| 22-Nov-2023 |
PENDING |
|
|
View Order |
22-Dec-2023 |
| 25-Oct-2023 |
PENDING |
Sh. Prince Kumar (Manager) is
present on behalf of the promoter.
The
reply submitted by the promoter be examined and put up on file.
The
matter to come up on 22.11.2023 for further proceedings.
|
VIJAY KUMAR GOYAL |
View Order |
16-Nov-2023 |
| 11-Oct-2023 |
PENDING |
The person present is not
carrying any authorization and hence not heard. One last opportunity is
granted to submit present status and schedule of
completion of the project and making application for registration.
The matter to come up on
25.10.2023.
|
VIJAY KUMAR GOYAL |
View Order |
15-Nov-2023 |
| 13-Sep-2023 |
PENDING |
Sh. Prince
Kumar (Sr. Manager) is present on behalf of the promoter.
The AR submits
that out of registered area of 52.37125 acres.
The promoter
stated that license no. 33 of 2017 having total area 6.81 acres out of which
5.31 acres migrated from license no. 19 of 2014 and 1.50 acres is fresh area.
License no. 88 of 2017 having total area 8.8125 acres out of which 6.56875
acres migrated from license no. 19 of 2014 and 2.24375 acres is fresh area
and both the project of DDJAY are completed and completion certificate also
granted by DTCP.
License no. 28
of 2023 having area 7.3875 acres migrated from license no 19 of 2014 and
License no. 34 of 2023 having area 13.2875 acres out of which 11.2625 acres
migrated from license no. 19 of 2014.
Total migrated
area from License no. 19 of 2014 is 30.52875 acres and balance area left in
license no. 19 of 214 is 27.1525 acres.
It is noticed
that four pockets have been migrated to DDJAY from the license no. 19 of 2014.
Further, promoter states that all the remaining infrastructure works are
almost complete in the balance area except Electricity connection. As soon as
electric connection is completed, they can apply for completion certificate.
The
matter to come up on 11.10.2023. |
VIJAY KUMAR GOYAL |
View Order |
28-Dec-2023 |
| 16-Aug-2023 |
PENDING |
Sh. Prince Kumar (Sr. Manager) is present on behalf
of the promoter.
The AR submits that the promoter has obtained
migration of the license from the DTCP for the land admeasuring 7.875 acres
and 11.2625 acres and for remaining area, development works have been
completed except provisions of electricity connection from DHBVN. Further,
the promoter is applying for CC of this portion from the DTCP shortly and
shall be applying for extension in the Authority as OC/CC is not yet
obtained. The AR seeks three weeks’ time for applying for extension. One last
opportunity is being given. Reply is also being submitted today.
The matter to come up on 13.09.2023.
|
VIJAY KUMAR GOYAL |
View Order |
18-Aug-2023 |
| 26-Jul-2023 |
FIRST HEARING |
None is present on behalf of the promoter. One
more opportunity is being granted to the promoter to put in appearance and to
file the reply alongwith copy of OC/CC/ Part CC if obtained failing which
further penal action shall be initiated including freezing of the bank
account and putting restrictions on any sale in the above project. The concerned PE is hereby directed to
ensure issuance of a notice alongwith above proceedings to the promoter
within one week.
The matter to come up on 16.08.2023.
|
VIJAY KUMAR GOYAL |
View Order |
09-Aug-2023 |