30-Jan-2023 |
Sh.
Sumeet, Engineer Executive and Ms. Asha Chartered Accountant briefed about the
facts of the case.
Sh.
Rahul Sharma (AR) is present on behalf of the promoter.
The
OC of the project after completion of the construction already stands obtained
way back in 2018(on 09.10.2018) and the requisite application for renewal of
license alongwith requisite fee and undertaking stands submitted to DTCP and
renewal of license is under consideration. The AR submits that a security
amount of Rs 25 Lakhs is being submitted on account of submission of renewed
license no. 277 of 2007 by 28.02.2023 and Rs 25 lakhs on account of submission
of approved service plan and estimates within 3 months. In case of failure, the
security amount shall be forfeited. Therefore, RC be issued subject to above
conditions and further sale in the project shall be made as per the terms and
conditions of RC. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
16-Jan-2023 |
The matter is adjourned to 30.01.2023. |
ADJOURNMENT |
View Order |
02-Jan-2023 |
Sh.
Sumeet, Engineer Executive and Ms. Asha Chartered Accountant briefed about the
facts of the case.
Sh.
Rahul Sharma (Manager) is present on behalf of the promoter.
The ARs of the promoter is
directed to remove the deficiencies and submit the deficit documents as
detailed above.
The
matter is adjourned to 16.01.2023. |
ADJOURNMENT |
View Order |
19-Dec-2022 |
The AR of the promoter is directed to remove the deficiencies. The matter to come up on 02.01.2023 |
ADJOURNMENT |
View Order |
28-Nov-2022 |
Sh.
Sumeet, Engineer Executive and Ms. Asha Chartered Accountant briefed about the
facts of the case.
Sh.
Rahul Sharma (GM) is present on behalf of the promoter.
The
AR of the promoter requests for three weeks’ time for submission of renewal of
license and approved service plan and estimates. Further, the AR of the
promoter requests to return the two cheques having no. 547736 and 577737 dated
17.10.2022 amounting to Rs 25 lakhs each submitted as a guarantee for
submission of above approvals. The Authority accepts the request.
The
matter to come up on 19.12.2022. (Sanjeev Kumar Arora)
Member, HARERA Gurugram
(Vijay Kumar Goyal)
Member, HARERA Gurugram
(Ashok Sangwan)
Member, HARERA, Gurugram
(Dr. K.K. Khandelwal)
Chairman, HARERA, Gurugram
|
ADJOURNMENT |
--- |
17-Oct-2022 |
Proceedings dated:
17.10.2022
Sh. Sumeet, Engineer
Executive and Ms. Asha Chartered Accountant briefed about the facts of the
case.
Sh. Rahul Sharma (Manager
Compliance) is present on behalf of the promoter.
License is
still not renewed.
The
matter to come up on 28.11.2022.
(Sanjeev Kumar Arora)
Member, HARERA Gurugram
(Vijay Kumar Goyal)
Member, HARERA Gurugram
(Ashok Sangwan)
Member, HARERA, Gurugram
(Dr. K.K. Khandelwal)
Chairman, HARERA, Gurugram
|
OBJECTION |
View Order |
12-Sep-2022 |
Sh.
Sumeet, Engineer Executive briefed about the facts of the case.
None
is present on behalf of the promoter. License of the promoter company stands
expired on 16.12.2019. Directions of the Authority dated 06.06.2022 with regard
to deposit of DD of Rs. 25 lakh as BG for submission of renewal of license and
approved service plan estimates has not been complied. As the promoter failed
to rectify the deficiencies and comply with the directions despite various
opportunities (more than 25 opportunities) a public notice be issued on behalf
of the Authority that no sales in this project be effected further by the
promoter and public be cautioned not to indulge in any kind of purchase and
sale in the project.
The
Authority hereby exercising the powers under section 5(1) (b) of the Act, 2016
read with rule 5(2) of the Haryana Rules, 2017
give show cause notice as why the application for grant of registration
should not be rejected and also grant an opportunity to the promoter to rectify
the defects as pointed above within a
period of 30 days from the date of
issuance of communication of such defects i.e. today 12.09.2022 and also an
opportunity of hearing on 17.10.2022 at 2.00 PM in the office of the Authority.
The matter to come up on 17.10.2022.Member (Sanjeev Kumar Arora)Member (Ashok Sangwan)Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
View Order |
17-Aug-2022 |
Ms Geeta Rathee Singh, Sr. legal officer and Sh.
Sumeet, Engineer Executive briefed about the facts of the case.
Sh.
Rahul Sharma (Manager Compliance) is present on behalf of the promoter.
The AR seeks two week time for submission
of DD required as per directions of the authority. the request is allowed. This will be last opportunity and if the promoter fails to deposit the requisite DD, the case shall be rejected and returned.
The matter to come up on 12.09.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
27-Jul-2022 |
Proceedings
dated: 27.07.2022
Sh.
Sumeet, Engineer Executive briefed about the facts of the case.
Sh.
Rahul Sharma (Manager Compliance) is present on behalf of the promoter.
The AR requests for one week for submission
of DD with a further request to allow three months’ time for submission of deficit
documents as per above.
The matter to come up on 17.08.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
25-Jul-2022 |
Proceedings
dated: 25.07.2022
Sh.
Sumeet, Engineer Executive briefed about the facts of the case.
Due
to administrative work of the Authority, the matter is adjourned to 27.07.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
06-Jun-2022 |
Sh. Ashish Kush, Planning Executive briefed about the facts of the case.
Sh. Rahul Sharma (Manager Compliance) is present on behalf of the promoter.
The authority allowed promoter to submit Demand Draft of Rs 25 Lakhs each as a bank guarantee for submission of renewal of license and approved service plan estimates within 2 months from the date of issuance of registration. In case of failure of submission of license renewal and service plan estimates within specified time, the Demand Draft will be encashed by the authority.
The matter to come up on 25.07.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
02-May-2022 |
Proceedings
dated: 02.05.2022 Sh.
Ashish Kush, Planning Executive briefed about the facts of the case.No
one is present on behalf of the promoter.
The
promoter sent an email dated 02.05.2022, requesting for 3 weeks’ time for the
compliance of the deficit documents.
The
authority decided to seek clarification from DTCP regarding the approval of
service plans and estimates that the occupation certificate was granted without
the approved service plan and estimates. The approval of service plans and estimates
shall be granted with the license or approval of building plans.
On
18.04.2022, the authority directed the promoter to submit corrected Online DPI
as per the marking made on the hard copy. Bind copies of DPI to be submitted.
The promoter was also directed to submit a bank certificate creating a lien of
HARERA to the extent of cheque amount till clearance by Authority.
The
promoter fails to comply with the directions of the Authority within the given
time. The Authority decided to issue a show cause notice as why the application
for grant of registration shall not be rejected on account of deficiencies as
mentioned above as per provisions of section 5(2)(b) of the Act, 2016 read with
rule 5(2) of Haryana Rules, 2017. If promoter has to say anything in the matter,
he may represent before the authority on 06.06.2022 at 3.00 PM in the office of
the authority or rectify deficiencies before that date.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
18-Apr-2022 |
Proceedings
dated: 18.04.2022
Sh.
Ashish Kush, Planning Executive briefed about the facts of the case.
Sh.
Rahul Sharma (AR) is present on behalf of the promoter. The AR submitted that
all the above deficiencies have been attended which needs to be checked by the
office. Online DPI also need to be corrected as per the marking made on the
hard copy. Binded copies of DPI to be submitted. The promoter applicant is
submitting two number of cheques of Rs. 25 lakhs each as security for submission
of license renewal and service plan estimates within 3 months. The promoter is
also directed to submit a bank certificate creating a lien of HARERA to the
extent of cheque amount till clearance by Authority. The Authority is
considering the registration in view of the fact that the building has been
constructed and has also obtained requisite occupation certificate from DTCP on
09.10.2018 itself and registration is being sought as CC of the project is not
obtained and OC was also obtained after coming into force of the Act.
The
matter to come up on 02.05.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
04-Apr-2022 |
Proceedings
dated: 04.04.2022
Sh.
Ashish Kush, briefed about the facts of the case.
Sh.
Rahul Sharma (Manager Compliance) is present on behalf of the promoter.
The
Authority directed the promoter to submit the bank guarantee of Rs 25 lakhs on
account of submission of license renewal and bank guarantee of Rs 25 lakhs on
account of submission of Approved service plan and estimates. The Authority
also directed the promoter to submit the deficit fee- Rs 16,96,765/- alongwith the other
deficiencies mentioned above. The matter to come up on 18.04.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
28-Feb-2022 |
Sh.
