Quarterly Schedules | ||
| HRERA Panchkula | ||
| Project Registration Number : HRERA-PKL-JJR-1-2018 | ||
| Project Name : MODEL ECONOMY TOWNSHIP INDUSTRIAL COLONY | ||
| Project Number : RERA-PKL-483-2019 | ||
| Project Type : ONGOING | ||
| Report Online Submission Date : 12-Nov-2019 |
| Particulars | Expenditure already incurred up to the date of registration. (In Lakhs) | Total Estimated/ Revised cost of project. (In Lakhs) |
| Land | 13447.97 | 15122.92 |
| Building | 0 | 0 |
| Infrastructure facilities, etc. | 4260 | 25187.73 |
| Other costs including EDC, IDC, etc. | 775 | 1475.04 |
| Total | 18482.97 | 41785.69 |
| Name of the approval | Status | Date |
| Layout Plan | Revised approval obtained on | 30-12-2022 |
| Demarcation Plan | Revised approval obtained on | 16-02-2023 |
| Zoning Plan | Revised approval obtained on | 24-05-2023 |
| Service Plans | Obtained Approval on | 06-06-2023 |
| Electricity Plans | Revised approval obtained on | 19-02-2025 |
| Name of the approval | Status | Date |
| Demarcation Plan | Have not applied till date | N/A |
| Zoning Plan | Have not applied till date | N/A |
| Service Plans | Have not applied till date | N/A |
| Electricity Plans | Have not applied till date | N/A |
| Site Plans | Have not applied till date | N/A |
| Building Plans | Have not applied till date | N/A |
| FIre NOC | Have not applied till date | N/A |
| Total Expenditure on the project | 14428.67 |
| Expenditure made upto the date of Registration | 4260 |
| EDC due as on the date of Registration | 0.00 |
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 25491.7 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 510.6 |
| 3 | Amount availed from the bank/financial institutions | 0.0 |
| 4 | Amount contributed by the promoters/his associates | 348.8 |
| 5 | Any other receipt | 0.0 |
| Total | 26351.1 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 17167.40 |
| 2 | Cost of construction of apartments | 0.00 |
| 3 | Cost of infrastructure & other structure | 6030.23 |
| 4 | Other costs including EDC, taxes, etc | 902.69 |
| Total | 24100.32 | |
| Balance | 8476.61 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 1906.66 |
| 2 | Amount deposited in Escrow Account | 389.76 |
| 3 | Amount withdrawn during the quarter | 45.00 |
| 4 | Balance at the end of the quarter | 2251.43 |
| Total Plots in the colony | 66 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL | 36 |
| Total Apartments in the colony | 66 |
| Apartments sold upto the date of Registration | 36 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | INDUSTRIAL | 6 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 6030.23 |
| 2 | Apartments | 0.00 |
| 3 | EDC, IDC, etc | 902.69 |
| 4 | Others Expenditure | 0.00 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0.00 |
| 2 | EDC due as on date | 0.00 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 26351.8 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 522.54 |
| 3 | Amount availed from the bank/financial institutions | 0.0 |
| 4 | Amount contributed by the promoters/his associates | -365.20 |
| 5 | Any other receipt | 0.0 |
| Total | 26509.1 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 17167.40 |
| 2 | Cost of construction of apartments | 0.0 |
| 3 | Cost of infrastructure & other structure | 7680.86 |
| 4 | Other costs including EDC, taxes, etc | 909.66 |
| Total | 25757.92 | |
| Balance | 6819.01 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 2251.43 |
| 2 | Amount deposited in Escrow Account | 1504.22 |
| 3 | Amount withdrawn during the quarter | 3004.50 |
| 4 | Balance at the end of the quarter | 751.14 |
| Total Plots in the colony | 66 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 7680.86 |
| 2 | Apartments | 0.00 |
| 3 | EDC, IDC, etc | 0.00 |
| 4 | Others Expenditure | 909.66 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 26509.1 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 50.88 |
| 3 | Amount availed from the bank/financial institutions | 0.0 |
| 4 | Amount contributed by the promoters/his associates | -558.87 |
| 5 | Any other receipt | 0.0 |
| Total | 26001.1 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 17167.40 |
| 2 | Cost of construction of apartments | 0.0 |
| 3 | Cost of infrastructure & other structure | 7921.81 |
| 4 | Other costs including EDC, taxes, etc | 912.20 |
| Total | 26001.40 | |
| Balance | 6575.53 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 751.14 |
| 2 | Amount deposited in Escrow Account | 48.8 |
| 3 | Amount withdrawn during the quarter | 799.75 |
| 4 | Balance at the end of the quarter | 0.19 |
| Total Plots in the colony | 66 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL | 2 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 7921.81 |
| 2 | Apartments | 0.0 |
| 3 | EDC, IDC, etc | 0.0 |
| 4 | Others Expenditure | 912.20 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 26001.1 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 185.06 |
| 3 | Amount availed from the bank/financial institutions | 0.0 |
| 4 | Amount contributed by the promoters/his associates | 367.53 |
| 5 | Any other receipt | 0.0 |
| Total | 26553.70 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 17167.40 |
| 2 | Cost of construction of apartments | 0.0 |
| 3 | Cost of infrastructure & other structure | 8471.02 |
| 4 | Other costs including EDC, taxes, etc | 915.09 |
| Total | 26553.50 | |
| Balance | 6023.43 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.19 |
| 2 | Amount deposited in Escrow Account | 116.00 |
| 3 | Amount withdrawn during the quarter | 116.00 |
| 4 | Balance at the end of the quarter | 0.19 |
| Total Plots in the colony | 66 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 8471.02 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 915.09 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 26553.7 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | -26.84 |
| 5 | Any other receipt | 0 |
| Total | 26526.86 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 17167.40 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 8432.27 |
| 4 | Other costs including EDC, taxes, etc | 927.00 |
| Total | 26526.66 | |
| Balance | 25945.26 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.19 |
| 2 | Amount deposited in Escrow Account | 0.50 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0.69 |
| Total Plots in the colony | 66 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL | 0 |
| 2 | COMMERCIAL | 0 |
| 3 | GROUP HOUSING | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | APARTMENT | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | -38.75 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 11.91 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 8356.18 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 8356.18 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | -3607.53 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 1262.13 |
