HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1477-2023
Submission Date : 04-01-2024 11:42:07 AM
Applicant Type : Company
Project Type: NEW




ADVANCE INDIA PROJECTS LIMITED
AIPL BUSINESS CLUB, 5TH FLOOR, GOLF COURSE EXTENTION ROAD, SECTOR-62, GURUGRAM, HARYANA-122101
01246077777
8800563717 (Number Shared by Promoter in Public)
rera-haryana@aipl.com
https://aipl.com
XXXX859J
U45209HR1997PLC080240
 
 


 
 


 
 


 
 


 
 


 
 


 
 







AIPL JOY DISTRICT
VILLAGE HAYATPUR, SECTOR 88
HARSARU ST
GURUGRAM
9211160000
8800563717 (Number Shared by Promoter in Public)
rera-haryana@aipl.com
ASHOK KUMAR RASTOGI
9211160000
8800563717 (Number Shared by Promoter in Public)
rera-haryana@aipl.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1526514-11-2023789870.00HDFC BANK HRERA Gurugram
24412125-09-20171000000ANDHRA BANK HRERA Gurugram
34412025-09-2017844077ANDHRA BANK HRERA Gurugram
4426614-11-2019743100AXIS BANK, SEC-29,GURUGRAMHRERA Gurugram
55202203105265046710-03-2022228036HDFC BANK HRERA Gurugram
65202204075971173707-04-2022739200HDFC BANK HRERA Gurugram
75202205186908091916-05-202210528956HDFC BANK HRERA Gurugram







10.4375 (Acre)
187
187
10.4375 (Acre)
56 of 2013 dated 10.07.2013
No
Address     B-76, FIRST FLOOR, DEFENCE COLONY, NEW DELHI- 110024
Annexure-B- BIP/COD HOLDER
COLLABORATION AGREEMENT IS EXECUTED ON 29.09.2023
Yes
COLLABORATION AGREEMENT TO CONCEPTUALIZE, PROMOTE, CONSTRUCT AND DEVELOP A COMMERCIAL PROJECT ON THE LICENSED LAND.
No
Yes
Yes







121176.25 Lakhs
7830.21 Lakhs
45997.76 Lakhs
448.91 Lakhs
66899.37 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS5.9083
3CONSTRUCTION OF ROADS1.568
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0
6GREEN BELTS0.36
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.1120
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER2.4892
Total10.4375




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDANo
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS0SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM131.83SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE31.56SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM0SUBMITTED TO TOWN & COUNTRY PLANNING
5SEWAGE TREATMENT & GARBAGE DISPOSAL47.30SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING16.02SUBMITTED TO TOWN & COUNTRY PLANNING
7SECURITY AND FIRE FIGHTING32.17SUBMITTED TO TOWN & COUNTRY PLANNING
8PLAYGROUNDS AND PARKS0SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE0SUBMITTED TO TOWN & COUNTRY PLANNING
10SHOPPING AREA0SUBMITTED TO TOWN & COUNTRY PLANNING
11RENEWABLE ENERGY SYSTEM0SUBMITTED TO TOWN & COUNTRY PLANNING
12SCHOOL0SUBMITTED TO TOWN & COUNTRY PLANNING
13HOSPITAL/DISPENSARY0SUBMITTED TO TOWN & COUNTRY PLANNING
14ANY OTHER0SUBMITTED TO TOWN & COUNTRY PLANNING
15SEWERAGE TREATMENT PLANT31.70SUBMITTED TO TOWN & COUNTRY PLANNING
16UNDERGROUND WATER TANK50SUBMITTED TO TOWN & COUNTRY PLANNING
17RAIN WATER HARVESTING10.44SUBMITTED TO TOWN & COUNTRY PLANNING
18CONSTRUCTION OF CIRCULATION ROADS38.09SUBMITTED TO TOWN & COUNTRY PLANNING
19MAINTENANCE CHARGE FOR TEN YEARS59.80SUBMITTED TO TOWN & COUNTRY PLANNING


16-12-2021 (date)
16-12-2021 (date)
01-04-2024
30-06-2028
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings49774.8211901





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops32.84
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops1026.701209.771753.222827.17
Plots0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops4281.204987.704576.543777.93
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops4204.495005.084950.792374.79
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops1654.961654.961053.08626.52
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System00013.18
Sewerage treatment & garbage disposal4.2614.1915.1413.72
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0003.22

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System39.5546.1432.960
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage02.5217.3611.68
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other10.2910.947.720
Rain Water Harvesting2.308.14
Security and Fire Fighting0

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.8112.1912.199.90
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Underground Water Tank7.5023.5019.000
Sewerage treatment plant3.8013.3114.580
Street Lighting2.408.335.290

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000












Yes
No
HDFC BANK LTD., SECTOR 56, GURUGRAM
50200088749753
HDFC0003871
110240358
3871
MR. DALJEET SINGH, MR. HARINDER SINGH AND MR. GURDEEP SINGH
NO DEFAULT HAS BEEN MADE.











Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes


Yes
No
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. ENVIRONMENT CLEARANCEALREADY BEEN OBTAINED15-11-2022
II. AIRPORT HEIGHT CLEARANCEALREADY BEEN OBTAINED06-11-2019
III. REVISED BUILDING PLAN APPROVALALREADY BEEN OBTAINED16-12-2021
IV. LICENSEALREADY BEEN OBTAINED10-07-2013
V. FIRE SCHEME APPROVALALREADY BEEN OBTAINED13-01-2024
VI. SERVICE PLAN AND ESTIMATESALREADY BEEN OBTAINED15-01-2024








Yes


Yes


AS PER HARERA NORMS.







AIPL JOY GALLERY, SEC 66, GURUGRAM
4.418
401
0
350
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
66125.4866125.4830597.88
Cost of the apartments31681.9131681.9113540.09
Cost of the infrastructure5356.135356.13406.29
Others costs29087.4429087.4416651.5


18600.58 Lakhs
25016.47 Lakhs
16000 Lakhs
9620 Lakhs
No
13-05-2025
13-05-2025




AIPL AUTOGRAPH, SEC-66, GURUGRAM
6.1375
150
0
56
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
90150.2590150.2534958.65
Cost of the apartments38753.0738753.0714236.91
Cost of the infrastructure5451.005451.00322.78
Others costs45946.1845946.1820398.96


18422.58 Lakhs
16618.48 Lakhs
27200 Lakhs
25647 Lakhs
No
08-04-2026
08-04-2026










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITREOUS TILES, KOTA STONE, MARBLE.
2WALL FINISHING DETAILSPOP AND PAINT
3KITCHEN DETAILSANTI SKID TILES
4BATHROOM FITTINGSKOHLER, ASTRAL, SUPREME OR SIMILAR MAKE.
5WOOD WORK ETCNOT APPLICABLE
6DOORS AND WINDOS FRAMESALUMINIUM
7GLASS WORKST. GOBAIN
8ELECTRIC FITTINGSHAVELLS, PHILIPS, CROMPTON, ABB, TVISHA OR SIMILAR MAKE
9CONDUCTING AND WIRING DETAILSHAVELLS, POLYCAB OR EQUIVALENT BRAND
10CUPBOARD DETAILSNOT APPLICABLE
11WATER STORAGEPVC SYNTEX
12LIFT DETAILSJOHNSON LIFTS, KONE, MITSIBUSHI OR EQUIVALENT BRAND
13EXTERNAL GLAZINGSST. GOBAIN
13.1WINDOWS/GLAZINGSALUMINIUM
14DOORSALUMINIUM
14.1MAIN DOORSALUMINIUM
14.2INTERNAL DOORSALUMINIUM
15AIR CONDITIONINGNOT APPLICABLE
16ELECTRICAL FITTINGSHAVELLS OR EQUIVALENT
17CNG PIPE LINENOT APPLICABLE
18PROVISION OF WIFI AND BROADBAND FACILITYAIRTEL, JIO OR SIMILAR
19EXTERNAL FINISHING/COLOUR SCHEMETEXTURE
20INTERNAL FINISHINGTEXTURE
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNOT APPLICABLE
1 . 2 WALLSNOT APPLICABLE
1 . 3 CEILINGNOT APPLICABLE
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNOT APPLICABLE
2 . 2 WALLSNOT APPLICABLE
2 . 3 CEILINGNOT APPLICABLE
2 . 4 MODULAR WARDROBESNOT APPLICABLE
3 . MASTER TOILET
3 . 1 FLOORNOT APPLICABLE
3 . 2 WALLSNOT APPLICABLE
3 . 3 CEILINGNOT APPLICABLE
3 . 4 COUNTERSNOT APPLICABLE
3 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE
3 . 6 FITTING/FIXTURESNOT APPLICABLE
4 . BED ROOMS
4 . 1 FLOORNOT APPLICABLE
4 . 2 WALLSNOT APPLICABLE
4 . 3 CEILINGNOT APPLICABLE
4 . 4 WARDROBESNOT APPLICABLE
5 . TOILET
5 . 1 FLOORNOT APPLICABLE
5 . 2 WALLSNOT APPLICABLE
5 . 3 CEILINGNOT APPLICABLE
5 . 4 COUNTERSNOT APPLICABLE
5 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE
5 . 6 FIXTURESNOT APPLICABLE
6 . KITCHEN
6 . 1 FLOORNOT APPLICABLE
6 . 2 WALLSNOT APPLICABLE
6 . 3 CEILINGNOT APPLICABLE
6 . 4 COUNTERSNOT APPLICABLE
6 . 5 FIXTURESNOT APPLICABLE
6 . 6 KITCHEN APPLIANCESNOT APPLICABLE
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNOT APPLICABLE
7 . 2 WALLS & CEILINGNOT APPLICABLE
7 . 3 TOILETNOT APPLICABLE
7 . 4 BALCONYNOT APPLICABLE
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE
8 . 2 WALLS & CEILINGNOT APPLICABLE
8 . 3 RAILINGSNOT APPLICABLE
8 . 4 FIXTURESNOT APPLICABLE












