| 10-Jun-2024 |
PENDING |
|
|
--- |
--- |
| 01-Apr-2024 |
PENDING |
Ms. Nikita (Planning Exeutive0 briefed the facts of the case. Ms. Alka Malik (Advocate) is present on behalf of the promoter.The AR states that the services have been completed and an application for grant of CC also stand made to DTCP on 15.02.2024. The AR further assures to submit the approved service plans and estimates within eight weeks.The matter to come up on 10.06.2024 |
ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
25-Apr-2024 |
| 22-Mar-2024 |
PENDING |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Ms. Alka Malik (AR) along
with advocate Garvit Gupta is present on behalf of the promoter. The AR of the
promoter states that the matter is being pursued at the level of the DTCP where
certain complications have arisen.
In view of the continued non- compliance of
the conditions of registration, the matter be placed before the Authority in
its next meeting fixed on 01.04.2024. |
ASHOK SANGWAN |
--- |
--- |
| 01-Mar-2024 |
PENDING |
MATTER TO COME UP ON 22.03.2024. |
ASHOK SANGWAN |
View Order |
19-Mar-2024 |
| 02-Feb-2024 |
PENDING |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Ms. Alka Malik (AR) are
present on behalf of the promoter and states that demand letter for deposit of
bank guarantee amounting to Rs. 100.497 lacs has been received from DTCP on
30.11.2021which is placed on record.
In view of the fact that the promoter
has failed to submit the approval of service plans and estimates within the
specified timeline of three months as per conditions of the registration
certificate dated 17.04.2023, the security deposited by the promoter in lieu of
the timely submission of all the above approval is hereby forfeited. The
promoter is further directed to submit the approval from the competent
authority within a period of one month failing which legal consequences
including but not restricted to freezing of bank accounts and restriction for
creating any further third-party rights shall follow.
Matter to come up on
01.03.2024. |
ASHOK SANGWAN |
View Order |
12-Feb-2024 |
| 19-Jan-2024 |
PENDING |
THE MATTER IS ADJOURNED TO 02.02.2024. |
ASHOK SANGWAN |
View Order |
23-Jan-2024 |
| 15-Dec-2023 |
PENDING |
THE MATTER TO COME UP ON 15.12.2023 |
ASHOK SANGWAN SANJEEV KUMAR ARORA |
--- |
--- |
| 07-Dec-2023 |
PENDING |
THE MATTER TO COME UP ON 15.12.2023 |
ASHOK SANGWAN |
View Order |
12-Dec-2023 |
| 10-Nov-2023 |
PENDING |
THE MATTER TO COME UP ON 07.12.2023 AT 11:30 AM |
ASHOK SANGWAN |
View Order |
20-Nov-2023 |
| 27-Oct-2023 |
PENDING |
THE MATTER TO COME UP ON 10.11.2023 AT 11:30 AM |
ASHOK SANGWAN |
View Order |
02-Nov-2023 |
| 22-Sep-2023 |
FIRST HEARING |
Sh. Sanjeev Kumar
(AR) is present on behalf of the promoter and states that the approval of
service plans and estimates is pending at the level of DTCP and is likely to be
issued soon. So far as the environmental clearance is concerned, their project
does not fall under the category where EC is required and the requisite
instructions/notification will be submitted within one week.
The promoter has not
complied with the conditions of registration and nor has he submitted the
requisite BG on the basis of which the registration was issued. In view of the
above, it is recommended that the registration of the project may be suspended,
and the promoter be restrained from sale of any further inventory or creation
of 3rd party rights in the project until compliance of the condition
is made and/or BG is submitted.
The matter to come up on 27.10.2023. |
ASHOK SANGWAN |
View Order |
26-Oct-2023 |