| HARERA GURUGRAM THROUGH JYOTI V/S SIGNATUREGLOBAL HOMES PRIVATE LIMITED |
Self | GURUGRAM | PENDING | 06-Jan-2023 | Yes | 15-Jun-2022 | EH316626507IN | PROJECT RC COMPLIANCE HEARING | PROJECT RC COMPLIANCES HEARING |
| Notice Number | Remarks | Dispatching Date | Dispatch Id | View Notice |
|---|---|---|---|---|
| First Notice | PROJECT RC COMPLIANCE HEARING | 15-Jun-2022 | EH316626507IN |
| Date of Hearing | Status | Proceedings of the day | Bench | Order | Order Uploaded On |
|---|---|---|---|---|---|
| 06-Jan-2023 | PENDING | --- | --- | ||
| 18-Nov-2022 | PENDING | Proceedings dated: 18-11-2022 Ms. Jyoti Yadav, Planning Executive briefed about the facts of the project. Sh. Anurag Srivastava (Manager) is present on behalf of the promoter. The AR of the promoter states that the approval for service plans and estimates has been received vide letter No. LC 3856-JE(MK)2021/999 dated 15.01.2021. A copy of the same is being handed over to the Planning Branch today. It is observed that the approval granted is for a combined area of 10.55 acres and registration was granted for 6.293 acres. The AR of the promoter explained that the area comprises of two projects namely Signature Global Park-III (registered vide RC No. 40 of 2020) and Signature Park-III Ext. Phase-II (registered vide RC No. 44 of 2019). The matter to come up for further proceeding on 06-01-2023. | K K KHANDELWAL VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA | View Order | 29-Nov-2022 |
| 01-Jul-2022 | FIRST HEARING | The promoter is directed to submit the deficit documents to comply with the conditions of registration certificate. Matter to come up on 18-11-2022. | K K KHANDELWAL VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA | --- | --- |
| Dak ID | Receiving Date | Submitted By | Remarks |
|---|---|---|---|
| 35057 | 11/06/2022 | JYOTI | NEW COMPLAINT |
| 40223 | 30/08/2022 | SHARAD GOYAL | REPLY OF SHOW CAUSE NOTICE FOR REVOCATION OF RC OF NOTICE- 4397-2022, DATED: 15.06.2022. |