Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
Colonnade Sector-66, village badshahpur, gurugram GURUGRAM Emaar mgf land ltd.
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-838-2021 12-Mar-2021 12-Mar-2021 EXTENSION APPROVED NOT REQUIRED Not Yet -- 1st deficiency notice sent on 10.03.2021
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
03-Feb-2023 Ms.  Asha, Chartered Accountant briefed about the project. Mr. Anitesh Singh (Manager) is present on behalf of the promoter.  The AR of the promoter stated that the occupation certificate for the project has already been obtained vide dated 31.03.2022. The AR of the promoter admitted the violation of section 4(2)(l)(C) and after hearing him on quantum of penalty the Authority decided to impose a penalty of Rs. 25 lakh. The penalty be deposited with the Authority within a period of one month. The Authority decides to permit the registration to remain in force upto 31.12.2023. It is without prejudice to the rights of the allottees accrued on account of the delay in handing over of possession of units as per the date specified in the Builder Buyer Agreement.  EXTENSION APPROVED View Order
31-Jan-2023 The matter is adjourned to 14.02.2023. On request of the promoter, the matter is preponed to 03.02.2023 for hearing. ADJOURNMENT View Order
17-Jan-2023 The authorized representative of the promoter is advised to rectify the deficiencies and submit the deficit fee (if any) along with the deficit documents apart from the filing of information in online detailed project information.  The matter is adjourned to 31.01.2023 ADJOURNMENT View Order
03-Jan-2023 The authorized representative of the promoter is advised to rectify the deficiencies and submit the deficit fee (if any) along with the deficit documents apart from the filing of information in online detailed project information.  The matter is adjourned to 17.01.2023 ADJOURNMENT View Order
19-Dec-2022 Matter to come up on 03.01.2023           ADJOURNMENT View Order
15-Nov-2022 Proceedings dated 15.11.2022 Ms.  Asha, Chartered Accountant briefed about the project. Mr. Anitesh Singh (Manager) is present on behalf of the promoter. The AR submits that out of 2/3rd allottees i.e. 120, consent of about 97 unit holders have been obtained and the company is in process of obtaining the consent of remaining allottees as well and hence seeks a 4 weeks adjournment for their submission. Matter to come up on 19.12.2022.     OBJECTION ---
18-Oct-2022 Proceedings dated 18.10.2022 Ms.  Asha, Chartered Accountant briefed about the project. Mr. Anitesh Singh (Manager) is present on behalf of the promoter.  The promoter has not submitted the consent of 2/3rd allottees of the project on account of revision of building plan. The AR of the promoter seeks a short adjournment for providing the consent of 2/3rd allottees on account of revision of building plan. Last opportunity is granted. Matter to come up on 15.11.2022. OBJECTION ---
28-Sep-2022 Ms.  Asha, Chartered Accountant briefed about the project. Mr. Anitesh Singh (Manager) is present on behalf of the promoter.  Deficiencies have already been communicated. Promoter is advised to submit deficient documents, as detailed above. Matter to come up on 18.10.2022. ADJOURNMENT ---
13-Sep-2022 Sh. Naresh Kumar, Chartered Accountant and Ms.  Asha, Chartered Accountant briefed about the project. Mr. Anitesh Singh (Manager) is present on behalf of the promoter. The AR of the promoter submitted that they are in process of obtaining  consent of 2/3rd  of the allottees regarding revised sanctioned plan and requested for adjournment. The matter to come up on 28.09.2022.  ADJOURNMENT ---
23-Aug-2022 MATTER IS ADJOURNED TO 13.09.2022. ADJOURNMENT ---
09-Aug-2022 Sh. Asha and Sh. Naresh Kumar chartered accountant is brief about the project on behalf of the authority and Sh. Laxmi Kant Saini (Expert/consultant) has been present on behalf of the authority.  Sh Anitesh Singh Chauhan (manager) is present on behalf of the promoter. The present application is for continuation of the registration under section 7(3). The initial registration for the project was granted by Interim RERA Panchkula in 2017 and was valid upto 30.06.2020 + 6 months COVID 19 i.e., 30.12.2020. Although, the applicant promoter has obtained OC for the entire building which is constructed at site. But it is noticed that the above application has included FAR under TOD Policy which otherwise has not yet been got registered and hence continuation of the project u/s 7(3) for this extra covered area cannot be considered. The office to re-examine and submit the matter with details of extra covered area allowed and status of consents obtained for this extra FAR from the existing allottees. The matter to be come up on 23.08.2022. ADJOURNMENT ---
