| 05-Feb-2024 |
PENDING |
|
|
--- |
--- |
| 27-Dec-2023 |
PENDING |
The AR of the promoter stated
that the application for CC is still pending with the DGTCP. The matter to
come up on 05.02.2024 for further proceedings.
|
VIJAY KUMAR GOYAL |
View Order |
28-Dec-2023 |
| 22-Nov-2023 |
PENDING |
The AR submits that the
application for CC is still pending with the DGTCP. The matter to come up on 27.12.2023.
|
VIJAY KUMAR GOYAL |
View Order |
22-Dec-2023 |
| 25-Oct-2023 |
PENDING |
Sh.
Anitesh Singh (AR), Sh. Purushottam Grover (V.P) and Sh. Kulbhushan (Sr. GM)
are present on behalf of the promoter.
The
AR of the promoter stated that the OC for all the towers has already been
obtained and also uploaded on the website. Further he states that the CC is
applied and submit the same after obtaining from DTCP.
The
matter to come up on 22.11.2023 for further proceedings.
|
VIJAY KUMAR GOYAL |
View Order |
16-Nov-2023 |
| 13-Sep-2023 |
PENDING |
Sh. Anitesh Singh (Sr. Manager – Govt. Affairs)
is present on behalf of the promoter.
The AR submits that OC in respect of all the
units has already been obtained within the prescribed timeline and possession
also offered/handed over to RWA and CC for the whole of the project has
already been applied to DTCP and hence extension may not be insisted in such
cases. The AR is given six weeks’ time for submission of CC.
The matter to come up on 25.10.2023.
|
VIJAY KUMAR GOYAL |
View Order |
16-Nov-2023 |
| 16-Aug-2023 |
PENDING |
Sh. Anitesh Singh (Sr. Manager – Govt. Affairs)
is present on behalf of the promoter.
The AR submits that OC has been received before
the expiry of registration for the entire project and has already been
uploaded on the website. Further, states that CC is being applied and the
status of CC will be submitted within the next two weeks.
The matter to come up on 13.09.2023.
|
VIJAY KUMAR GOYAL |
View Order |
18-Aug-2023 |
| 26-Jul-2023 |
FIRST HEARING |
Sh. Anitesh Singh (Sr. Manager- Govt. affairs)
is present on behalf of the promoter. The AR of the promoter states that OC in
respect of construction and sold units have been received and handed over to
the allottees. Reply will be filed within 2 weeks.
The matter to come up on 16.08.2023.
|
VIJAY KUMAR GOYAL |
View Order |
09-Aug-2023 |