201-212, SPLENDOR FORUM, IIND FLOOR, JASOLA DISTRICT CENTRE, NEW DELHI-110025
01140655000
9810946102 (Number Shared by Promoter in Public)
secretarial@eldecoproperties.com
https://www.eldecogroup.com
XXXX177D
U74899HR2000PLC043893
ELDECO ESTATE ONE PRESTIGE
PANIPAT
PANIPAT
PANIPAT
01140655000
9818871148 (Number Shared by Promoter in Public)
sanjay.kumar@eldecoproperties.com
SANJAY KUMAR
01140655000
9818871148 (Number Shared by Promoter in Public)
sanjay.kumar@eldecoproperties.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
8558
14-05-2024
117612
HDFC BANK LIMITED
HRERA Panchkula
2
271
21-06-2024
22808
HDFC BANK LIMITED
HRERA Panchkula
2.90625 (Acre)
1.45
1
153.1937 (Acre)
24 of 2024
No
Address VILLAGE NIZAMPUR, PANIPAT-132103
Address VILLAGE NIZAMPUR, PANIPAT-132103
Address REGD. OFFICE - S-16, ELDECO STATION 1, SITE NO. 1, SECTOR 12, FARIDABAD, HARYANA-121007
Annexure-B- ANNEXURE-B- THE APPLICANT IS APPLYING FOR REGISTRATION AS "DEVELOPER" AS DEFINED IN COLLABORATION AGREEMENT DATED 04/11/2022. THE COLLABORATION AGREEMENT AND POWER OF ATTORNEY ARE ENCLOSED WITH THE APPLICATION
THE APPLICANT IS APPLYING BY VIRTUE OF COLLABORATION AGREEMENT, THE COLLABORATION AGREEMENT AND POWER OF ATTORNEY WAS MADE BEFORE THE GRANT OF LICENSE
Yes
THE IMPORTANT CLAUSES OF THE COLLABORATION AGREEMENT WHERE THE APPLICANT HAVE THE POWER TO DEVELOP/ CONSTRUCT THE PROJECT LAND IS AS UNDER: CLAUSE 2 : 2. THE OWNERS HAVE HANDED OVER TO THE DEVELOPER THE VACANT PHYSICAL POSSESSION OF THE SAID LAND FOR DEVELOPMENT OF PROJECT COLONY AND HAVE VESTED IN THE NOMINEE/REPRESENTATIVE OF THE DEVELOPER SUCH POWERS AND AUTHORITY OF THE OWNERS AS IS CONSIDERED NECESSARY FOR OBTAINING THE REQUISITE PERMISSIONS, SANCTIONS, APPROVALS ETC. FOR THE DEVELOPMENT ON THE SAID LAND. CLAUSE 3: 3. THE DEVELOPER, ON RECEIPT OF THE POSSESSION OF THE SAID LAND, SHALL ENTER UPON THE SAID LAND FOR TAKING UP THE DEVELOPMENT ACTIVITY AFTER OBTAINING REQUISITE PERMISSION AND APPROVAL FROM THE CONCERN AUTHORITIES. FURTHER, THE OWNERS SHALL EXECUTE A SPECIAL/GENERAL POWER OF ATTORNEY IN FAVOUR OF THE DEVELOPER AND ITS REPRESENTATIVES TO ENABLE THE DEVELOPER TO UNDERTAKE THE