27-Jul-2021 |
Sh. Ashish Kush, Planning Executive briefed the
facts about the project.
Sh. Arvinder Dhingra (SVP) is present on behalf
of the promoter.
The promoter M/s Elan City LLP who is a third party
right holder/sale deed holder applied for the registration of real estate
project namely “Elan Empire” located at Sector-66, Gurugram under section 4 of
the Real Estate (Regulations and Development) Act, 2016 vide central receipt
no. 10284/19595 dated 19.05.2021 and RPIN-333. The Temp I.D. of REP – I (Part
A-H) is RERA -GRG-PROJ-852-2021. The project area for registration is 1.4625
acres (a commercial site) in a residential plotted colony namely “Marbella”
developed by Emaar India Limited (formerly known as Emaar MGF Land Limited).
The residential plotted colony having total area 107.919 acres registered in
two phases. Phase-I having area 41.86 acres was registered under the
registration certificate no. 307 of 2017 dated 17.10.2017 and Phase-II having
area 66.059 acres registered vide. registration no. 08 of 2021 dated
01.03.2021. The applied area for registration is falling in the Phase-I. The
application for registration was scrutinized and 1st deficiency notice conveyed
vide notice no. HARERA/GGM/RPIN/333 dated 27.05.2021 was issued to the promoter
with an opportunity of being heard on 07.06.2021. The promoter submitted a
reply on 03.06.2021 in the Authority and after the scrutiny of the reply some
of the deficiencies were pending. On 07.06.2021, the hearing was adjourned due
to COVID-19 Pandemic and fixed for 08.06.2021. On 08.06.2021, the promoter is
advised to remove the deficiencies and matter is fixed for 01.07.2021. The
promoter submitted the reply on 25.06.2021. On 01.07.2021, the authority
directed the promoter to remove the deficiencies and matter is fixed for
15.07.2021. The promoter submitted the reply dated 07.07.2021 and 09.07.2021.
On 15.07.2021, the authority directed the promoter to submit the deficit
documents and adjourned the matter and fixed for 20.07.2021. The promoter
submitted the reply on 14.07.2021 and 15.07.2021. After the scrutiny of these
replies all the deficiencies are removed by the promoter. On 20.07.2021, the
Authority decided to grant them registration certificate as and when
corrections are complete and adjourned the matter for 27.07.2021.
The promoter made the requisite corrections in
online DPI and during hearing on 27.07.2021, the authority decided to grant the
registration certificate.Member (Samir Kumar)Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
20-Jul-2021 |
Sh. Ashish Kush, Planning Executive briefed the facts
about the project.
Sh. Arvinder Dhigra (AR) is present on behalf of
the promoter.
The promoter M/s
Elan City LLP who is a Third-party right holder/ sale deed holder applied for
the registration of real estate project namely “Elan Empire” located at
Sector-66, Gurugram under section 4 of the Real Estate (Regulations and
Development) Act, 2016 vide central receipt no. 10284/19595 dated 19.05.2021
and RPIN-333. The Temp I.D. of REP – I (Part A-H) is RERA -GRG-PROJ-852-2021.
The project area for registration is 1.4625 acres (a commercial site) in a
residential plotted colony namely “Marbella” developed by Emaar India Limited
(formerly known as Emaar MGF Land Limited. The residential plotted colony
having total area 107.919 acres registered in two phases. Phase-I having area
41.86 acres was registered under the registration certificate 307 of 2017 dated
17.10.2017 and Phase-II having area 66.059 acres registered vide. registration
no. 08 of 2021 dated 01.03.2021. The applied area for registration is falling
in the Phase-I. The application for registration was scrutinized and 1st
deficiency notice vide notice no. HARERA/GGM/RPIN/333 dated 27.05.2021 was
issued to the promoter with an opportunity of being heard on 07.06.2021. The
promoter submitted a reply on 03.06.2021 in the Authority and after the
scrutiny of the reply some of the deficiencies were pending. On 07.06.2021, the
hearing was adjourned due to COVID-19 Pandemic and fixed for 08.06.2021. On
08.06.2021, the promoter is advised to remove the deficiencies and matter is
fixed for 01.07.2021. The promoter submitted the reply on 25.06.2021. On
01.07.2021, the authority directed the promoter to remove the deficiencies and
matter is fixed for 15.07.2021. The promoter submitted the reply dated
07.07.2021 and 09.07.2021. On scrutiny of the reply some of the deficiencies
are remaining which are mentioned below:
1.