Ashish Kush, briefed about the facts of the case.
None
is present is present on behalf of the promoter. However, an e-mail request has
been received from the promoter company requesting for an adjournment of two
months’ time as the company is in process to apply for completion certificate
of the project and removal of other deficiencies conveyed by the Authority. It
is noticed that the promoter is trying to delay the process of registration on
one pretext or other instead of trying to comply with the deficiencies. One
last opportunity be given to the promoter to make compliance with the
deficiency notice already conveyed including payment of deficit fees of Rs.
16,96,765/- already demanded and a show cause notice before rejection of the application under
provisions of section 5 of the Act, 2016
be issued giving four weeks time for necessary compliance by the promoter.
The
matter to come up on 04.04.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
24-Jan-2022 |
Sh.
Ashish Kush, briefed about the facts of the case.
Sh.
Rahul Sharma (Manager) is present on behalf of the promoter. The AR request for
four week adjournment as many of their executives are suffering from COVID-19 hence
not available to fill up the requisite details in DPI.
The
matter to come up on 28.02.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
20-Dec-2021 |
Sh. Ashish Kush,
briefed about the facts of the case.
Sh. Rahul Sharma
(AR) is present on behalf of the promoter.
The promoter is
hereby afforded last opportunity to complete the deficit information and submit
requisite documents. It is surprising to note that in this case without
approval of service plans and estimates by the competent authority. The license
be immediately got renewed as per the requirement of the Act, 2016. A show
cause notice be issued to the promoter as why the application for grant of
registration shall not be rejected on account of deficiencies as mentioned
above as per provisions of section 5(2)(b) of the Act, 2016 read with rule 5(2)
of Haryana Rules, 2017. If promoter has to say anything in the matter he may
represent before the authority on 24.01.2022 at 3.00 PM in the office of the
authority or rectify deficiencies before that date.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
30-Nov-2021 |
Proceedings
dated: 30.11.2021 The hearing is adjourned and matter is fixed for 20.12.2021. |
ADJOURNMENT |
--- |
09-Nov-2021 |
Proceedings
dated: 09.11.2021
Sh.
Ashish Kush, Planning Executive briefed the facts about the project.
No one
is present on behalf of the promoter.
The AR of the promoter
requests through email for 3 weeks’ time and authority considers the same. The
matter to come up on 30.11.2021.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
19-Oct-2021 |
Sh.
Ashish Kush, Planning Executive briefed the facts about the project.
No
one is present on behalf of the promoter.
The AR of the promoter
requests through email for 3 weeks’ time and authority considers the same. The
matter to come up on 09.11.2021.Member (Samir Kumar)Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
28-Sep-2021 |
Sh.
Ashish Kush, Planning Executive briefed the facts about the project.
No
one is present on behalf of the promoter.
The Promoter M/s Countrywide Promoters Pvt. Ltd. who is a collaborator
applied for the registration of real estate project namely “Centra One” located
at Sector-61, Gurugram under section 4 of the Real Estate (Regulations and
Development) Act, 2016 vide central receipt no. 10458/18778 dated 07.04.2021
and RPIN-323. The Temp I.D. of REP – I (Part A-H) is RERA -GRG-PROJ-845-2021.
The project area for registration is same as that of the licensed area i.e.
3.675 acres vide License no – 277 of 2007 dated 17.12.2007 and the Occupation
Certificate has been obtained dated 09.10.2018 for the 18641.67sqm which
includes commercial building (Ground Floor to 14th Floor). The application for
registration was scrutinized and 1st deficiency notice vide notice no.
HARERA/GGM/RPIN/323 dated 09.04.2021 was issued to the promoter with an
opportunity of being heard on 19.04.2021, but the hearing is adjourned due to
COVID-19 Pandemic and the matter is adjourned for 23.04.2021. On 23.04.2021 the
promoter requested for the adjournment. The authority accepts the request and
fixed the matter for 17.05.2021. On 17.05.2021 the hearing is adjourned due to
COVID Pandemic and the matter is fixed for 30.06.2021. The promoter submitted
the reply on 30.06.2021. On 30.06.2021 the hearing is adjourned and fixed for
01.07.2021. On 01.07.2021, the authority advised the promoter to remove the
deficiencies and complete the online information on www.hrera.in/app1/sign_up and matter is fixed for
15.07.2021. The promoter did not submit any reply after 01.07.2021.
1. The annexures in the online application are
not uploaded as well as the correction needs to be done in the online
application (A-H).