CONSTRUCTION AND DEVELOPMENT OF THE SAID LAND AND CARRY OUT ALL SUCH ACTS, DEEDS, THINGS AS MAY BE DEEMED NECESSARY BY THE DEVELOPER TO GIVE EFFECT TO THE TRANSACTION CONTEMPLATED UNDER THIS COLLABORATION AGREEMENT AND/ OR OTHERWISE EXERCISE ITS RIGHTS AND ENTITLEMENTS HEREUNDER, INCLUDING BUT NOT LIMITED TO THE FOLLOWING: (I) COMMENCEMENT, CONSTRUCTION, DEVELOPMENT, COMPLETION OF THE SAID LAND; (II) APPOINTMENT AND ENGAGEMENT OF OUTSIDE AGENCIES, ARCHITECTS, CONTRACTORS, ENGINEERS AND OTHER CONSULTANTS FOR THE DEVELOPMENT OF THE SAID LAND; (III) MARKETING AND SALE OF THE SALEABLE AREAS OF THE SAID LAND; AND TO COLLECT THE SALE PROCEEDS AND OTHER CHARGES IN RESPECT OF UNITS FROM THE CUSTOMERS/ BUYERS IN THE NAME OF DEVELOPER IN RESPECT OF DEVELOPER SHARE (“DEFINED HEREINAFTER”); (IV) TO BORROW MONEY OR AVAIL ANY FINANCIAL FACILITIES OR LENDING OR LOANS FROM ANY FINANCIAL OR BANKING INSTITUTIONS ON DEVELOPER SHARE; (V) TO CREATE CHARGE/ SECURITY/ ENCUMBRANCE, BY WAY OF MORTGAGE, HYPOTHECATION OR OTHERWISE, IN RESPECT OF THE SAID LAND OR ANY PART THEREOF, AND THE DEVELOPMENT RIGHTS OF THE DEVELOPER UNDER THIS COLLABORATION AGREEMENT; (VI) TO EXECUTE AND PRESENT FOR REGISTRATION AS DEEMED FIT BY THE DEVELOPER, ALL DOCUMENTS INCLUDING BUT NOT LIMITED TO MORTGAGE DEEDS, MEMORANDUM OF ENTRY, DECLARATION, GUARANTEES, HYPOTHECATION DEEDS, LOAN AGREEMENTS, DEBENTURE TRUST DEED, DEBENTURE SUBSCRIPTION AGREEMENTS, TRUST DEED, PLEDGE, NO OBJECTION CERTIFICATES, DECLARATION, AFFIDAVITS, POWERS OF ATTORNEY, ETC., AS MAY BE REQUIRED TO RECORD OR CREATE ANY SECURITY/ MORTGAGE/ ENCUMBRANCE/ CHARGE/ LIEN IN RESPECT OF DEVELOPER SHARE AND/OR SAID LAND AND/OR ANY PART THEREOF; (VII) TO SIGN, EXECUTE AND SUBMIT ALL PAPERS, DOCUMENTS, DEEDS, LETTERS, AFFIDAVITS, NO OBJECTION CERTIFICATES, AUTHORIZATIONS, UNDERTAKINGS AND TAKE SUCH OTHER ACTIONS AS MAY BE REQUIRED TO CONSUMMATE MORE EFFECTIVELY THE PURPOSES OR SUBJECT MATTER OF THIS COLLABORATION AGREEMENT; AND (VIII) TO OTHERWISE DEAL WITH THE SALEABLE AREAS FALLING IN THE SAID LAND AND/ OR THE SAID LAND IN ACCORDANCE WITH THIS COLLABORATION AGREEMENT AND TO GIVE EFFECT TO THIS COLLABORATION AGREEMENT.
