HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-2089-2026
Submission Date : 02-06-2026 04:16:47 PM
Applicant Type : Firm
Project Type: ONGOING


J ESTATE
SUNCITY KAITHAL,OPPOSIT OFDISPENSARY KAITHAL
8800000763 (Number Shared by Promoter in Public)
anilg121981@gmail.com
06005202400025
AATFJ2765J













ANANTARA
SECTOR 12 FATEHABAD
FATEHABAD
FATEHABAD
8800000763 (Number Shared by Promoter in Public)
anilg121981@gmail.com
ANIL KUMAR
8800000763 (Number Shared by Promoter in Public)
anil121981@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques/Online Banking:-

Drafts/ Banker’s Cheques

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1019-05-2026100000ONLINE TRANSFERHRERA Panchkula

Online Banking








6 (Acre)
1
1
6 (Acre)
License no. 241 of 2025 dated 02.12.2025
Yes







2920.14 Lakhs
514.10 Lakhs
0 Lakhs
1936.04 Lakhs
470 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 4.22
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 1.78
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
Total6




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS149.81YET TO BE PREPARED
2WATER SUPPLY SYSTEM99.87YET TO BE PREPARED
3STORM WATER DRAINAGE36.02YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM89.28YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL81.72YET TO BE PREPARED
6STREET LIGHTING23YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING8.47YET TO BE PREPARED
8PLAYGROUNDS AND PARKS37.83YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE562.93YET TO BE PREPARED
10SHOPPING AREA463.05YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER384.06YET TO BE PREPARED
15STREET LIGHTING23YET TO BE PREPARED
16SECURITY AND FIRE FIGHTING8.47YET TO BE PREPARED


03-12-2025 (date)
NA (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartments Total number of plots/apartments in the project Total size of the plots/carpet area of the apartments Plots/apartments booked/ sold upto the date of application Yet to be sold/ booked No. of towers to be/ being constructed for booked apartments
1 PLOT Type N 149.64 16 2394.24 0 0 0
2 PLOT Type O 143.96 37 5326.52 0 0 0
3 PLOT Type O1 148.54 2 297.08 0 0 0
4 PLOT Type O2 118.05 1 118.05 0 0 0
5 PLOT Type P 143.78 36 5176.08 0 0 0
6 PLOT Type P1 143.25 4 573 0 0 0
7 PLOT Type Q 145.92 22 3210.24 0 0 0
Total11817095.21000






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
NA00


N/A
N/A
N/A
01-02-2025
0
31-03-2028


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT48THE INTERNAL ROAD NETWORK, DEMARCATION OF PLOTS, SEWERAGE SYSTEM, WATER SUPPLY NETWORK, ELECTRIFICATION WORKS AND OTHER ESSENTIAL INFRASTRUCTURE WORK HAVE BEEN INITIATED. POSSESSION OF THE PLOTS SHALL BE OFFERED TO THE ALLOTTEES IMMEDIATELY UPON RECEIPT OF THE COMPLETION CERTIFICATE AND COMPLETION OF ALL STATUTORY FORMALITIES.
01-02-2025
0
31-03-2028


0
0
0
0
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements12.11
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds4.54
Clubhouse/community centres0
Shopping area0
Other0
Security and Fire Fighting0
Street Lighting6.05

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements18.1619.6722.70
Water Supply System15.1313.6215.13
Sewerage treatment & garbage disposal12.1115.1318.16
Electricity Supply System12.1113.6213.62
Storm Water Drainage6.055.455.15
Parks and Playgrounds4.844.544.84
Clubhouse/community centres75.6684.7478.69
Shopping area63.5666.5869.61
Other54.4855.6952.96
Street Lighting4.244.544.54
Security and Fire Fighting000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements24.2119.6718.1615.13
Water Supply System12.1113.6215.1315.13
Sewerage treatment & garbage disposal19.6716.6500
Electricity Supply System12.1112.1113.6212.11
Storm Water Drainage4.845.454.544.54
Parks and Playgrounds4.544.545.454.54
Clubhouse/community centres87.7781.7278.6975.66
Shopping area72.6463.5666.5860.53
Other54.4857.5054.4854.48
Street Lighting3.63000
Security and Firefighting1.51
Security and Fire Fighting1.512.423.03








Cash Flow in each quarter (In Lakhs)












Particulars Remarks, if any
i. No. of Flats/Apartments constructed323
ii. No. of Flats/ Apartments booked48
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter1068.35 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter421.77 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter646.58 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter0 Lakhs
vii. Amount invested in the project upto the date of application1677.71 Lakhs
Land cost (If any)1145.02 Lakhs
Apartments0 Lakhs
Infrastructure75.00 Lakhs
EDC/ Taxes Etc.457.51 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession6872.00 Lakhs
(a) In respect of existing allottees421.77 Lakhs
(b) In respect of rest of the project6450.23 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
1050.00 LakhsUnsecured Loans
x. Total liabilities against the project up-to-date. (Annex details in folder C) 1050.00 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS495.0040
II. WATER SUPPLY SYSTEM330.000
III. STORM WATER DRAINAGE119.000
IV. ELECTRICITY SUPPLY SYSTEM295.0020
V. SEWAGE TREATMENT & GARBAGE DISPOSAL270.000
VI. CLUB HOUSE/COMMUNITY CENTRE1860.000
VII. SCHOOL00
VIII. ANY OTHER14700
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING1530.000
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.015
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM28.000
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









No
No
Account Details
ICICI BANK, BRANCH -ADAMPUR DISTRICT - HISAR
085905007670
ICIC0000859
125229452
0859
Priya W/o Kuldeep Kumar R/o House no. 305, Model Town, Adampur, District Hissar, Haryana
Copy Attached











Yes
Yes
Yes
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LAYOUT PLANALREADY BEEN OBTAINED03-12-2025
II. DEMARCATION CUM ZONNING PLANALREADY BEEN OBTAINED12-05-2026
III. SERVICE PLAN AND ESTIMATESAPPLIED FOR BUT YET TO RECEIVENA








Yes


Yes















SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 01-06-2026 View Document
2 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 01-06-2026 View Document
3 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 01-06-2026 View Document
4 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 01-06-2026 View Document
5 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 02-06-2026 View Document
6 DEMARCATION PLAN 01-06-2026 View Document
7 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 01-06-2026 View Document
8 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 01-06-2026 View Document
9 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 01-06-2026 View Document
10 ZONING PLAN 01-06-2026 View Document
11 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 01-06-2026 View Document
12 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 02-06-2026 View Document
13 PAYMENT PLAN 11-08-2026 View Document