Complaint Detail:RERA-GRG-3863-2023
Party Dtls Self / Adv Name District Current Status Next Date of Hearing Complaint Dispatched Complaint Dispatched On Dispatched Tracking Id Complaint Dispatched Remarks First-Hearing/Scrutinized Remarks View Notice
HARERA THROUGH NEERAJ GAUTAM V/S
MRG GROUP INDIA PRIVATE LIMITED (FORMERLY KNOWN AS ANUDHARA SOLUTIONS PRIVATE LIMITED))
Self GURUGRAM DISPOSED NOT REQUIRED Yes 21-Aug-2023 EH733094818IN NOTICE DISPATCHED TO THE RESPONDENT NON COMPLIANCE OF RC CONDITIONS
Notice Details
Notice Number Remarks Dispatching Date Dispatch Id View Notice
First Notice NOTICE DISPATCHED TO THE RESPONDENT 21-Aug-2023 EH733094818IN
Complaint Listing Details
Date of Hearing Status Proceedings of the day Bench Order Order Uploaded On
22-Mar-2024 DISPOSED Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. Sh. Chamangeet Monga (AR) is present on behalf of the promoter. The AR of the promoter states that the Authority may condone the delay in submission of the requisite clearance which has now been submitted. However, it is not disputed that the promoter was granted conditional registration at its own accord and depositing of security amount in the form of cheque in lieu of submission of the requisite clearances within the time specified in the conditional registration. It was clearly mentioned in the registration certificate that this guarantee shall be forfeited by the Authority in case the promoter fails to submit the approval within the stipulated time. In view of the fact that the promoter has failed to submit the approval of service plans and estimates within the specified timeline of three months as per conditions of the registration certificate no. 703/435/2023/47 dated 20.03.2023, the security deposited by the promoter in lieu of the timely submission of the above approval is hereby forfeited. The matter stands disposed of. ASHOK SANGWAN --- ---
29-Feb-2024 PENDING Matter is adjourned to 22.03.2024. ASHOK SANGWAN View Order 19-Mar-2024
23-Nov-2023 PENDING Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. The Authority is in the process of framing guidelines/Regulation to deal with cases of delayed compliance. The above matter shall be dealt according to the decision of the Authority in this regard. Till then, the proceedings may be kept pending. The matter to come up on 29.02.2024. ASHOK SANGWAN View Order 24-Nov-2023
10-Nov-2023 PENDING THE MATTER TO COME UP ON 23.11.2023 AT 11:30 AM ASHOK SANGWAN View Order 20-Nov-2023
27-Oct-2023 PENDING THE MATTER TO COME UP ON 10.11.2023 AT 11:30 AM ASHOK SANGWAN View Order 02-Nov-2023
22-Sep-2023 FIRST HEARING Proceedings dated 22.09.2023 Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. Ms. Anjana Gulati (AR) is present on behalf of the promoter. The AR of the promoter seeks 6 months’ time to submit the compliance of the conditions imposed. One final opportunity is granted for submitting the above compliance subject to the final decision of the Authority regarding delay in submission of compliance in terms of the registration certificate. Matter to come up on 27.10.2023 for further proceedings. ASHOK SANGWAN View Order 29-Sep-2023
Complaint Final Judgement Details
Date of Judgement Party Details Judgement Uploading Date View Judgement
22-Mar-2024 HARERA THROUGH NEERAJ GAUTAM V/S
MRG GROUP INDIA PRIVATE LIMITED (FORMERLY KNOWN AS ANUDHARA SOLUTIONS PRIVATE LIMITED))
--- ---