No
Yes
Yes
1347.03 Lakhs
1249 Lakhs
0 Lakhs
771.03 Lakhs
576 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
6371.995
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
3573.64165
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
1565.876
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
249.6626
Total
11761.17525
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HARYANA SHEHRI VIKAS PRADHIKARAN
No
WATER SUPPLY
HARYANA SHEHRI VIKAS PRADHIKARAN
No
ELECTRICITY
HARYANA SHEHRI VIKAS PRADHIKARAN
No
SEWAGE DISPOSAL
HARYANA SHEHRI VIKAS PRADHIKARAN
No
STORM WATER DRAINAGE
HARYANA SHEHRI VIKAS PRADHIKARAN
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
140.76
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
6.46
YET TO BE PREPARED
3
STORM WATER DRAINAGE
13.63
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
143.88
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
0
YET TO BE PREPARED
6
STREET LIGHTING
8
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
11.21
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
189.15
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
257.94
YET TO BE PREPARED
NA (date)
NA (date)
01-08-2024
12-02-2029
Plot Area(In Square Meter)
Number of plots in the project
259.37
6
293
3
283
6
220
8
478.775
1
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
10.84
10.84
Water Supply System
0
0
0
Sewerage treatment & garbage disposal
0
0
2.42
Electricity Supply System
0
0
0
Storm Water Drainage
0
2.27
2.27
Parks and Playgrounds
0
0
0
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
43.84
43.84
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
10.84
15.84
15.84
11.86
Water Supply System
0
1.5
1.5
1.50
Sewerage treatment & garbage disposal
2.42
2.42
2.42
2.42
Electricity Supply System
0
21.7
21.7
21.70
Storm Water Drainage
2.27
2.27
2.27
2.27
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
43.84
43.84
43.84
43.84
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
14.69
10.00
10.00
10.00
Water Supply System
1.5
0.46
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
21.7
21.70
21.70
21.70
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
43.84
43.84
43.84
43.84
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
10.00
10.00
0
0
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
31.53
31.53
31.53
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
43.84
43.84
43.84
43.84
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
0
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
31.53
31.53
31.53
31.53
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
43.84
43.84
43.84
43.84
Particulars
Year-2029
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
Water Supply System
0
0
Sewerage treatment & garbage disposal
0
0
Electricity Supply System
0
0
Storm Water Drainage
0
0
Parks and Playgrounds
0
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
43.84
13.53
Yes
No
ICICI BANK LTD, 12A, 14 15, SPLENDOR FORUM, JASOLA DISTRICT CENTRE NEW DELHI-110025
113405003295
ICIC0001134
110229196
1134
Mr. Rohit Kishore, Mr. Naveen Kashyap and Mr. Manish Jaiswal 201-212 Splender Centre New Delhi-110025
ENCLOSED
Yes
Yes
Yes
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. DEMARCATION CUM ZONING PLAN
ALREADY BEEN OBTAINED
24-04-2024
II. LICENSE
ALREADY BEEN OBTAINED
13-02-2024
Yes
Yes
Gist of the important provisions of the Draft Agreement (Annex a copy in Folder F) The total price of Plot for residential usage ("Total Price"), other charges, payable by the Allottee/s for transfer of the Plots in his/ her/ its favour is as mentioned in Schedule V hereto. Explanation: (i) The Total Price as mentioned above includes the booking amount paid by the Allottee to the Promoter towards the Plots for residential usage; (ii) The Total Price as mentioned above includes Taxes (any taxes/ fees/ charges/ levies etc. which may be levied, in connection with the development/ construction of the Project paid/ payable by the Promoter up to the date of offer of possession of the Plots for residential usage to the Allottee or the competent authority, as the case may be, Provided that, in case there is any change / modification in the taxes/ charges/ fees/ levies etc., the subsequent amount payable by the Allottee to the Promoter shall be increased/ decreased based on such change /modification. Provided further, if there is any increase in the taxes/ charges/ fees/ levies etc. after the expiry of the scheduled date of completion of the Project as per registration with the Authority, which shall include the extension of registration, if any, granted to the Project by the Authority, as per the Act, the same shall not be charged from the Allottee; (iii) The Promoter shall intimate in writing to the Allottee, the amount payable as stated in (i) and (ii) above and the Allottee shall make payment demanded by the Promoter within the time and in the manner specified therein. In addition, the Promoter shall provide to the Allottee(s) the details of the taxes/ fees/ charges/ levies etc. paid or demanded along with the acts/ rules/ notifications together with dates from which such taxes/ fees/ charges/ levies etc. have been imposed or become effective; (iv) The Total Price of Plots for residential usage includes recovery of price of land, development of Plots but also of the Common Areas, External Development Charges, State Internal Development Charges, Infrastructure Augmentation charges.