2. DPI not filled properly.
3. Deficit Fee- Rs 16,96,765/-
4. Renewal of license no 277 of 2007 needs to
be submitted.
5. Approved Service Plans and Estimates needs
to be submitted if applied than copy of applied service plans and estimates
needs to be submitted.
6. Approvals / NOC’s from various agencies for
connecting external services like sewerage disposal, storm water drainage needs
to be submitted.
7. Electrical Load availability needs to be
submitted.
8. Non-encumbrance Certificate or ROC needs to
be submitted.
9. Copy of brochure of the project.
10. Project Report and PERT Chart needs to be
submitted.
11. REP-II needs to be submitted.
12. Draft Allotment letter is not as per the
prescribed format needs to be revised.
13. Draft Builder Buyer Agreement is not as per
the prescribed format needs to be revised.
14. Details of all three bank accounts needs to
be provided in DPI.
15. Bank undertaking duly acknowledged by bank
for operation of bank account specifying same to be 70% collection account as
per RERA rules needs to be provided.
16. Affidavit by the promoter, keeping in view
the provisions of section 4 (2) (l) (D) of the Real Estate (Regulation &
Development) Act, 2016 needs to be submitted.
On 15.07.2021, the promoter
requested for the time for compliance of the deficiencies and filing of online
DPI same was granted by the authority and matter is fixed for 03.08.2021. No
reply was submitted by the promoter till now. On 03.08.2021, the matter was
adjourned and fixed for 10.08.2021. On 10.08.2021, the matter was adjourned for
12.08.2021. On 12.08.2021, the hearing was adjourned for 17.08.2021. On
17.08.2021, the AR requested for three weeks’ time and same was granted by the
promoter and matter to come up on 07.09.2021.
The AR of the promoter
requests for 3 weeks’ time and authority considers the same. The matter to come
up on 28.09.2021. The promoter requested for the adjournment through the email.
The authority considers the request of the adjournment. The matter to come up
on 19.10.2021.Member (Samir Kumar)Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
OBJECTION |
--- |
07-Sep-2021 |
Sh.
Ashish Kush, Planning Executive briefed the facts about the project.
Sh.
Rahul Sharma (Manager) is present on behalf of the promoter.
The Promoter M/s Countrywide Promoters Pvt. Ltd. who is a collaborator
applied for the registration of real estate project namely “Centra One” located
at Sector-61, Gurugram under section 4 of the Real Estate (Regulations and
Development) Act, 2016 vide central receipt no. 10458/18778 dated 07.04.2021
and RPIN-323. The Temp I.D. of REP – I (Part A-H) is RERA -GRG-PROJ-845-2021.
The project area for registration is same as that of the licensed area i.e.
3.675 acres vide License no – 277 of 2007 dated 17.12.2007 and the Occupation
Certificate has been obtained dated 09.10.2018 for the 18641.67sqm which
includes commercial building (Ground Floor to 14th Floor). The application for
registration was scrutinized and 1st deficiency notice vide notice no.
HARERA/GGM/RPIN/323 dated 09.04.2021 was issued to the promoter with an
opportunity of being heard on 19.04.2021, but the hearing is adjourned due to
COVID-19 Pandemic and the matter is adjourned for 23.04.2021. On 23.04.2021 the
promoter requested for the adjournment. The authority accepts the request and
fixed the matter for 17.05.2021. On 17.05.2021 the hearing is adjourned due to
COVID Pandemic and the matter is fixed for 30.06.2021. The promoter submitted
the reply on 30.06.2021. On 30.06.2021 the hearing is adjourned and fixed for
01.07.2021. On 01.07.2021, the authority advised the promoter to remove the
deficiencies and complete the online information on www.hrera.in/app1/sign_up and matter is fixed for
15.07.2021. The promoter did not submit any reply after 01.07.2021.
1. The annexures in the online application are
not uploaded as well as the correction needs to be done in the online
application (A-H).
2. DPI not filled properly.
3. Deficit Fee- Rs 16,96,765/-
4. Renewal of license no 277 of 2007 needs to
be submitted.
5. Approved Service Plans and Estimates needs
to be submitted if applied than copy of applied service plans and estimates
needs to be submitted.
6. Approvals / NOC’s from various agencies for
connecting external services like sewerage disposal, storm water drainage needs
to be submitted.
