Comprehensive Complaint Details
Complaint Detail:RERA-GRG-3860-2023
Party Dtls Self / Adv Name District Current Status Next Date of Hearing Complaint Dispatched Complaint Dispatched On Dispatched Tracking Id Complaint Dispatched Remarks First-Hearing/Scrutinized Remarks View Notice
HARERA THROUGH NEERAJ GAUTAM V/S
ISHV REALTORS PRIVATE LIMITED
Self GURUGRAM PENDING 04-Mar-2024 Yes 21-Aug-2023 EH733094821IN NOTICE DISPATCHED TO THE RESPONDENT NON COMPLIANCE OF RC CONDITIONS
Notice Details
Notice Number Remarks Dispatching Date Dispatch Id View Notice
First Notice NOTICE DISPATCHED TO THE RESPONDENT 21-Aug-2023 EH733094821IN
Complaint Listing Details
Date of Hearing Status Proceedings of the day Bench Order Order Uploaded On
04-Mar-2024 PENDING --- ---
02-Feb-2024 PENDING Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. Sh. Shankar Wig (Advocate) is present on behalf of the promoter. The AR of the promoter states that ‘in principal’ approval of the revised building plans has been received and the promoter shall submit the pending approvals to the Authority within one month. In the peculiar circumstances of the case, the matter may be placed before the Authority on 04.03.2024. The restriction on creation of third-party rights shall continue meanwhile. ASHOK SANGWAN View Order 12-Feb-2024
19-Jan-2024 PENDING THE MATTER IS ADJOURNED TO 02.02.2024. ASHOK SANGWAN View Order 23-Jan-2024
15-Dec-2023 PENDING Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. Sh. Shankar Wig (Advocate) is present on behalf of the promoter. The counsel of the promoter states that the RERA registration was granted for the project on 02.02.2023 with the condition to submit the revalidated building plans, approved service plans and estimates, approved fire scheme and road access permission within three months. Thereafter, the promoter applied for revision in building plans and in- principle approval of the same was obtained on 23.11.2023. Now, the promoter is fulfilling the compliance of the conditions of in- principle approval of revision of building plans. In absence of the revalidated and revised building plans, the promoter was not able to obtain the approvals of service plans and estimates and fire scheme. The counsel for the promoter requests 90 days’ time to submit the compliance in the Authority. Keeping in view the facts submitted by the promoter, the promoter is directed not to create any 3rd party rights in the project without obtaining the revised RERA registration certificate for the project. One more opportunity is granted for submission of compliance of the conditions mentioned in registration certificate subject to the final decision of the Authority regarding delay in submission of compliance in terms of the registration certificate. Matter to come up on 19.01.2024. ASHOK SANGWAN View Order 20-Dec-2023
07-Dec-2023 PENDING THE MATTER TO COME UP ON 15.12.2023  ASHOK SANGWAN View Order 12-Dec-2023
10-Nov-2023 PENDING THE MATTER TO COME UP ON 07.12.2023 AT 11:30 AM ASHOK SANGWAN View Order 20-Nov-2023
27-Oct-2023 PENDING THE MATTER TO COME UP ON 10.11.2023 AT 11:30 AM ASHOK SANGWAN View Order 02-Nov-2023
22-Sep-2023 FIRST HEARING Proceedings dated 22.09.2023 Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. None is present on behalf of the promoter. One final opportunity is granted for submitting the above compliance subject to the final decision of the Authority regarding delay in submission of compliance in terms of the registration certificate. Matter to come up on 27.10.2023 for further proceedings. ASHOK SANGWAN View Order 29-Sep-2023