| 08-Nov-2023 |
PENDING |
|
|
--- |
--- |
| 06-Oct-2023 |
PENDING |
Sh. Rahul Yadav (Advocate) is present on
behalf of the promoter.
The AR of the promoter stated that they have
submitted the reply which needs to be scrutinized. However, it is notices
that there are 282 sold units out of which refund of allottees of 266 units
is done and 16 allottees are in process.
The matter to come up on 08.11.2023 for further proceedings.
|
VIJAY KUMAR GOYAL |
View Order |
15-Nov-2023 |
| 08-Sep-2023 |
PENDING |
The AR could not travel due to traffic
restriction in view of the G20 conference.
The matter to come up on 06.10.2023.
|
VIJAY KUMAR GOYAL |
View Order |
15-Nov-2023 |
| 16-Aug-2023 |
PENDING |
Sh. Rahul Yadav (Advocate) is present on behalf
of the promoter.
The AR seeks one week time to submit detailed
reply with respect to the status of the project. The project is not developed
and refund to about more than 90% to the allottees has already been made.
Detailed status will be filed within one week.
The matter to come up on 08.09.2023.
|
VIJAY KUMAR GOYAL |
View Order |
18-Aug-2023 |
| 26-Jul-2023 |
FIRST HEARING |
Sh. Vikas Sachdeva and Sh. Rahul Yadav
(Advocate) are present on behalf of the promoter. Advocate Sh. Rahul Yadav
has put in appearance and is filing resolution of the promoter to be in
appearance and request for 2 seeks time to file the reply to the notice along
with status of the project and likely date of completion is not already
complete and also assures to apply for extension in next three weeks. The
matter to come up on 16.08.2023.
|
VIJAY KUMAR GOYAL |
View Order |
09-Aug-2023 |