| 03-Feb-2023 |
Ms. Asha, Chartered Accountant briefed about the
project.
Mr. Anitesh Singh
(Manager) is present on behalf of the promoter.
The AR of the
promoter stated that the occupation certificate for the project has already
been obtained vide dated 31.03.2022.
The AR of the
promoter admitted the violation of section 4(2)(l)(C) and after hearing him on
quantum of penalty the Authority decided to impose a penalty of Rs. 25 lakh. The
penalty be deposited with the Authority within a period of one month.
The Authority
decides to permit the registration to remain in force upto 31.12.2023. It is
without prejudice to the rights of the allottees accrued on account of the
delay in handing over of possession of units as per the date specified in the
Builder Buyer Agreement. |
EXTENSION APPROVED |
View Order |
| 31-Jan-2023 |
The matter is adjourned to 14.02.2023. On request of the promoter, the matter is preponed to 03.02.2023 for hearing. |
ADJOURNMENT |
View Order |
| 17-Jan-2023 |
The authorized representative of the promoter is advised to rectify the deficiencies and submit the deficit fee (if any) along with the deficit documents apart from the filing of information in online detailed project information. The matter is adjourned to 31.01.2023 |
ADJOURNMENT |
View Order |
| 03-Jan-2023 |
The authorized representative of the promoter is advised to rectify the deficiencies and submit the deficit fee (if any) along with the deficit documents apart from the filing of information in online detailed project information. The matter is adjourned to 17.01.2023 |
ADJOURNMENT |
View Order |
| 19-Dec-2022 |
Matter to come up on 03.01.2023 |
ADJOURNMENT |
View Order |
| 15-Nov-2022 |
Proceedings
dated 15.11.2022
Ms. Asha, Chartered Accountant briefed about
the project.
Mr. Anitesh Singh (Manager) is present on behalf of the promoter. The AR
submits that out of 2/3rd allottees i.e. 120, consent of about 97
unit holders have been obtained and the company is in process of obtaining
the consent of remaining allottees as well and hence seeks a 4 weeks
adjournment for their submission.
Matter to come up on 19.12.2022.
|
OBJECTION |
--- |
| 18-Oct-2022 |
Proceedings dated 18.10.2022
Ms. Asha, Chartered Accountant briefed about the
project.
Mr. Anitesh
Singh (Manager) is present on behalf of the promoter.
The promoter has not submitted the consent
of 2/3rd allottees of the project on account of revision of building
plan.
The AR of the promoter seeks a short
adjournment for providing the consent of 2/3rd allottees on account
of revision of building plan. Last opportunity is granted.
Matter to come
up on 15.11.2022. |
OBJECTION |
--- |
| 28-Sep-2022 |
Ms. Asha, Chartered Accountant briefed about the
project.
Mr. Anitesh
Singh (Manager) is present on behalf of the promoter.
Deficiencies
have already been communicated. Promoter is advised to submit deficient
documents, as detailed above.
Matter to come
up on 18.10.2022. |
ADJOURNMENT |
--- |
| 13-Sep-2022 |
Sh. Naresh Kumar,
Chartered Accountant and Ms. Asha,
Chartered Accountant briefed about the project.
Mr. Anitesh
Singh (Manager) is present on behalf of the promoter. The AR of the
promoter submitted that they are in process of obtaining consent of 2/3rd of the allottees regarding revised sanctioned
plan and requested for adjournment.
The matter to come
up on 28.09.2022. |
ADJOURNMENT |
--- |
| 23-Aug-2022 |
MATTER IS ADJOURNED TO 13.09.2022. |
ADJOURNMENT |
--- |
| 09-Aug-2022 |
Sh. Asha and Sh. Naresh
Kumar chartered accountant is brief about the project on behalf of the
authority and Sh. Laxmi Kant Saini (Expert/consultant) has been present on
behalf of the authority.
Sh Anitesh Singh
Chauhan (manager) is present on behalf of the promoter.
The present
application is for continuation of the registration under section 7(3). The
initial registration for the project was granted by Interim RERA Panchkula in
2017 and was valid upto 30.06.2020 + 6 months COVID 19 i.e., 30.12.2020. Although,
the applicant promoter has obtained OC for the entire building which is
constructed at site. But it is noticed that the above application has included
FAR under TOD Policy which otherwise has not yet been got registered and hence
continuation of the project u/s 7(3) for this extra covered area cannot be
considered. The office to re-examine and submit the matter with details of
extra covered area allowed and status of consents obtained for this extra FAR
from the existing allottees.
