| 16-Jun-2026 |
PENDING |
|
|
--- |
--- |
| 09-Jun-2026 |
PENDING |
THE MATTER IS ADJOURNED TO 16.06.2026 |
ANU |
View Order |
09-Jun-2026 |
| 30-Mar-2026 |
PENDING |
THE MATTER IS ADJOURNED TO 09.06.2026 |
ANU |
View Order |
22-May-2026 |
| 02-Mar-2026 |
PENDING |
THE MATTER IS ADJOURNED TO 30.03.2026 |
ANU |
View Order |
10-Mar-2026 |
| 21-Jun-2023 |
PENDING |
MATTER TO COME UP ON 02.03.2026 |
ANU |
--- |
--- |
| 17-Mar-2023 |
PENDING |
MATTER TO COME UP ON 21.06.2023 |
VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
--- |
--- |
| 24-Feb-2023 |
FIRST HEARING |
Proceedings
dated 24-02-2023.
Sh.
Hokesh Kumar (CRM Manager) is present on behalf of the promoter.
At the
time of issuance of registration certificate, as per clause I (ii) the promoter
has to submit the bank guarantee of Rs. 15 lakhs and Rs. 10 lakhs each as a
guarantee for compliance of submission of approved service plan and estimates
and revalidated building plan within 15 days from the date of issuance of RC
which has not been complied by the promoter till date.
Therefore,
the promoter is directed to submit the BG’s/cheques by 27-02-2023 otherwise the
registration certificate may be revoked.
Matter to come up on 17-03-2023. |