7. Electrical Load availability needs to be
submitted.
8. Non-encumbrance Certificate or ROC needs to
be submitted.
9. Copy of brochure of the project.
10. Project Report and PERT Chart needs to be
submitted.
11. REP-II needs to be submitted.
12. Draft Allotment letter is not as per the
prescribed format needs to be revised.
13. Draft Builder Buyer Agreement is not as per
the prescribed format needs to be revised.
14. Details of all three bank accounts needs to
be provided in DPI.
15. Bank undertaking duly acknowledged by bank
for operation of bank account specifying same to be 70% collection account as
per RERA rules needs to be provided.
16. Affidavit by the promoter, keeping in view
the provisions of section 4 (2) (l) (D) of the Real Estate (Regulation &
Development) Act, 2016 needs to be submitted.
On 15.07.2021, the promoter
requested for the time for compliance of the deficiencies and filing of online
DPI same was granted by the authority and matter is fixed for 03.08.2021. No
reply was submitted by the promoter till now. On 03.08.2021, the matter was
adjourned and fixed for 10.08.2021. On 10.08.2021, the matter was adjourned for
12.08.2021. On 12.08.2021, the hearing was adjourned for 17.08.2021. On
17.08.2021, the AR requested for three weeks’ time and same was granted by the
promoter and matter to come up on 07.09.2021.
The AR of the promoter
requests for 3 weeks’ time and authority considers the same. The matter to come
up on 28.09.2021.Member (Samir Kumar)Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
OBJECTION |
--- |
17-Aug-2021 |
Sh.
Ashish Kush, Planning Executive briefed the facts about the project.
Sh.
Rahul Sharma (Manager) is present on behalf of the promoter.
The Promoter M/s Countrywide Promoters Pvt. Ltd. who is a collaborator
applied for the registration of real estate project namely “Centra One” located
at Sector-61, Gurugram under section 4 of the Real Estate (Regulations and
Development) Act, 2016 vide central receipt no. 10458/18778 dated 07.04.2021
and RPIN-323. The Temp I.D. of REP – I (Part A-H) is RERA -GRG-PROJ-845-2021.
The project area for registration is same as that of the licensed area i.e.
3.675 acres vide License no – 277 of 2007 dated 17.12.2007 and the Occupation
Certificate has been obtained dated 09.10.2018 for the 18641.67sqm which
includes commercial building (Ground Floor to 14th Floor). The application for
registration was scrutinized and 1st deficiency notice vide notice no.
HARERA/GGM/RPIN/323 dated 09.04.2021 was issued to the promoter with an
opportunity of being heard on 19.04.2021, but the hearing is adjourned due to
COVID-19 Pandemic and the matter is adjourned for 23.04.2021. On 23.04.2021 the
promoter requested for the adjournment. The authority accepts the request and
fixed the matter for 17.05.2021. On 17.05.2021 the hearing is adjourned due to
COVID Pandemic and the matter is fixed for 30.06.2021. The promoter submitted
the reply on 30.06.2021. On 30.06.2021 the hearing is adjourned and fixed for
01.07.2021. On 01.07.2021, the authority advised the promoter to remove the
deficiencies and complete the online information on www.hrera.in/app1/sign_up and matter is fixed for
15.07.2021. The promoter did not submit any reply after 01.07.2021.
1. The annexures in the online application are
not uploaded as well as the correction needs to be done in the online
application (A-H).
2. DPI not filled properly.
3. Deficit Fee- Rs 16,96,765/-
4. Renewal of license no 277 of 2007 needs to
be submitted.
5. Approved Service Plans and Estimates needs
to be submitted if applied than copy of applied service plans and estimates
needs to be submitted.
6. Approvals / NOC’s from various agencies for
connecting external services like sewerage disposal, storm water drainage needs
to be submitted.
7. Electrical Load availability needs to be
submitted.
8. Non-encumbrance Certificate or ROC needs to
be submitted.
9. Copy of brochure of the project.
10. Project Report and PERT Chart needs to be
submitted.
11. REP-II needs to be submitted.
12. Draft Allotment letter is not as per the
prescribed format needs to be revised.
13. Draft Builder Buyer Agreement is not as per
the prescribed format needs to be revised.
14. Details of all three bank accounts needs to
be provided in DPI.
15. Bank undertaking duly acknowledged by bank
for operation of bank account specifying same to be 70% collection account as
per RERA rules needs to be provided.