The matter to be come
up on 23.08.2022. |
ADJOURNMENT |
--- |
| 04-Aug-2022 |
The matter is adjourned for 09.08.2022 |
ADJOURNMENT |
--- |
| 02-Aug-2022 |
The matter is adjourned for 04.08.2022 |
ADJOURNMENT |
--- |
| 21-Jul-2022 |
Sh. Asha and Sh. Naresh
Kumar chartered accountant is brief about the project on behalf of the
authority and Sh Laxmi Kant Saini (Expert/consultant) has been present on
behalf of the authority. Sh Anitesh Singh Chauhan (manager) is present on
behalf of the promoter. As
the authority has taken a general decision to issue public notice regarding
inviting objection before permitting permission under section 7(3) of the Act,
2016.The
matter be come up on 02.08.2022. |
ADJOURNMENT |
--- |
| 12-Jul-2022 |
Sh. Asha and Sh. Naresh Kumar chartered accountant
is brief about the project on
behalf of the authority and Sh Laxmi Kant Saini (Expert/consultant) has been
present on behalf of the authority. Sh Anitesh Singh Chauhan (Manager) is
present on behalf of the promoter. The promoter has requested one more year for
the completion of the said project. Hence, the deficiency fees would increase
by 4,73,336/- the promoter agreed to pay the deficit fees with in 7 days.
Keeping in view of the above and recommendation made by the expert/consultant
and chartered accountant of the authority, the authority has decided to permit
the registration certificate remain in force subject to submission of requisite
fees.The matter be come up on 21.07.2022. |
ADJOURNMENT |
--- |
| 05-Jul-2022 |
Naresh Kumar chartered
accountant is brief about the project on behalf of the authority. No one is
present on behalf of the promoter. The promoter is directed to attend to the
deficiencies before the next date of hearing. The matter to come up on 12.07.2022. |
ADJOURNMENT |
--- |
| 13-May-2022 |
The matter adjourned for 05.07.2022 |
ADJOURNMENT |
--- |
| 11-Apr-2022 |
The matter adjourned for 13.05.2022 |
ADJOURNMENT |
--- |
| 04-Apr-2022 |
The matter adjourned for 11.04.2022 |
ADJOURNMENT |
--- |
| 02-Apr-2022 |
The matter adjourned for 04.04.2022 |
ADJOURNMENT |
--- |
| 28-Mar-2022 |
Sh. Naresh Kumar, CA briefed about the facts of the case. Sh. Anitesh Singh (Deputy Manager) is present on behalf of the promoter. The promoter was asked to submit clarification regarding cost of land and total project cost. The matter will come up on 02.04.2022 |
ADJOURNMENT |
--- |
| 28-Feb-2022 |
The matter adjourned for 28.03.2022 |
ADJOURNMENT |
--- |
| 25-Jan-2022 |
Sh. Anitesh Singh (Deputy Manager) is present on behalf of the promoter. The Authority directed the promoter to submit the deficit documents & correction in the online DPI. The matter will be come up on 28.02.2022 |
ADJOURNMENT |
--- |
| 12-Jan-2022 |
The matter will be come up on 25.01.2022 |
ADJOURNMENT |
--- |
| 22-Dec-2021 |
Sh. Ashish Kush,
Planning Executive briefed about the facts of the case.
Sh. Anitesh Singh
(Deputy Manager) is present on behalf of the promoter.
Following remaining
deficiencies are mentioned below:
1.
License no. 163 of 2008 dated 19.09.2008
valid up to 18.08.2010. Renewal of license needs to be submitted -AR informed
that license has been renewed. Copy submitted.
2.
Copy of original and revised service
plans and estimates not provided – AR informed that copy of approval will be
submitted within a week.
3.
Copy of revised BR-III, needs to be
submitted – AR informed that copy of approval revised BR III received from DTCP
and same has been submitted.
4. Financial viability of
the project needs to be provided – In REP file figures are to be matched with
DPI.
As most of the information is complete
except some information to be upgraded keeping in view the factual status as on
today. The permissible maximum time period under section 6 is one year over and
above the original time period allowed at the time of registration. Keeping in
view the status of completion of the project and in the interest of allottees
and completion of the project authority may consider their application under
section 7(3) for permitting registration to remain in force subject to further
terms and conditions that may be imposed by the authority and binding on the
promoter in the interest of the allottees.
The matter to come up on
12.01.2022..Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman) |
ADJOURNMENT |
--- |
| 23-Aug-2021 |
The authority
directed the promoter to submit the deficit documents. The matter to come up on
22.12.2021..Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman) |
OBJECTION |
--- |
| 20-Jul-2021 |
Sh. Ashish Kush, Planning Executive briefed the
facts about the project.
Sh. Rohit (AR) is present on behalf of the
promoter.
