1309, 13TH FLOOR, DR. GOPAL DAS BHAWAN, 28 BARAKHAMBA ROAD, NEW DELHI-110001
01244908200
9810899381 (Number Shared by Promoter in Public)
compliance@signatureglobal.in
https://www.signatureglobal.in/
XXXX888R
U70100DL2008PTC176641
SIGNATURE GLOBAL PARK -II (PHASE II)
VILLAGE DHUNELA, SECTOR-36
SOHNA
GURUGRAM
01244908200
9810899381 (Number Shared by Promoter in Public)
compliance@signatureglobal.in
SANJAY KUMAR VARSHNEY
01244908200
9810899381 (Number Shared by Promoter in Public)
compliance@signatureglobal.in
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
52021050680651165
06-05-2021
759292
YES BANK LIMITED
HRERA Gurugram
2
52021050680651509
06-05-2021
287610
YES BANK LIMITED
HRERA Gurugram
2.00 (Acre)
2.64
2.43
11.0625 (Acre)
39 of 2019 dated 01/03/2019 vide Endst. No. LC-3857-Asstt.(AK)/2019/6205
Yes
10943.37 Lakhs
2401.14 Lakhs
7200 Lakhs
0 Lakhs
3342.23 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
2.00
3
CONSTRUCTION OF ROADS
0
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
Total
2
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
NHAI
Yes
WATER SUPPLY
HSVP
Yes
ELECTRICITY
DHBVH
Yes
SEWAGE DISPOSAL
HSVP
Yes
STORM WATER DRAINAGE
No
STP
HSVP
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
266.20
SUBMITTED TO TOWN & COUNTRY PLANNING
2
WATER SUPPLY SYSTEM
158.80
SUBMITTED TO TOWN & COUNTRY PLANNING
3
STORM WATER DRAINAGE
105.10
SUBMITTED TO TOWN & COUNTRY PLANNING
4
ELECTRICITY SUPPLY SYSTEM
0
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
110.60
SUBMITTED TO TOWN & COUNTRY PLANNING
6
STREET LIGHTING
42.40
SUBMITTED TO TOWN & COUNTRY PLANNING
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
7.10
SUBMITTED TO TOWN & COUNTRY PLANNING
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
MAINTENANCE
332.40
SUBMITTED TO TOWN & COUNTRY PLANNING
NA (date)
NA (date)
01-04-2021
31-03-2023
Plot Area(In Square Meter)
Number of plots in the project
0
0
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
83.6
32
8
Apartment/Shops/Other Buildings
70.3
60
15
Apartment/Shops/Other Buildings
60.13
32
8
Apartment/Shops/Other Buildings
43.29
148
37
Apartment/Shops/Other Buildings
43.46
8
2
Apartment/Shops/Other Buildings
36.61
16
4
Apartment/Shops/Other Buildings
65.61
12
3
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
400
Shops
0
Plots
0
External Development Charges
326
Infrastructure development charges
66.66
Land Cost
2401.14
Others Cost
1585
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
200
200
200
Shops
0
0
0
Plots
0
0
0
Others Cost
240
150
Cost of construction of apartment
200
External Development Charges
103.57
Other Cost
171
Cost of Construction of Apartment
200
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
200
200
300
300
Shops
0
0
0
0
Plots
0
0
0
0
Cost of construction of apartment
200
200
350
350
Others Cost
134
138
132
126
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
800
800
650
650
Shops
0
0
0
0
Plots
0
0
0
0
Others Cost
165
145
50
50
Cost of construction of apartment
350
350
350
350
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
650
550
550
650
Shops
0
0
0
0
Plots
0
0
0
0
Cost of construction of apartment
350
550
550
450
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
236.2
Water Supply System
158.8
Sewerage treatment & garbage disposal
110.6
Electricity Supply System
0
Storm Water Drainage
105.1
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
30
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Parking Horticulture
3.1
Street Light
12.4
Yes
No
KOTAK MAHINDRA BANK LIMITED, 1ST FLOOR , ASSET AREA 9 IBIS , COMMERCIAL BLOCK, HOSPITALITY DISTRICT DELHI AEROCITY, NEW DELHI -110037YES BANK LIMITED, GROUND AND MEZZANINE FLOOR, , 56, JANPATH, ALPS BLDG, , NEXT TO PIZZA HUT, CONNAUGHT PLACE, DELHI-110001
8045100099
KKBK0000261
110532031
000261
Ravi Aggarwal and Pradeep Kumar Aggarwal, House No. 34, Road No.61, West Pinjabi Bagh, Delhi-110026
Attached as Annexure
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes
Yes
No
Yes
No
Yes
Yes
Yes
Yes
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. ENVIRONMENT CLEARANCE SEIAA(124)/HR/2020/341
ALREADY BEEN OBTAINED
27-08-2020
II. LICENSE 39 OF 2019
ALREADY BEEN OBTAINED
01-03-2019
III. ZONING DRG. NO. DTCP 6994
ALREADY BEEN OBTAINED
07-06-2019
IV. LAYOUT DTCP-6841
ALREADY BEEN OBTAINED
15-02-2019
V. WATER SUPPLY MEMO NO. 76333
ALREADY BEEN OBTAINED
25-04-2019
VI. SEWAGE DISPOSAL MEMO NO. 76323
ALREADY BEEN OBTAINED
25-04-2019
VII. STP MEMO NO. 76319
ALREADY BEEN OBTAINED
25-04-2019
VIII. ELECTRICAL LOAD AVAILABILITY MEMO NO. 1890
ALREADY BEEN OBTAINED
26-04-2019
Yes
Yes
Yes
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: