7.031 acres, being developed by M/s Countrywide Promoters
Pvt Ltd.
The time period
for completion of the project declared by the promoter under Section 4(2)(l)(c)
shall be for part completion of 7.031 acres of additional licensed area under
license no. 41 of 2021 and completion certificate for the whole project i.e.,
133.705 acres of all the three licenses i.e., license no. 58 of 2010, 45 of
2011 and 41 of 2021.
The promoter
has submitted an application dated 21.09.2021 requesting the Authority to grant
registration of additional license no. 41 of 2021 and revision of service
estimates and plans, zoning plan and environmental clearance are applied in the
competent authority, and they will submit copies of their approval within three
months.
The Authority decided to register the project (as a
separate phase, which shall be considered as a standalone real estate project
in terms of explanation attached with Section 3 of the Real Estate (Regulation
and Development) Act, 2016) and grant registration for this additional 7.03125
acres of license subject to submission of undertaking that they will submit
compliance report in this context within 3 months failing which the RC shall
stand revoked automatically. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |
07-Sep-2021 |
Proceedings Dated: 07.09.2021
Ms. Jyoti Yadav, Coordinator, Planning Branch briefed
about the facts of the project.
Sh. Rahul Sharma is present on behalf of the promoter.
The promoter was advised to submit the deficient
documents and remove the deficiencies as have been pointed out above. It also came to the notice of the Authority
that advertisement has already been issued regarding this project without
registration. Show cause notice be issued.
The matter to come up on 21.09.2021 |
OBJECTION |
--- |
17-Aug-2021 |
Proceedings Dated: 17.08.2021
Ms. Jyoti Yadav, Coordinator, Planning Branch briefed
about the facts of the project.
Sh. Rahul Sharma is present on behalf of the promoter.
An application regarding registration of plotted
colony project namely “102 Eden Estate II” situated at sector 102 & 102A,
Gurugram being developed by M/s Countrywide Promoters Pvt Ltd was submitted on
13.07.2021 under section 4 of Real Estate (Regulation and Development), Act
2016.
The present application pertains to 81 residential
plots forming additional plotted license measuring 7.031 acres, being developed
by M/s Countrywide Promoters Pvt Ltd.
On scrutiny of application, it was found that there
were deficiencies in the application which were conveyed to the promoter vide
notice no. HARERA/GGM/RPIN/350 dated 19.07.2021 with the directions to remove
the deficiencies/ observations and an opportunity of hearing was offered on 03.08.2021.
The promoter has submitted the reply on 02.08.2021
which was scrutinized and found that there are still deficiencies in the
application which were conveyed to the promoter vide email dated 07.08.2021.
On
03.08.2021, matter adjourned for 10.08.2021.
On
10.08.2021, the promoter has submitted the reply in the hearing, which was
scrutinized, and remaining deficiencies were conveyed to the promoter. Matter
got adjourned for 12.08.2021.
On
12.08.2021, matter adjourned for 17.08.2021. As on today, the promoter has not
submitted the reply of the remaining deficiencies which were conveyed to the
promoter.
Deficit
documents
1. Online corrections in REP-I
(Part A-H) needs to be done.
2. Corrections in detailed
project information needs to be done.
3. Approvals for water supply,
sewage disposal, storm water drainage from competent authority needs to be
submitted.
Status: water supply assurance submitted. other approvals still pending
4. Copy of approved environment
clearance not submitted. (Annexure A16)
Status: Applied on 10.06.2021 for revision of EC. Final approval still
awaited.
5. Copy of approved service
estimates and plans needs to be submitted along with sanction letter from DTCP,
Haryana. (Annexure A18)
Status: applied on 03.08.2021. Final approval not submitted.
6. Copy of approved zoning
plan, demarcation plan needs to be submitted. (Annexure C2, C3)
Status: applied on 19.04.2021 but final approval still awaited.
7. Copy of superimposed
demarcation plan on approved site plan on A1 sheet not submitted. (Annexure
C14)
Status: not submitted.
8. PERT Chart needs to be
submitted. (Annexure C15)
Status: needs to be revised.
9. Copy of draft application
form needs to be revised. (Annexure D15)
10. Allotment letter, builder
buyer agreement, conveyance deed, payment plan and payment receipt need to be
submitted in the prescribed format. BBA shall be signed with the buyer by the
promoter with the concurrence and signatures of licensee. Schedule of BBA and
allotment letter not provided. (Annexure D16, D17, D18, D19)
Status: not submitted.
On the request of the AR promoter, three weeks
time is granted for removing the deficiencies. The matter to come up on
07.09.2021. |
ADJOURNMENT |
--- |
12-Aug-2021 |
Matter adjourned for 17.08.2021 |
ADJOURNMENT |
--- |
10-Aug-2021 |
Matter adjourned for 12.08.2021 |
ADJOURNMENT |
--- |
03-Aug-2021 |
Matter adjourned for 10.08.2021 |
EXAMINATION BY AUTHORITY |
--- |