HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1079-2022
Submission Date : 03-07-2022 12:53:28 PM
Applicant Type : Registered Society or Trust or Authority
Project Type: NEW




ESTATE OFFICER HSVP KARNAL
HSVP BUILDING SEC-12 KARNAL
01842267909
9466694664 (Number Shared by Promoter in Public)
eokarnalhsvp@gmail.com
http://www.hsvphry.org.n
XXXX087M
06AAAAH0087M1ZN
HUDA ACT,1977
 
 


 
 











SECTOR 9 GHARAUNDA
HSVP COMPLEX SECTOR-12, KARNAL
KARNAL
KARNAL
01842267909
9466694664 (Number Shared by Promoter in Public)
eokarnalhsvp@gmail.com
ESTATE OFFICER HSVP KARNAL
9466694664 (Number Shared by Promoter in Public)
eokarnalhsvp@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
191863102-07-2022339936PUNJAB NATIONAL BANK SEC-12, KARNAL.HRERA Panchkula







11.85 (Acre)
100 for plotted/ 150 for commercial
100
11.85 (Acre)
License no. 147 of 2022 dated 28 september 2022 valid till 27 september 2027
Yes







476.10 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 9.11
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 3.68
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 1.23
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 1.64
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0.076
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0.37
Total16.106




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSNo
WATER SUPPLYNo
ELECTRICITYNo
SEWAGE DISPOSALNo
STORM WATER DRAINAGENo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS229.50SUBMITTED TO HUDA
2WATER SUPPLY SYSTEM201.05SUBMITTED TO HUDA
3STORM WATER DRAINAGE83.28SUBMITTED TO HUDA
4ELECTRICITY SUPPLY SYSTEM107.91YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL107.64SUBMITTED TO HUDA
6STREET LIGHTING45.47SUBMITTED TO HUDA
7SECURITY AND FIRE FIGHTING21.50YET TO BE PREPARED
8PLAYGROUNDS AND PARKS26.24YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER462.88YET TO BE PREPARED


29-09-2022 (date)
NA (date)
01-09-2021
01-05-2022
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 36877.00 294
Total294


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements9330062
Water Supply System15475749
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar












Yes
No
PNB MANIMAJRA
1183005900001699
PUNB0118300
NA
PUNB0118300
CA HSVP Sector 6 Panchkula
NA











Yes
Yes
No
No
No
No
No
No
No
No


Yes
No
Yes
Yes
Yes
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. CTP/DTP(D)VY 24531ALREADY BEEN OBTAINED18-02-2021








No


No


NA







SECTOR 9 GHARAUNDA
1680
0
294
0
294
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
476.100248.05
Cost of the apartments000
Cost of the infrastructure000
Others costs000


0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
10-09-2021
20-05-2022










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 03-07-2022 View Document
2 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 03-07-2022 View Document
3 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 03-07-2022 View Document
4 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 03-07-2022 View Document
5 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 03-07-2022 View Document
6 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 03-07-2022 View Document
7 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 03-07-2022 View Document
8 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 03-07-2022 View Document
9 DEMARCATION PLAN 03-07-2022 View Document
10 ZONING PLAN 03-07-2022 View Document
11 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 03-07-2022 View Document
12 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 03-07-2022 View Document