ELDECO ESTATE ONE PHASE THREE
29.17
0
308
0
308
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
7745.30
0
8298.3
Cost of the apartments
0
0
0
Cost of the infrastructure
2132.10
0
2543.7
Others costs
5613.21
0
5754.6
16018.10 Lakhs
16018.10 Lakhs
3816 Lakhs
3816 Lakhs
No
30-11-2023
30-05-2024
ELDECO ARANYA
13.0875
56
179
48
169
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
4211.33
0
6508.24
Cost of the apartments
658.55
0
1558.08
Cost of the infrastructure
1243.31
0
1501.1
Others costs
2309.47
0
3449.06
11630.8 Lakhs
2217.10 Lakhs
4200 Lakhs
3840 Lakhs
No
30-11-2024
30-11-2024
ELDECO PLAZA
0.903
0
23
0
23
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
630
0
428.31
Cost of the apartments
0
0
0
Cost of the infrastructure
145
0
62.67
Others costs
460
0
365.64
811.77 Lakhs
250.35 Lakhs
0 Lakhs
0 Lakhs
No
12-04-2024
12-04-2024
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
NA
2
WALL FINISHING DETAILS
NA
3
KITCHEN DETAILS
NA
4
BATHROOM FITTINGS
NA
5
WOOD WORK ETC
NA
6
DOORS AND WINDOS FRAMES
NA
7
GLASS WORK
NA
8
ELECTRIC FITTINGS
NA
9
CONDUCTING AND WIRING DETAILS
NA
10
CUPBOARD DETAILS
NA
11
WATER STORAGE
NA
12
LIFT DETAILS
NA
13
EXTERNAL GLAZINGS
NA
13.1
WINDOWS/GLAZINGS
NA
14
DOORS
NA
14.1
MAIN DOORS
NA
14.2
INTERNAL DOORS
NA
15
AIR CONDITIONING
NA
16
ELECTRICAL FITTINGS
NA
17
CNG PIPE LINE
NA
18
PROVISION OF WIFI AND BROADBAND FACILITY
NA
19
EXTERNAL FINISHING/COLOUR SCHEME
NA
20
INTERNAL FINISHING
NA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
NA
1 . 2
WALLS
NA
1 . 3
CEILING
NA
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
NA
2 . 2
WALLS
NA
2 . 3
CEILING
NA
2 . 4
MODULAR WARDROBES
NA
3 . MASTER TOILET
3 . 1
FLOOR
NA
3 . 2
WALLS
NA
3 . 3
CEILING
NA
3 . 4
COUNTERS
NA
3 . 5
SANITARY WARE/CP FITTINGS
NA
3 . 6
FITTING/FIXTURES
NA
4 . BED ROOMS
4 . 1
FLOOR
NA
4 . 2
WALLS
NA
4 . 3
CEILING
NA
4 . 4
WARDROBES
NA
5 . TOILET
5 . 1
FLOOR
NA
5 . 2
WALLS
NA
5 . 3
CEILING
NA
5 . 4
COUNTERS
NA
5 . 5
SANITARY WARE/CP FITTINGS
NA
5 . 6
FIXTURES
NA
6 . KITCHEN
6 . 1
FLOOR
NA
6 . 2
WALLS
NA
6 . 3
CEILING
NA
6 . 4
COUNTERS
NA
6 . 5
FIXTURES
NA
6 . 6
KITCHEN APPLIANCES
NA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
NA
7 . 2
WALLS & CEILING
NA
7 . 3
TOILET
NA
7 . 4
BALCONY
NA
8 . SIT-OUTS
8 . 1
FLOOR
NA
8 . 2
WALLS & CEILING
NA
8 . 3
RAILINGS
NA
8 . 4
FIXTURES
NA
Sr. No.
Document Description
Date of Document Upload
View Document
1
DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT