| 05-Oct-2020 |
During the hearing proceedings, Mr. Vijay Kumar (Authorized
Signatory) of the company was present. He intimated that the service plan and
estimates for their colony has been processed and approved. But the same have
been withheld for wait of furnishing Bank Guarantee Amounting Rs. 90 lakhs
which has been communicated by memo no. LC-2421/Asstt. (AK)/2020/728 dated
09.10.2020. As such the authority has concerned the matter and observed that
now, the release of service plan and estimates only a formality and the same
shall be released by DTCP, Haryana after submission of B.G. The representative
has requested that the service plan and estimates within 1 month. similarly,
the other deficiency regarding NOC for electrical load availability shall also
be obtained from concerned agency by the promoter shall be submit within 1
month. In view of above, the authority has decided to issue extension of
registration of their project i.e. 31.12.2020 with the above mentioned
conditions. |
EXTENSION APPROVED |
--- |
| 05-Oct-2020 |
|
OBJECTION |
--- |
| 22-Sep-2020 |
The promoter is asked to
submit an affidavit that they have submitted a request with DHBVN for
electricity load availability and reply of the department in this regard has
not been received so far. Till the time the electricity load is not available
for their project the promoter will provide electricity with their own
arrangement. The matter is adjourned to 05.10.2020. |
ADJOURNMENT |
--- |
| 21-Sep-2020 |
The matter fixed for 22.09.2020 |
ADJOURNMENT |
--- |
| 10-Sep-2020 |
The matter is adjourned to 21.09.2020 at 3:00 p.m. |
ADJOURNMENT |
--- |
| 07-Sep-2020 |
HEARING ADJOURNED FOR DATED 10.09.2020 |
ADJOURNMENT |
--- |
| 04-Sep-2020 |
HEARING ADJOURNED FOR DATED 07.09.2020 |
OBJECTION |
--- |
| 26-Aug-2020 |
During
the online hearing held on 26.08.2020, Mr. Devender Pandey authorized
representative of the promoter is present. The promoter is directed to submit the
copy of approved service plan and estimates and the copy of documents submitted
along with application for issue of occupation certificate in the office of
DTCP, Haryana in the authority by 03.09.2020 positively failing which penal
action shall be initiated against the promoter as per provision of the Act. The matter is fixed for next date of hearing
on 04.09.2020. |
ADJOURNMENT |
--- |
| 24-Aug-2020 |
Adjourned for dated 26.08.2020 |
OBJECTION |
--- |
| 05-Aug-2020 |
During proceedings it came to
the knowledge that the promoter has applied for OC even when the service plan
and estimates have not been approved by the competent authority. Further it was
noticed that the promoter has even not got the fire scheme sanctioned before
start of construction. It is not understood that how the application for OC has
been submitted by the promoter. Furthermore, the promoter has got the building
plans revised on 2.12.2019 i.e. after the registration of the project without
prior written consent of 2/3 allottees and making necessary changes in the DPI
and online information for registration of the project. On the request of the
promoter a period of 15 days was granted to rectify the defects and submit
requisite documents on 24.8.2020. |
ADJOURNMENT |
--- |
| 27-Jul-2020 |
Next date of hearing on 05.08.2020 |
OBJECTION |
--- |
| 17-Jun-2020 |
The authorized signatory Mr. Devender Pandey
was not present for online hearing. Mr.
Akhil Gupta, System Manager of the Company attended the hearing and intimated to
the authority that Mr. Devender Pandey was not able to attend the hearing due
to his other meeting scheduled at 3.00 PM. The authority has observed that the
promoter is not serious about the completion of their project and has neither
complied with the conditions mentioned in registration certificate within three
months and also did not submit QPR as required. Accordingly, the authority
decided to issue a show cause notice for revocation of the registration of the
real estate project as per provisions of under section-7 of the Real Estate
(Regulation and Development) Act 2016 and Rule-7 of the Haryana Real Estate
(Regulation and Development) Rules, 2017. It was also decided to issue show cause notice
for rejection of present application for extension of registration and to
freeze the project bank account and to get these accounts audited by the
empaneled Chartered Accountant. |
OBJECTION |
View Order |
| 10-Jun-2020 |
The
promoter is directed to comply with deficiencies by 17.06.2020. The case will
be heard on 17.06.2020. |
EXAMINATION BY AUTHORITY |
--- |