Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
Sobha City, Phase-5 Revenue Estate of Babupur Village, Village Babupur, Sector-108, Gurugram, Haryana GURUGRAM Gurgaon Sobha Limited
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/410/142/2020/26 DATED 21.09.2020 RERA-GRG-701-2020 01-Jul-2020 17-Jun-2020 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 15-Jul-2020 received by hand 1st deficiency notice
1st deficiency notice sent to the promoter. View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/410/142/2020/26 DATED 21.09.2020 21-Oct-2020 RC Approved and Certificate Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
21-Sep-2020 Approved APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS ---
10-Sep-2020 Matter will be heard on 21.09.2020 ADJOURNMENT ---
07-Sep-2020 HEARING ADJOURNED FOR DATED 10.09.2020 OBJECTION ---
26-Aug-2020 During online hearing, Mr. Jagdish Nanigeni along with his team is present on behalf of the promoter.  During discussions few points were raised which are as follows: 1.      Deficiency fee of Rs. 11,82,261 needs to be submitted by the promoter. 2.  It has been brought on record that a loan of Rs. 200 crores have been taken by the builder by mortgaging the land. Encumbrance is created in favour of Standard Chartered Bank.  Hence, the promoter is directed to submit the affidavit that the land shall be made free from all encumbrances and master account and RERA account will be loan free and lien free and all the repayments will be done from free account. 3.   The promoter is directed that the builder should declare reasonable completion period of the project i.e. not beyond the validity of license. Matter to come up on 07.09.2020.  ADJOURNMENT ---
24-Aug-2020 Adjourned for dated 26.08.2020 OBJECTION ---
17-Aug-2020 The case came up for hearing today. During discussions three main points were raised: 1.       Deficiency fee to the tune of Rs. 11,82,261. It has been directed that the matter with regard to deficiency may be sorted out urgently failing the promoter shall be liable for making full payment in the matter. 2.       It has been brought on record that a loan of Rs. 200 crores has been taken by the builder by mortgaging the land. Encumbrance is created in favour of Standard Chartered Bank.  As a matter of principle the land should be free from all incumbrances only then he shall be able to issue conveyance deed in favour of the apartment buyers as per the provisions of section 11(h) of the Real Estate (Regulation and Development) Act, 2016. 3.       There is also dissipation with regard to the completion of the project. Since the license has been issued in 2008 and the proposed completion date has been given 2029. The project shall be completed in 21 years which seems to be unreasonable. In this way interests of home buyers are fully jeopardized. It is therefore, directed that the builder should declare reasonable completion period of the project. Although promoter may indicate different dates for different towers for giving possession to the allottees after taking Occupation Certificate from competent authority. Matter to come up on 24.8.2020.  OBJECTION ---
05-Aug-2020 The promoter was explained various deficiencies still remain to be rectified. Loan documents is also to besubmitted. The promoter asked for a week to rectify the deficiencies. The promoter was also asked tosubmit approval of the phases by the competent authority. Matter to come up on 17.08.2020. ADJOURNMENT ---
27-Jul-2020 NEXT DATE OF HEARING ON 05.08.2020 EXAMINATION BY AUTHORITY ---
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
28-Aug-2020 During online hearing, Mr. Jagdish Nanigeni along with his team is present on behalf of the promoter.  During discussions few points were raised which are as follows: 1.      Deficiency fee of Rs. 11,82,261 needs to be submitted by the promoter. 2.  It has been brought on record that a loan of Rs. 200 crores have been taken by the builder by mortgaging the land. Encumbrance is created in favour of Standard Chartered Bank.  Hence, the promoter is directed to submit the affidavit that the land shall be made free from all encumbrances and master account and RERA account will be loan free and lien free and all the repayments will be done from free account. 3.   The promoter is directed that the builder should declare reasonable completion period of the project i.e. not beyond the validity of license. Matter to come up on 07.09.2020.  Not Yet
18-Aug-2020 The case came up for hearing today. During discussions three main points were raised: 1.       Deficiency fee to the tune of Rs. 11,82,261. It has been directed that the matter with regard to deficiency may be sorted out urgently failing the promoter shall be liable for making full payment in the matter. 2.       It has been brought on record that a loan of Rs. 200 crores has been taken by the builder by mortgaging the land. Encumbrance is created in favour of Standard Chartered Bank.  As a matter of principle the land should be free from all incumbrances only then he shall be able to issue conveyance deed in favour of the apartment buyers as per the provisions of section 11(h) of the Real Estate (Regulation and Development) Act, 2016. 3.       There is also dissipation with regard to the completion of the project. Since the license has been issued in 2008 and the proposed completion date has been given 2029. The project shall be completed in 21 years which seems to be unreasonable. In this way interests of home buyers are fully jeopardized. It is therefore, directed that the builder should declare reasonable completion period of the project. Although promoter may indicate different dates for different towers for giving possession to the allottees after taking Occupation Certificate from competent authority. Matter to come up on 24.8.2020.  Not Yet
13-Aug-2020 The promoter was explained various deficiencies still remain to be rectified. Loan documents is also to besubmitted. The promoter asked for a week to rectify the deficiencies. The promoter was also asked tosubmit approval of the phases by the competent authority. Matter to come up on 17.08.2020. Not Yet