16. Affidavit by the promoter, Keeping in view
the provisions of section 4 (2) (l) (D) of the Real Estate (Regulation &
Development) Act, 2016 needs to be submitted.
On 15.07.2021, the promoter
requested for the time for compliance of the deficiencies and filing of online
DPI same was granted by the authority and matter is fixed for 03.08.2021. No
reply was submitted by the promoter till now. On 03.08.2021, the matter was
adjourned and fixed for 10.08.2021. On 10.08.2021, the matter was adjourned for
12.08.2021. On 12.08.2021, the matter was adjourned and fixed for 17.08.2021.
On
the request of the AR of the promoter three weeks’ time is granted.
The matter to come up on 07.09.2021.Member (Samir Kumar)Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
12-Aug-2021 |
Matter adjourned for 17.08.2021 |
ADJOURNMENT |
--- |
10-Aug-2021 |
Matter adjourned for 12.08.2021 |
ADJOURNMENT |
--- |
03-Aug-2021 |
Due to Covid-19 pandemic, authority meeting could not be held. Now, the authority has decided to fix the matter on 10.08.2021. |
OBJECTION |
--- |
15-Jul-2021 |
Sh. Ashish Kush, Planning Executive briefed
the facts about the project.
Sh. Rahul Sharma (Manager) is present on
behalf of the promoter.
The Promoter M/s Countrywide Promoters Pvt.
Ltd. who is a collaborator applied for the registration of real estate project
namely “Centra One” located at Sector-61, Gurugram under section 4 of the Real
Estate (Regulations and Development) Act, 2016 vide central receipt no.
10458/18778 dated 07.04.2021 and RPIN-323. The Temp I.D. of REP – I (Part A-H)
is RERA -GRG-PROJ-845-2021. The project area for registration is same as that
of the licensed area i.e. 3.675 acres vide License no – 277 of 2007 dated
17.12.2007 and the Occupation Certificate has been obtained dated 09.10.2018
for the 18641.67sqm which includes commercial building (Ground Floor to 14th
Floor). The application for registration was scrutinized and 1st deficiency
notice vide notice no. HARERA/GGM/RPIN/323 dated 09.04.2021 was issued to the
promoter with an opportunity of being heard on 19.04.2021, but the hearing is
adjourned due to COVID-19 Pandemic and the matter is adjourned for 23.04.2021.
On 23.04.2021 the promoter requested for the adjournment. The authority accepts
the request and fixed the matter for 17.05.2021. On 17.05.2021 the hearing is
adjourned due to COVID Pandemic and the matter is fixed for 30.06.2021. The
promoter submitted the reply on 30.06.2021. On 30.06.2021 the hearing is
adjourned and fixed for 01.07.2021. On 01.07.2021, the authority advised the
promoter to remove the deficiencies and complete the online information on www.hrera.in/app1/sign_up and matter is fixed for 15.07.2021. The promoter did not submit any
reply after 01.07.2021. The deficiencies still remaining as mentioned below:
1.
The
annexures in the online application are not uploaded as well as the correction
needs to be done in the online application (A-H).
2.
DPI
not filled properly.
3.
Deficit
Fee- Rs 16,96,765/-
4.
Renewal
of license no 277 of 2007 needs to be submitted.
5.
Approved
Service Plans and Estimates needs to be submitted if applied than copy of
applied service plans and estimates needs to be submitted.
6.
Approvals
/ NOC’s from various agencies for connecting external services like sewerage
disposal, storm water drainage needs to be submitted.
7.
Electrical
Load availability needs to be submitted.
8.
Non-encumbrance
Certificate or ROC needs to be submitted.
9.
Copy
of brochure of the project.
10.
Project
Report and PERT Chart needs to be submitted.
11.
REP-II
needs to be submitted.
12.
Draft
Allotment letter is not as per the prescribed format needs to be revised.
13.
Draft
Builder Buyer Agreement is not as per the prescribed format needs to be
revised.
14.
Details
of all three bank accounts needs to be provided in DPI.
15.
Bank
undertaking duly acknowledged by bank for operation of bank account specifying
same to be 70% collection account as per RERA rules needs to be provided.
16.
Affidavit
by the promoter, Keeping in view the provisions of section 4 (2) (l) (D) of the
Real Estate (Regulation & Development) Act, 2016 needs to be submitted.