04-Aug-2022 The matter is adjourned for 09.08.2022 ADJOURNMENT ---
02-Aug-2022 The matter is adjourned for 04.08.2022 ADJOURNMENT ---
21-Jul-2022 Sh. Asha and Sh. Naresh Kumar chartered accountant is brief about the project on behalf of the authority and Sh Laxmi Kant Saini (Expert/consultant) has been present on behalf of the authority. Sh Anitesh Singh Chauhan (manager) is present on behalf of the promoter. As the authority has taken a general decision to issue public notice regarding inviting objection before permitting permission under section 7(3) of the Act, 2016.The matter be come up on 02.08.2022. ADJOURNMENT ---
12-Jul-2022 Sh. Asha and Sh. Naresh Kumar chartered accountant is brief about the project on behalf of the authority and Sh Laxmi Kant Saini (Expert/consultant) has been present on behalf of the authority. Sh Anitesh Singh Chauhan (Manager) is present on behalf of the promoter. The promoter has requested one more year for the completion of the said project. Hence, the deficiency fees would increase by 4,73,336/- the promoter agreed to pay the deficit fees with in 7 days. Keeping in view of the above and recommendation made by the expert/consultant and chartered accountant of the authority, the authority has decided to permit the registration certificate remain in force subject to submission of requisite fees.The matter be come up on 21.07.2022. ADJOURNMENT ---
05-Jul-2022 Naresh Kumar chartered accountant is brief about the project on behalf of the authority. No one is present on behalf of the promoter. The promoter is directed to attend to the deficiencies before the next date of hearing. The matter to come up on 12.07.2022. ADJOURNMENT ---
13-May-2022  The matter adjourned for 05.07.2022 ADJOURNMENT ---
11-Apr-2022  The matter adjourned for 13.05.2022 ADJOURNMENT ---
04-Apr-2022  The matter adjourned for 11.04.2022 ADJOURNMENT ---
02-Apr-2022  The matter adjourned for 04.04.2022 ADJOURNMENT ---
28-Mar-2022  Sh. Naresh Kumar, CA briefed about the facts of the case. Sh. Anitesh Singh (Deputy Manager) is present on behalf of the promoter. The promoter was  asked to submit clarification regarding cost of land and total project cost. The matter will come up on 02.04.2022 ADJOURNMENT ---
28-Feb-2022  The matter adjourned for 28.03.2022 ADJOURNMENT ---
25-Jan-2022  Sh. Anitesh Singh (Deputy Manager) is present on behalf of the promoter. The Authority directed the promoter to submit the deficit documents & correction in the online DPI. The matter will be come up on 28.02.2022 ADJOURNMENT ---
12-Jan-2022 The matter will be come up on 25.01.2022 ADJOURNMENT ---
22-Dec-2021 Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Anitesh Singh (Deputy Manager) is present on behalf of the promoter. Following remaining deficiencies are mentioned below: 1.       License no. 163 of 2008 dated 19.09.2008 valid up to 18.08.2010. Renewal of license needs to be submitted -AR informed that license has been renewed. Copy submitted. 2.       Copy of original and revised service plans and estimates not provided – AR informed that copy of approval will be submitted within a week. 3.       Copy of revised BR-III, needs to be submitted – AR informed that copy of approval revised BR III received from DTCP and same has been submitted. 4.       Financial viability of the project needs to be provided – In REP file figures are to be matched with DPI. As most of the information is complete except some information to be upgraded keeping in view the factual status as on today. The permissible maximum time period under section 6 is one year over and above the original time period allowed at the time of registration. Keeping in view the status of completion of the project and in the interest of allottees and completion of the project authority may consider their application under section 7(3) for permitting registration to remain in force subject to further terms and conditions that may be imposed by the authority and binding on the promoter in the interest of the allottees. The matter to come up on 12.01.2022..Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman) ADJOURNMENT ---
23-Aug-2021 The authority directed the promoter to submit the deficit documents. The matter to come up on 22.12.2021..Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman) OBJECTION ---
20-Jul-2021 Sh. Ashish Kush, Planning Executive briefed the facts about the project. Sh. Rohit (AR) is present on behalf of the promoter. The Promoter M/s Emaar India Ltd. who is a collaborator applied for the extension of registration of real estate project namely “Emaar Colonnade” located at Sector-66, Gurugram under section 6 of the Real Estate (Regulations and Development) Act, 2016 vide central receipt no. 9482/17012 dated 02.03.2021 and RPIN-305. The Temp I.D. of REP – I (Part A-H) is RERA -GRG-PROJ-644-2020 and online generated for project extension temp id RERA-GRG-838-2021. The project area for registration is same as that of the licensed area i.e. 2.25 acres. License no – 163 of 2008 dated 19.08.2008. The application for extension of registration was scrutinized and 1st deficiency notice vide notice no. HARERA/GGM/REP/RC/156/2017/EXT/305/2021 dated 10.03.2021 was issued to the promoter with an opportunity of being heard on 22.03.2021. On 22.03.2021 the promoter submitted a reply and requested for 15 days for removing the deficiencies. The authority considered the request and matter is fixed for 05.04.2021. On 05.04.2021, the authority decided to impose a penalty of Rs 5.00 lac and matter is fixed for 10.05.2021. On 10.05.2021, the hearing was adjourned and matter was fixed for 20.07.2021. On 14.07.2021, the promoter submits a reply which was scrutinized and deficiencies are mentioned below: 1.      License no. 163 of 2008 dated 19.09.2008 valid up to 18.08.2010. Renewal of license needs to be submitted. 2.      Copy of original and revised service plans and estimates not provided. 3.      Copy of earlier approved and revised BR-III, needs to be submitted. 4.      Copy of original environmental clearance needs to be submitted. 5.      Audit report under section 4(2)(l)(d) for the financial year 2018-19 needs to be provided as per new format. 6.      Certificate of engineer, architect provided. However, needs to be clarified and CA certificate at the time of last withdrawal needs to be submitted.   7.      Financial viability of the project needs to be provided. The promoter also requested to condone the penalty of Rs 5.00 lac which was imposed on the promoter. A show cause notice be issued to the promoter as why their application for extension of registration shall not be rejected on account of deficiencies mentioned above as per provisions of section 6 of the Real Estate (Regulation and Development) Act, 2016. The request for waiver of penalty is declined and the promoter is directed to submit the penalty of Rs. 5.00 lakh within a week. The reasons for delay in implementing the project and failure to complete the same within the time period declared by the promoter under section 4(2)(l)(C) found not to be reasonable and with sufficient cause. Show cause notice be issued as why penal proceeding be not issued for violation of section 4 and for not completing the project within the period declared by the promoter under section 4(2)(l)(C). The matter to come up on 23.08.2021.Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman) ADJOURNMENT ---
10-May-2021 The hearing is adjourned and fixed for 20.07.2021. OBJECTION ---
05-Apr-2021 No one is present on behalf of the promoter. No information received regarding non appearance. Ms. Jyoti Yadav Coordinator Planning read out the proceedings of the last hearing as under:"Deficiencies have already been conveyed to the promoter and as per the statement by the AR reply regarding compliances has been submitted today which needs to be examined by the office. No building plans have been submitted so far and it has been informed that their building plan are under revision and in principal approval has been given. The license has already expired. As per the office record the license approval documents have been submitted only upto 18.8.2010 but as per statement of AR their license is renewed upto 18.8.2020 and renewal has been applied after depositing due amount.  It is surprising that service plan and estimates of the project has not been approved so far which is a  serious lapse on the part of the promoter. Now the promoter is directed to get the service plan and estimates approved on the basis of revised building plan. On the request of the promoter 15 days period is granted for compliance. Matter to come up on 05.04.2021"No compliance of the orders of the Authority has been made. A penalty of Rs. 5.00 lac is imposed. Keeping in view the glaring deficiencies the Authority decided to issue show cause notice as why the application for grant of extension shall not be rejected for the reasons as above as this application does not conform to the provisions of the Act, Rules and regulations made thereunder. The promoter is hereby given an opportunity of being heard in the matter on 10.05.2021 at 2.00 PM in the Conference Room of the Authority. (Dr. K.K.Khandelwal) Chairman(Samir Kumar) Member(Vijay Kumar Goyal) Member OBJECTION ---
22-Mar-2021 Ms. Roli Aggarwal, (GM) and  Sh. Rohit Mehta, (GM- Govt.Affairs) are present on behalf of the promoter. Deficiencies have already been conveyed to the promoter and as per the statement by the AR reply regarding compliances has been submitted today which needs to be examined by the office. No building plans have been submitted so far and it has been informed that their building plan are under revision and in principal approval has been given. The license has already expired. As per the office record the license approval documents have been submitted only upto 18.8.2010 but as per statement of AR their license is renewed upto 18.8.2020 and renewal has been applied after depositing due amount.  It is surprising that service plan and estimates of the project has not been approved so far which is a  serious lapse on the part of the promoter. Now the promoter is directed to get the service plan and estimates approved on the basis of revised building plan. On the request of the promoter 15 days period is granted for compliance. Matter to come up on 5.4.2021.  EXAMINATION BY AUTHORITY ---
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
21-Oct-2022 Proceedings dated 18.10.2022 Ms.  Asha, Chartered Accountant briefed about the project. Mr. Anitesh Singh (Manager) is present on behalf of the promoter.  The promoter has not submitted the consent of 2/3rd allottees of the project on account of revision of building plan. The AR of the promoter seeks a short adjournment for providing the consent of 2/3rd allottees on account of revision of building plan. Last opportunity is granted. Matter to come up on 15.11.2022. Not Yet
30-Sep-2022 Ms.  Asha, Chartered Accountant briefed about the project. Mr. Anitesh Singh (Manager) is present on behalf of the promoter.  Deficiencies have already been communicated. Promoter is advised to submit deficient documents, as detailed above. Matter to come up on 18.10.2022. Not Yet
23-Jul-2021 Sh. Ashish Kush, Planning Executive briefed the facts about the project. Sh. Rohit (AR) is present on behalf of the promoter. The Promoter M/s Emaar India Ltd. who is a collaborator applied for the extension of registration of real estate project namely “Emaar Colonnade” located at Sector-66, Gurugram under section 6 of the Real Estate (Regulations and Development) Act, 2016 vide central receipt no. 9482/17012 dated 02.03.2021 and RPIN-305. The Temp I.D. of REP – I (Part A-H) is RERA -GRG-PROJ-644-2020 and online generated for project extension temp id RERA-GRG-838-2021. The project area for registration is same as that of the licensed area i.e. 2.25 acres. License no – 163 of 2008 dated 19.08.2008. The application for extension of registration was scrutinized and 1st deficiency notice vide notice no. HARERA/GGM/REP/RC/156/2017/EXT/305/2021 dated 10.03.2021 was issued to the promoter with an opportunity of being heard on 22.03.2021. On 22.03.2021 the promoter submitted a reply and requested for 15 days for removing the deficiencies. The authority considered the request and matter is fixed for 05.04.2021. On 05.04.2021, the authority decided to impose a penalty of Rs 5.00 lac and matter is fixed for 10.05.2021. On 10.05.2021, the hearing was adjourned and matter was fixed for 20.07.2021. On 14.07.2021, the promoter submits a reply which was scrutinized and deficiencies are mentioned below: 1.      License no. 163 of 2008 dated 19.09.2008 valid up to 18.08.2010. Renewal of license needs to be submitted. 2.      