The
annexures in the online application are not uploaded as well as the correction
needs to be done in the online (A-H).
2.
DPI
needs to be corrected.
3. Tree
Cutting permission NOC from DFO needs to be submitted.
Tree cutting
permission was submitted on 14.07.2021. Major corrections in the DPI have been
made. Other corrections likely to be concluded within 2-3 days. Authority
decided to grant them registration certificate as and when corrections are
completed.
The matter to come up on 27.07.2021.Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman) |
OBJECTION |
View Order |
15-Jul-2021 |
Sh. Ashish Kush, Planning Executive briefed the
facts about the project. The deficencies are mentioned below:1 The annexures in the online application are not uploaded as well as the correction needs to be done in the online (A-H).2 DPI needs to be corrected.2 Tree cutting permission NOC from DFO needs to be submitted.The authority decided to adjourn the matter and fixed for 20.07.2021.Vijay Kumar Goyal (Member)Samir Kumar (Member) Dr. K.K. Khandelwal (Chairman) |
OBJECTION |
View Order |
02-Jul-2021 |
Proceedings dated: 02.07.2021
Sh. Ashish Kush, Planning Executive briefed the
facts about the project.
Sh. Arvinder Dhingra and Sh. Gaurav Khandelwal
(Director) are present on behalf of the promoter.
The promoter M/s Elan City LLP who is a third-party
right holder/ sale deed holder applied for the registration of real estate
project namely “Elan Empire” located at Sector-66, Gurugram under section 4 of
the Real Estate (Regulations and Development) Act, 2016 vide central receipt
no. 10284/19595 dated 19.05.2021 and RPIN-333. The Temp I.D. of REP – I (Part
A-H) is RERA -GRG-PROJ-852-2021. The project area for registration is 1.4625
acres (a commercial site) in a residential plotted colony. The application for
registration was scrutinized and 1st deficiency notice vide notice no.
HARERA/GGM/RPIN/333 dated 27.05.2021 was issued to the promoter with an
opportunity of being heard on 07.06.2021. The
promoter submitted a reply on 03.06.2021 in the Authority and after the
scrutiny of the reply some of the deficiencies were pending. On 07.06.2021, the
hearing was adjourned due to COVID-19 Pandemic and fixed for 08.06.2021. On
08.06.2021, the promoter is advised to remove the deficiencies and matter is
fixed for 01.07.2021. The promoter submitted the reply on 25.06.2021. After scrutiny
of the reply, some of the deficiencies are remaining which are mentioned below:
1.
The
annexures in the online application are not uploaded as well as the correction
needs to be done in the online (A-H).
2.
DPI
needs to be corrected.
3. Environment
Clearance needs to be submitted.
4. Tree
Cutting Permission/ NOC from DFO needs to be submitted.
5. Draft
Allotment letter needs to be revised.
6. Draft
BBA needs to be revised.
7. Pert
Chart needs to be revised.
8. Interest
cost to financial institution supporting document needs to be provided.
The
AR submits that the meeting for environmental clearance has already been held
and relevant copy of extract of minutes has also been attached wherein the
project has been considered for grant of EC. Further regarding Tree Cutting
Permission/NOC to DFO has been applied on 02.06.2021 and is expected to get the
same in next one week. The remaining corrections pointed out as above will also
be made in next 5 days including filling up of complete details in online DPI
and accordingly requested for a short adjournment.
The matter to come up on 15.07.2021.
Dr. K.K. Khandelwal (Chairman)
Samir Kumar (Member)
Vijay Kumar Goyal (Member) |
ADJOURNMENT |
View Order |
01-Jul-2021 |
The matter is adjourned for 02.07.2021 at 3 pm. |
ADJOURNMENT |
View Order |
08-Jun-2021 |
Deficiencies has also been conveyed to
the promoter. The promoter is advised to rectify the same. The matter to be
came up on 01.07.2021. |
ADJOURNMENT |
View Order |
07-Jun-2021 |
Hearing is fixed for 08.06.2021. |
EXAMINATION BY AUTHORITY |
View Order |