The Promoter M/s Emaar India Ltd. who is a
collaborator applied for the extension of registration
of real estate project namely “Emaar Colonnade” located at Sector-66, Gurugram
under section 6 of the Real Estate (Regulations and Development) Act, 2016 vide
central receipt no. 9482/17012 dated 02.03.2021 and RPIN-305. The Temp I.D. of
REP – I (Part A-H) is RERA -GRG-PROJ-644-2020 and online generated for project
extension temp id RERA-GRG-838-2021. The project area for registration is same
as that of the licensed area i.e. 2.25 acres. License no – 163 of 2008 dated
19.08.2008. The application for extension of registration was scrutinized and 1st
deficiency notice vide notice no. HARERA/GGM/REP/RC/156/2017/EXT/305/2021 dated
10.03.2021 was issued to the promoter with an opportunity of being heard on
22.03.2021. On 22.03.2021 the promoter submitted a reply and requested for 15
days for removing the deficiencies. The authority considered the request and
matter is fixed for 05.04.2021. On 05.04.2021, the authority decided to impose
a penalty of Rs 5.00 lac and matter is fixed for 10.05.2021. On 10.05.2021, the
hearing was adjourned and matter was fixed for 20.07.2021. On 14.07.2021, the
promoter submits a reply which was scrutinized and deficiencies are mentioned
below:
1.
License no. 163 of 2008 dated 19.09.2008
valid up to 18.08.2010. Renewal of license needs to be submitted.
2.
Copy of original and revised service
plans and estimates not provided.
3.
Copy of earlier approved and revised
BR-III, needs to be submitted.
4.
Copy of original environmental clearance
needs to be submitted.
5.
Audit report under section 4(2)(l)(d)
for the financial year 2018-19 needs to be provided as per new format.
6.
Certificate of engineer, architect provided. However,
needs to be clarified and CA certificate at the time of last withdrawal needs
to be submitted.
7.
Financial viability of the project needs to be provided.
The promoter also
requested to condone the penalty of Rs 5.00 lac which was imposed on the
promoter.
A show cause
notice be issued to the promoter as why their application for extension of
registration shall not be rejected on account of deficiencies mentioned above
as per provisions of section 6 of the Real Estate (Regulation and Development)
Act, 2016.
The request for
waiver of penalty is declined and the promoter is directed to submit the
penalty of Rs. 5.00 lakh within a week. The reasons for delay in implementing
the project and failure to complete the same within the time period declared by
the promoter under section 4(2)(l)(C) found not to be reasonable and with
sufficient cause. Show cause notice be issued as why penal proceeding be not
issued for violation of section 4 and for not completing the project within the
period declared by the promoter under section 4(2)(l)(C).
The matter to come up on 23.08.2021.Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman) |
ADJOURNMENT |
--- |
| 10-May-2021 |
The hearing is adjourned and fixed for 20.07.2021. |
OBJECTION |
--- |
| 05-Apr-2021 |
No one is present on behalf of the promoter. No information received regarding non appearance. Ms. Jyoti Yadav Coordinator Planning read out the proceedings of the last hearing as under:"Deficiencies have already been conveyed to the promoter and as per the statement by the AR reply regarding compliances has been submitted today which needs to be examined by the office. No building plans have been submitted so far and it has been informed that their building plan are under revision and in principal approval has been given. The license has already expired. As per the office record the license approval documents have been submitted only upto 18.8.2010 but as per statement of AR their license is renewed upto 18.8.2020 and renewal has been applied after depositing due amount. It is surprising that service plan and estimates of the project has not been approved so far which is a serious lapse on the part of the promoter. Now the promoter is directed to get the service plan and estimates approved on the basis of revised building plan. On the request of the promoter 15 days period is granted for compliance. Matter to come up on 05.04.2021"No compliance of the orders of the Authority has been made. A penalty of Rs. 5.00 lac is imposed. Keeping in view the glaring deficiencies the Authority decided to issue show cause notice as why the application for grant of extension shall not be rejected for the reasons as above as this application does not conform to the provisions of the Act, Rules and regulations made thereunder. The promoter is hereby given an opportunity of being heard in the matter on 10.05.2021 at 2.00 PM in the Conference Room of the Authority. (Dr. K.K.Khandelwal) Chairman(Samir Kumar) Member(Vijay Kumar Goyal) Member |
OBJECTION |
--- |
| 22-Mar-2021 |
Ms. Roli Aggarwal, (GM) and Sh. Rohit Mehta, (GM- Govt.Affairs) are present on behalf of the promoter. Deficiencies have already been conveyed to the promoter and as per the statement by the AR reply regarding compliances has been submitted today which needs to be examined by the office. No building plans have been submitted so far and it has been informed that their building plan are under revision and in principal approval has been given. The license has already expired. As per the office record the license approval documents have been submitted only upto 18.8.2010 but as per statement of AR their license is renewed upto 18.8.2020 and renewal has been applied after depositing due amount. It is surprising that service plan and estimates of the project has not been approved so far which is a serious lapse on the part of the promoter. Now the promoter is directed to get the service plan and estimates approved on the basis of revised building plan. On the request of the promoter 15 days period is granted for compliance. Matter to come up on 5.4.2021. |
EXAMINATION BY AUTHORITY |
--- |