The promoter requested for the time for compliance
of the deficiencies and filing of online DPI. On request of the promoter the
authority considered the request and the matter to come up on 03.08.2021.Member (Vijay Kumar Goyal)Member (Samir Kumar)Chairman (Dr. K.K. Khandelwal) |
OBJECTION |
--- |
01-Jul-2021 |
Sh. Ashish Kush, Planning Executive briefed the
facts about the project.
Sh. Rahul Sharma (Manager) is present on behalf
of the promoter.
The promoter M/s Countrywide
Promoters Pvt. Ltd. who is a collaborator applied for the registration of real
estate project namely “Centra One” located at Sector-61, Gurugram under section
4 of the Real Estate (Regulations and Development) Act, 2016 vide central
receipt no. 10458/18778 dated 07.04.2021 and RPIN-323. The Temp I.D. of REP – I
(Part A-H) is RERA -GRG-PROJ-845-2021. The project area for registration is
same as that of the licensed area i.e. 3.675 acres vide License no – 277 of
2007 dated 17.12.2007 and the Occupation Certificate has been obtained dated
09.10.2018 for the 18641.67sqm which includes commercial building (Ground Floor
to 14th Floor). The application for registration was scrutinized and 1st
deficiency notice vide notice no. HARERA/GGM/RPIN/323 dated 09.04.2021 was
issued to the promoter with an opportunity of being heard on 19.04.2021, but
the hearing is adjourned due to COVID-19 Pandemic and the matter is adjourned
for 23.04.2021. On 23.04.2021 the promoter requested for the adjournment. The
authority accepts the request and fixed the matter for 17.05.2021. On
17.05.2021 the hearing is adjourned due to COVID Pandemic and the matter is
fixed for 30.06.2021.
The promoter submitted the
reply on 30.06.2021. On 30.06.2021 the hearing is adjourned and fixed for
01.07.2021. On scrutiny of reply some deficiencies are still remaining which
are mentioned below:
1.
The
annexures in the online application are not uploaded as well as the correction
needs to be done in the online application (A-H).
2.
DPI not filled properly.
3.
Deficit Fee- Rs 16,96,765/-
4.
Renewal of license no 277 of 2007 needs to be submitted.
5.
Approved Service Plans and Estimates needs to be submitted if applied
than copy of applied service plans and estimates needs to be submitted.
6.
Approvals / NOC’s from various agencies for connecting external services
like sewerage disposal, storm water drainage needs to be submitted.
7.
Electrical Load availability needs to be submitted.
8.
Non-encumbrance Certificate or ROC needs to be submitted.
9.
Copy of brochure of the project.
10.
Project Report and PERT Chart needs to be submitted.
11.
REP-II needs to be submitted.
12.
Draft Allotment letter is not as per the prescribed format needs to be
revised.
13. Draft Builder Buyer Agreement
is not as per the prescribed format needs to be revised.
14. Details of all three bank
accounts needs to be provided in DPI.
15. Bank undertaking duly
acknowledged by bank for operation of bank account specifying same to be 70%
collection account as per RERA rules needs to be provided.
16. Affidavit by the promoter,
Keeping in view the provisions of section 4 (2) (l) (D) of the Real Estate
(Regulation & Development) Act, 2016 needs to be submitted.
The
promoter is advised to complete online information on www.hrera.in/app1/sign_up. The matter to come up on 15.07.2021.Member (Vijay Kumar Goyal)Member (Samir Kumar)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
30-Jun-2021 |
The matter
is Adjourned for 01.07.2021. |
ADJOURNMENT |
--- |
17-May-2021 |
Due to COVID-19 Pandemic, the matter
is Adjourned for 30.06.2021. |
ADJOURNMENT |
--- |
23-Apr-2021 |
Sh. Ashish Kush, Planning Executive briefed about the project.No one is present on behalf of the promoter. An e-mail request has been received for adjournment in the matter due to lock-down situation in Delhi. Matter to come up on 17.05.2021.The promoter is advised to rectify the deficiencies and submit deficit documents. Dr. K.K.Khandelwal (Chairman)Samir Kumar (Member)Vijay Kumar Goyal (Member) |
ADJOURNMENT |
--- |
19-Apr-2021 |
Due to COVID-19 Pandemic, the matter is Adjourned for 23-04-2021 |
EXAMINATION BY AUTHORITY |
--- |