Sr. No.Document DescriptionDate of Document UploadView Document
1COPY OF LICENSE ALONG WITH SCHEDULE OF LAND31-10-2023 View Document
2IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN31-10-2023 View Document
3DEMARCATION PLAN31-10-2023 View Document
4ZONING PLAN31-10-2023 View Document
5IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN31-10-2023 View Document
6A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS14-11-2023 View Document
7CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT13-12-2023 View Document
8DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.13-12-2023 View Document
9STORM WATER DRAINAGE09-05-2024 ------
10SECTION PLAN09-05-2024 ------
11NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT09-05-2024 View Document
12SEWERAGE09-05-2024 ------
13FOURTH FLOOR PLAN09-05-2024 ------
14GROUND FLOOR COVERAGE PLAN09-05-2024 ------
15GROUND FLOOR FAR AREA DETAILS09-05-2024 ------
16GROUND FLOOR PLAN09-05-2024 ------
17X-SECTION PLAN09-05-2024 ------
18THIRD FLOOR AREA DETAIL09-05-2024 ------
19TERRACE FLOOR PLAN09-05-2024 ------
20FIRE FIGHTING PLAN09-05-2024 ------
21COD ORDER AMB TO AIPL09-05-2024 ------
22FIRE SCHEME AJD09-05-2024 ------
23FIRST FLOOR AREA DETAILS09-05-2024 ------
24LOWER BASEMENT 02 PARKING AREA DETAIL09-05-2024 ------
25AKSIZRA DT. 22-11-202309-05-2024 ------
26SUPERIMPOSED DEMARCATION PLAN09-05-2024 ------
27SITE PLAN09-05-2024 ------
28ROADS & PAVEMENT09-05-2024 ------
29CA CERTIFICATE FOR FINANCIAL AND INVENTORY DETAILS09-05-2024 ------
30SITE PLAN - PLUMBING LAYOUT09-05-2024 ------
31LOWER BASEMENT 02 AREA DETAIL09-05-2024 ------
32NEC09-05-2024 ------
33UPPER BASEMENT - 0109-05-2024 ------
34FOURTH FLOOR AREA DETAIL09-05-2024 ------
35BUILDING PLAN - BR III09-05-2024 ------
36UPPER BASEMENT 01 AREA DETAIL09-05-2024 ------
37SERVICE ESTIMATE APPROVALS09-05-2024 ------
38LOWER BASEMENT 0209-05-2024 ------
39SECOND FLOOR PLAN09-05-2024 ------
40SOLID WASTE MANAGEMENT09-05-2024 ------
41PARKING PLAN09-05-2024 ------
42FIRST FLOOR PLAN09-05-2024 ------
43JAMABANDHI DT. 22-11-2309-05-2024 ------
44SERVICE ESTIMATES - AIPL JOY DISTRICT09-05-2024 ------
45DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD09-05-2024 View Document
46UPPER BASEMENT 01 PARKING AREA DETAIL09-05-2024 ------
47THIRD FLOOR PLAN09-05-2024 ------
48ELEVATION PLAN09-05-2024 ------
49SECOND FLOOR AREA DETAILS09-05-2024 ------
50ENVIROMENT CLEARANCE09-05-2024 ------
51LIST OF INVENTORY_CARPET AREAWISE-AIPL JOY DISTRICT14-05-2024 ------