Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
M3M International Financial Center including Phase I & II Sector-66, Gurugram GURUGRAM Badshahpur ST Gentle Realtors Private Limited
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/564/296/2022/39 DATED 23.05.2022 RERA-GRG-809-2021 16-Mar-2021 19-Feb-2021 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 18-Mar-2021 BY MAIL BY MAIL
Hearing is fixed for 30.03.2021. View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/564/296/2022/39 DATED 23.05.2022 17-Feb-2023 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
23-May-2022 Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Abhijeet Singh (Authorized Signatory), Sh. Manik Sharma (Authorized Signatory) and Sh. Vineet Maheshwari (Legal Head) are present on behalf of the promoter. The consent of two third allottees for acceptance of variation/ alteration in allotment of commercial unit are required if there is a change in the approved building plan. The promoter now has submitted a reply alongwith requisite consent of two- third allottees alongwith other deficit fees & documents which have been scrutinized in office and as per details on pre-page, out of 112 sold units, only 81 units are unique and the promoter has submitted the consent of 54 allottees out of 81 allottees for acceptance of variation/ alteration in allotment of commercial unit which come out to be two- third of the total and deficit fees and other documents also submitted. In view of above & recommendation on pre-page, the Authority decided to grant the registration certificate for whole project on the condition that the promoter shall submit three binded DPI booklets within 3 days and the promoter is liable to compensate the existing allottees of the project, if there is any delay on part of the promoter and by any allottee claim on account of revisions/ changes otherwise already approved under TOD Policy of Haryana Government notified by T&CP; on 18.02.2015, allowing higher FAR on payment of augmentation charges and higher EDC etc as amended from time to time.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
04-May-2022 Proceedings dated 04.05.2022. Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Abhijeet Singh (Authorized Signatory) and Sh. Manik Sharma (Authorized Signatory) are present on behalf of the promoter. The project is discussed at length. The authority directed the promoter to correct the online DPI as a whole consisting of both phases. Phase 1 - Registered with the RERA vide registration no. 20 of 2018. Phase 2- Applied for the registration after obtaining FAR under TOD Policy. The authority directed the promoter to submit the corrected online DPI within two weeks. The matter to come up on 23.05.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) ADJOURNMENT ---
30-Mar-2021 The authority decided to keep the matter in sine die and should wait for reply of the reference sent to the Director, Town and Country Planning, Govt. of Haryana, Chandigarh for clarification and guidance in the matter. SINE DIE View Order