Comprehensive Complaint Details
Complaint Detail:RERA-GRG-3867-2023
Party Dtls Self / Adv Name District Current Status Next Date of Hearing Complaint Dispatched Complaint Dispatched On Dispatched Tracking Id Complaint Dispatched Remarks First-Hearing/Scrutinized Remarks View Notice
HARERA THROUGH NEERAJ GAUTAM V/S
DIVERSE DEVELOPERS LLP
Self GURUGRAM PENDING 10-Jun-2024 Yes 21-Aug-2023 EH733094971IN NOTICE DISPATCHED TO THE RESPONDENT NON COMPLIANCE OF RC CONDITIONS
Notice Details
Notice Number Remarks Dispatching Date Dispatch Id View Notice
First Notice NOTICE DISPATCHED TO THE RESPONDENT 21-Aug-2023 EH733094971IN
Complaint Listing Details
Date of Hearing Status Proceedings of the day Bench Order Order Uploaded On
10-Jun-2024 PENDING --- ---
01-Apr-2024 PENDING Ms. Nikita (Planning Exeutive0 briefed the facts of the case. Ms. Alka Malik (Advocate) is present on behalf of the promoter.The AR states that the services have been completed and an application for grant of CC also stand made to DTCP on 15.02.2024. The AR further assures to submit the approved service plans and estimates within eight weeks.The matter to come up on 10.06.2024 ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA View Order 25-Apr-2024
22-Mar-2024 PENDING Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. Ms. Alka Malik (AR) along with advocate Garvit Gupta is present on behalf of the promoter. The AR of the promoter states that the matter is being pursued at the level of the DTCP where certain complications have arisen.  In view of the continued non- compliance of the conditions of registration, the matter be placed before the Authority in its next meeting fixed on 01.04.2024. ASHOK SANGWAN --- ---
01-Mar-2024 PENDING MATTER TO COME UP ON 22.03.2024. ASHOK SANGWAN View Order 19-Mar-2024
02-Feb-2024 PENDING Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. Ms. Alka Malik (AR) are present on behalf of the promoter and states that demand letter for deposit of bank guarantee amounting to Rs. 100.497 lacs has been received from DTCP on 30.11.2021which is placed on record. In view of the fact that the promoter has failed to submit the approval of service plans and estimates within the specified timeline of three months as per conditions of the registration certificate dated 17.04.2023, the security deposited by the promoter in lieu of the timely submission of all the above approval is hereby forfeited. The promoter is further directed to submit the approval from the competent authority within a period of one month failing which legal consequences including but not restricted to freezing of bank accounts and restriction for creating any further third-party rights shall follow. Matter to come up on 01.03.2024. ASHOK SANGWAN View Order 12-Feb-2024
19-Jan-2024 PENDING THE MATTER IS ADJOURNED TO 02.02.2024. ASHOK SANGWAN View Order 23-Jan-2024
15-Dec-2023 PENDING THE MATTER TO COME UP ON 15.12.2023  ASHOK SANGWAN SANJEEV KUMAR ARORA --- ---
07-Dec-2023 PENDING THE MATTER TO COME UP ON 15.12.2023  ASHOK SANGWAN View Order 12-Dec-2023
10-Nov-2023 PENDING THE MATTER TO COME UP ON 07.12.2023 AT 11:30 AM ASHOK SANGWAN View Order 20-Nov-2023
27-Oct-2023 PENDING THE MATTER TO COME UP ON 10.11.2023 AT 11:30 AM ASHOK SANGWAN View Order 02-Nov-2023
22-Sep-2023 FIRST HEARING Sh. Sanjeev Kumar (AR) is present on behalf of the promoter and states that the approval of service plans and estimates is pending at the level of DTCP and is likely to be issued soon. So far as the environmental clearance is concerned, their project does not fall under the category where EC is required and the requisite instructions/notification will be submitted within one week. The promoter has not complied with the conditions of registration and nor has he submitted the requisite BG on the basis of which the registration was issued. In view of the above, it is recommended that the registration of the project may be suspended, and the promoter be restrained from sale of any further inventory or creation of 3rd party rights in the project until compliance of the condition is made and/or BG is submitted. The matter to come up on 27.10.2023. ASHOK SANGWAN View Order 26-Oct-2023
Documents Submitted
Dak ID Receiving Date Submitted By Remarks
67220 01/03/2024 GARVIT GUPTA ADV APPLICATION ON BEHALF OF M/S DIVERSE DEVELOPERS LLP TO RECALL ORDER DT: 02.02.2024 & AFFIDAVIT WITH ANNEXURES IN SOU-MOTO COMPLIANT- 3867-2023.
57364 16/08/2023 HARERA THROUGH NEERAJ GAUTAM NEW COMPLAINT
79352 19/09/2024 SANDEEP CHAUDHARY ADV SUBMISSION OF COPY OF HREAT APPEAL NO.- 399-2024, DT: 09.09.2024.
61324 03/11/2023 TANISH REPLY TO SHOW-CAUSE NOTICE - 3867-2023, DATED: 21.08.2023 WITH 2 BG. ( BG NO.- 1651NDDG00047024, RS.- 10, 00, 000/-, BG NO.- 1651NDDG00046924, RS.- 10,00,000/- AND BG NO.- 1651NDDG00047124, RS.- 5,00,000/-, DT: 02.11.2023 )