| 09-Sep-2024 |
PENDING |
|
|
--- |
--- |
| 08-Jul-2024 |
PENDING |
Ar. Neeraj Gautam [Associate Architectural Executive) briefed the facts of the case.Sh. Neeraj Mishra [ED) and Sh. Ashwani Kumar (AR) are present on behalf of the promoter.The AR of the promoter requested two months'time to submit the approved service plans and estimates in theAuthority,The matter to come up on 09.09.2024. |
ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
20-Aug-2024 |
| 08-Apr-2024 |
PENDING |
AR. NEERAJ GAUTAM ASSOCIATE
ARCHITECTURAL EXECUTIVE BRIEFED THE FACTS OF THE CASE.
SH. ASHOK KUMAR SH. ASHWANI
KUMAR ARE PRESENT ON BEHALF OF THE PROMOTER. SINCE THE PROMOTER HAS SUBMITTED
THE FIRE SCHEME APPROVAL WITH A DELAY OF 25 DAYS AND APPROVAL OF SERVICE PLANS
AND ESTIMATES IS YET TO BE SUBMITTED THE SECURITY AMOUNT SUBMITTED BY THE
PROMOTER ON ACCOUNT OF TIMELY SUBMISSION OF APPROVAL OF FIRE SCHEME AND SERVICE
PLAN ESTIMATES IS HEREBY FORFEITED.
THE MATTER WILL BE REVIEWED
AFTER THREE MONTHS ON 08.07.2024. |
ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
10-Apr-2024 |
| 12-Feb-2024 |
PENDING |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Ashok Kumar, Sh. Ashwani
Kumar are present on behalf of the promoter.
The Chairman of the promoter
states that the 37% of the consideration money from the allottees have been
received as per schedule of payment and amount spent at site in completion of
the building and development works are more than the amount received. Further
the promoter is submitting the BG on tentative estimate basis for release of
the approved service plans within six weeks.
The QPRs are being submitted
which be examined by the planning branch.
Matter to come up on
08.04.2024 for further proceedings. |
ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
--- |
--- |
| 02-Feb-2024 |
PENDING |
Ar. Neeraj Gautam (Associate Architectural
Executive) briefed the facts of the case.
Sh. Ashwani Kumar (AR) is present on
behalf of the promoter.
The Authority notes that the letter
dated 19.01.2024 from XEN HSVP Division VI Gurugram pertains to
non-availability of sewerage, water and road in sector 05, Sohna is in the form
of no objection and the last line states as under:
“Therefore, this office
has no objection if the agency arranges water from other source”.
The reply of the promoter for
non-submission of building plans and estimates is unsatisfactory especially in
view of the fact that another similarly situated project in Sohna sector 05 by
the name of “Mega City” has submitted the proposal for approval of service
plans and estimates to DTCP and has placed on record letter dated 17.07.2023 in
which bank guarantee has been demanded by DTCP Haryana for grant of approval of
the service plans and estimates. The text of the letter dated 17.07.2023 reads
as under:
“The service plan estimates of the above said colony
have been checked and corrected where ever necessary by chief engineer- I, HSVP
Panchkula and as per intimated cost by their office, you are required to
furnish the bank guarantee amounting to Rs. 268.26 lacs on account of IDW
against which you have already furnished the bank guarantee Rs. 79.87 lacs.
Therefore, you are requested to furnish an additional bank guarantee amounting
to Rs. 188.39 lacs on account of internal development work within 15 days, so
that service plan estimates could be approved.”
The promoter has failed to submit the
approval of service plans and estimates within the specified timeline of three
months as per conditions of the registration certificate dated 30.01.2023.
However, in the peculiar circumstances of the case, the matter may be placed
before Authority on 12.02.2024. Meanwhile, the promoter is directed not to
create any further third-party rights in the project.
Matter to come up on 12.02.2024 before the
Authority for further proceedings. |
ASHOK SANGWAN |
View Order |
12-Feb-2024 |
| 29-Dec-2023 |
PENDING |
Proceedings dated 29.12.2023
Ar. Neeraj Gautam (Associate Architectural
Executive) briefed the facts of the case.
Sh. Ashwani Kumar (AR) is present on behalf
of the promoter.
The AR of the promoter states that they are
pursuing the matter regarding service plans and estimates with the DTCP. DTCP
has till date not provided information
pertaining to road levels, sewer systems and water supply lines to enable them
to align the service plans and estimates with the current status of vital
components so that the service plans and estimates may be submitted before the
DTCP for approval. It is
expected that the levels for aligning the services in the project site will be
made available by the last week of January.
However, in a similar case of the project
“Mega City” located at sector 05, Sohna, it is noted that the DTCP has sought
bank guarantee from the promoter in the process of approval of service plans
and estimates.
The Authority has sought confirmation of
this fact submitted by the promoter through letter dated 07.12.2023 and no
reply from DTCP has been received yet. A reminder in this regard be issued to
the DTCP.
The matter to come up on 02.02.2024. |
ASHOK SANGWAN |
--- |
--- |
| 28-Dec-2023 |
PENDING |
Matter adjourned to 29.12.2023 |
ASHOK SANGWAN SANJEEV KUMAR ARORA |
--- |
--- |
| 23-Nov-2023 |
PENDING |
Proceedings dated 23.11.2023
Ar. Neeraj Gautam (Associate Architectural
Executive) briefed the facts of the case.
Sh. Ashwani Kumar (AR) is present on behalf
of the promoter.
The AR of the promoter states that they
have submitted another application before DTCP for providing information
pertaining to road levels, sewer systems and water supply lines to enable them
to align the service plans and estimates with the current status of vital
components so that the service plans and estimates may be submitted before the
DTCP for approval and a copy of same has been submitted in the Authority today.
The concerned executive of the Authority is
directed to send a letter to the DTCP seeking confirmation of the fact
submitted by the promoter regarding delay in approval being faced on account of
non- availability of information required from DTCP.
The promoter is directed to submit the above compliance subject to the final
decision of the Authority regarding delay in submission of compliance in terms
of the registration certificate.
The matter to come up on
28.12.2023. |
ASHOK SANGWAN |
View Order |
24-Nov-2023 |
| 26-Oct-2023 |
PENDING |
Proceedings dated 26.10.2023
Ar. Neeraj Gautam (Associate Architectural
Executive) briefed the facts of the case.
Sh. Ashwani Kumar (AR) is present on behalf
of the promoter. The AR of the promoter states that in sector 05 of Sohna, all
the promoters are facing an issue in the approval of service plan and
estimates. The promoter has submitted a representation to DTCP for providing information
pertaining to road levels, sewer systems and water supply lines to enable them
to align the service plans and estimates with the current status of vital
components. The promoter further requests six months’ time to get the approval
of service plans and estimates.
One opportunity is granted for submitting the above
compliance subject to the final decision of the Authority regarding delay in
submission of compliance in terms of the registration certificate.
The matter to come up on 23.11.2023
for further proceedings. |
ASHOK SANGWAN |
View Order |
31-Oct-2023 |
| 21-Sep-2023 |
FIRST HEARING |
Proceedings dated 21.09.2023
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Ms. Priyanka Aggarwal,
Advocate is present on behalf of the promoter.
The AR of the promoter seeks
one month time to submit the compliance of the conditions imposed.
One opportunity is granted
for submitting the above compliance subject to the final decision of the
Authority regarding delay in submission of compliance in terms of the
registration certificate.
The matter to come up on 26.10.2023. |
ASHOK SANGWAN |
View Order |
25-Sep-2023 |