01-Mar-2021 |
During personal hearing, Ms. Roli Aggarwal and Rohit Mehta
(Authorized signatory) was present on behalf of the promoter. The Authority has
discussed the project in detail. The promoter has submitted the corrected DPI for the
remaining area i.e., 66.059 acres along with corrected REP-I (Part A-H) which
was scrutinized and found in order. As per the directions given to the promoter
on 01.02.2021, he has submitted the revised REP-II declaring the date of offer of possession of 12.609
acres of Zone 4 is 31.12.2023 and remaining 53.45 acres (includes Zone-1-3.575
acres, Zone-2-18.94 acres, Zone -3-10.825 acres, Zone-4-2.23 acres,
Zone-5-17.88 acres) is 31.12.2027). The final completion date of the project as
per REP-II (declaration given by the promoter as per 4(2)(l)(C) is 31.12.2027.
After detailed scrutiny, it was
found that all the deficiencies have been
fulfilled by the promoter and the registration fee, processing fee and late fee
is duly paid by the promoter. Online corrections are done by the promoter. The
documents which are still pending are copy of renewal of license no. 97 of
2010, revised zoning plan, approval of external sewerage connection, storm
water drainage, revised service estimates and plans, however, applications
already filed in the concerned department for these approvals. An
affidavit was given by the promoter declaring that he will submit these deficit approvals within 3 months.
Therefore, the authority has decided to grant provisional registration
certificate and direct the promoter to submit these deficit documents within 3
months from the date of grant of registration certificate. The validity of registration certificate
is up to the expiry of the license but subject to the renewal of license and
the validity of certificate will automatically renew as per the undertaking
given by the promoter. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |
01-Feb-2021 |
The promoter is directed to submit revised REP-II along with corrected DPI, online A-H correction and other deficit documents. Matter will be heard on 01.03.2021. |
OBJECTION |
--- |
21-Dec-2020 |
During online hearing, no
one appeared on behalf of the promoter and requested for next date. Four opportunities for
the online hearing were given to the promoter, but he was not able to submit
the deficit documents as conveyed to him vide notice dated 27.10.2020 and proceeding
dated 09.11.2020, 24.11.2020, 11.12.2020, 21.12.2020. Hence, the authority has
decided to issue a show cause notice to you as why your application for
registration of real estate project “Marbella 2” should not be rejected on the ground for non-removal of deficiencies in
spite of repeated reminders and opportunity of online hearings as per the
provisions under section 5 of the Real Estate (Regulation and Development) Act,
2016 and Rule-5 of Haryana Real Estate (Regulation and Development) Rules,2017.
If you have anything to say in this regard, you are
given final opportunity of online hearing on 01.02.2021 at 3.00 p.m. In case you fail to remove the deficiencies and appear before the Authority for online
hearing on the above given date and time, it will be presumed that you have
nothing to say in this matter and your application will be rejected as per
provisions of the Act and rules referred as above. |
OBJECTION |
View Order |
11-Dec-2020 |
During online hearing, matter
was discussed at length. It was apprised that there is no provision as per RERA
Act 2016 for going in Phases until and unless the competent authority approves
it. As such it was impeached upon the developer to get the full project
registered by Tuesday i.e. on 15.12.2020 so that the matter may be taken up for
further necessary action.Matter will be heard on 21.12.2020 |
ADJOURNMENT |
--- |
08-Dec-2020 |
The matter has been adjourned since the Coram is not complete. The next date of hearing is 11.12.2020 |
OBJECTION |
--- |
24-Nov-2020 |
During online hearing, Ms.
Roli Aggarwal was present on behalf of the promoter. The Authority has
discussed the project in detail. The deficiencies have already been conveyed to
the promoter. The representative of the promoter apprised that necessary
documents will be submitted within a week and deficiencies will also be
attended accordingly. The promoter was asked to clarify whether they have got
phasing approved from the DTCP or not. If phasing has not been approved by the
DTCP, then it will amount to a revision of the layout plan of the project and it
will require the approval of two-third allottees under section 14 of RERA Act,
2016. The matter will be heard on 08.12.2020. |
ADJOURNMENT |
--- |
19-Nov-2020 |
The matter adjourned for 24.11.2020 |
ADJOURNMENT |
--- |
09-Nov-2020 |
The matter adjourned for 19.11.2020 |
EXAMINATION BY AUTHORITY |
--- |