Copy of original and revised service plans and estimates not provided. 3.      Copy of earlier approved and revised BR-III, needs to be submitted. 4.      Copy of original environmental clearance needs to be submitted. 5.      Audit report under section 4(2)(l)(d) for the financial year 2018-19 needs to be provided as per new format. 6.      Certificate of engineer, architect provided. However, needs to be clarified and CA certificate at the time of last withdrawal needs to be submitted.   7.      Financial viability of the project needs to be provided. The promoter also requested to condone the penalty of Rs 5.00 lac which was imposed on the promoter. A show cause notice be issued to the promoter as why their application for extension of registration shall not be rejected on account of deficiencies mentioned above as per provisions of section 6 of the Real Estate (Regulation and Development) Act, 2016. The request for waiver of penalty is declined and the promoter is directed to submit the penalty of Rs. 5.00 lakh within a week. The reasons for delay in implementing the project and failure to complete the same within the time period declared by the promoter under section 4(2)(l)(C) found not to be reasonable and with sufficient cause. Show cause notice be issued as why penal proceeding be not issued for violation of section 4 and for not completing the project within the period declared by the promoter under section 4(2)(l)(C). The matter to come up on 23.08.2021.Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman) Not Yet
05-Apr-2021 No one is present on behalf of the promoter. No information received regarding non appearance. Ms. Jyoti Yadav Coordinator Planning read out the proceedings of the last hearing as under:"Deficiencies have already been conveyed to the promoter and as per the statement by the AR reply regarding compliances has been submitted today which needs to be examined by the office. No building plans have been submitted so far and it has been informed that their building plan are under revision and in principal approval has been given. The license has already expired. As per the office record the license approval documents have been submitted only upto 18.8.2010 but as per statement of AR their license is renewed upto 18.8.2020 and renewal has been applied after depositing due amount.  It is surprising that service plan and estimates of the project has not been approved so far which is a  serious lapse on the part of the promoter. Now the promoter is directed to get the service plan and estimates approved on the basis of revised building plan. On the request of the promoter 15 days period is granted for compliance. Matter to come up on 05.04.2021"No compliance of the orders of the Authority has been made. A penalty of Rs. 5.00 lac is imposed. Keeping in view the glaring deficiencies the Authority decided to issue show cause notice as why the application for grant of extension shall not be rejected for the reasons as above as this application does not conform to the provisions of the Act, Rules and regulations made thereunder. The promoter is hereby given an opportunity of being heard in the matter on 10.05.2021 at 2.00 PM in the Conference Room of the Authority. (Dr. K.K.Khandelwal) Chairman(Samir Kumar) Member(Vijay Kumar Goyal) Member Not Yet
22-Mar-2021 Ms. Roli Aggarwal, (GM) and  Sh. Rohit Mehta, (GM- Govt.Affairs) are present on behalf of the promoter. Deficiencies have already been conveyed to the promoter and as per the statement by the AR reply regarding compliances has been submitted today which needs to be examined by the office. No building plans have been submitted so far and it has been informed that their building plan are under revision and in principal approval has been given. The license has already expired. As per the office record the license approval documents have been submitted only upto 18.8.2010 but as per statement of AR their license is renewed upto 18.8.2020 and renewal has been applied after depositing due amount.  It is surprising that service plan and estimates of the project has not been approved so far which is a  serious lapse on the part of the promoter. Now the promoter is directed to get the service plan and estimates approved on the basis of revised building plan. On the request of the promoter 15 days period is granted for compliance. Matter to come up on 5.4.2021.  Not Yet