| 4 | Other costs including EDC, taxes, etc | -41.88 |
| Total | -2387.29 | |
| Balance | 10743.47 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.69 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0.69 |
| Total Plots in the colony | 64 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 1262.13 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | -41.88 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 10743.46 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 102.56 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 10846.02 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 0.00 |
| 2 | Cost of construction of apartments | 0.00 |
| 3 | Cost of infrastructure & other structure | 199.57 |
| 4 | Other costs including EDC, taxes, etc | -17.70 |
| Total | 181.87 | |
| Balance | 10664.16 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.69 |
| 2 | Amount deposited in Escrow Account | 32.75 |
| 3 | Amount withdrawn during the quarter | 32.75 |
| 4 | Balance at the end of the quarter | 0.69 |
| Total Plots in the colony | 64 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL | 4 |
| 2 | COMMERCIAL | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | N.A | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 199.56 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | -17.7 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 10664.16 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 118.23 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 10782.39 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 0 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | -28.48 |
| 4 | Other costs including EDC, taxes, etc | 0 |
| Total | -28.48 | |
| Balance | 10810.87 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.69 |
| 2 | Amount deposited in Escrow Account | 176 |
| 3 | Amount withdrawn during the quarter | 176 |
| 4 | Balance at the end of the quarter | 0.69 |
| Total Plots in the colony | 64 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL PLOTS | 3 |
| 2 | COMMERCIAL PLOTS | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | -28.48 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 10810.87 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 422.53 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 11233.4 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 0.00 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 197.34 |
| 4 | Other costs including EDC, taxes, etc | 0.00 |
| Total | 197.34 | |
| Balance | 11036.06 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.69 |
| 2 | Amount deposited in Escrow Account | 452.04 |
| 3 | Amount withdrawn during the quarter | 452.04 |
| 4 | Balance at the end of the quarter | 0.69 |
| Total Plots in the colony | 64 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL PLOTS | 3 |
| 2 | COMMERCIAL PLOTS | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | N.A | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 197.34 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 11036.06 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 1582.99 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 12619.05 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 0 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 273.92 |
| 4 | Other costs including EDC, taxes, etc | 0 |
| Total | 273.92 | |
| Balance | 12345.13 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.69 |
| 2 | Amount deposited in Escrow Account | 1109.34 |
| 3 | Amount withdrawn during the quarter | 1109.34 |
| 4 | Balance at the end of the quarter | 0.69 |
| Total Plots in the colony | 59 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 273.92 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 867.42 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 12345.13 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 296.63 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 12641.76 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | -15.40 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 682.95 |
| 4 | Other costs including EDC, taxes, etc | 0 |
| Total | 667.55 | |
| Balance | 11974.21 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.69 |
| 2 | Amount deposited in Escrow Account | 207.19 |
| 3 | Amount withdrawn during the quarter | 207.19 |
| 4 | Balance at the end of the quarter | 0.69 |
| Total Apartments in the colony | 64 |
| Apartments sold upto the date of Registration | 36 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | INDUSTRIAL PLOTS (NO OPTION TO FILL DETAILS OF PLOT) | 1 |
| 2 | COMMERCIAL PLOTS (NO OPTION TO FILL DETAILS OF PLOT) | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | N.A. | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 682.95 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 12641.76 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 30.72 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 12672.48 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 0 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 424.28 |
| 4 | Other costs including EDC, taxes, etc | 57.45 |
| Total | 481.73 | |
| Balance | 1045.37 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.69 |
| 2 | Amount deposited in Escrow Account | 117.85 |
| 3 | Amount withdrawn during the quarter | 118.54 |
| 4 | Balance at the end of the quarter | 0 |
| Total Apartments in the colony | 64 |
| Apartments sold upto the date of Registration | 36 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | INDUSTRIAL | 1 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 424.28 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 12672.48 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 294.44 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 12966.92 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 13032.79 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 11335.74 |
| 4 | Other costs including EDC, taxes, etc | 982.98 |
| Total | 25351.51 | |
| Balance | 1488.48 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 244.78 |
| 3 | Amount withdrawn during the quarter | 244.78 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 64 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL PLOTS | 1 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 11335.74 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 982.98 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 982.98 |
| 2 | EDC due as on date | 1.77 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 12379.42 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 108.83 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 12488.25 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 31.79 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 218.55 |
| 4 | Other costs including EDC, taxes, etc | -89.65 |
| Total | 160.69 | |
| Balance | 12327.57 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 76.21 |
| 3 | Amount withdrawn during the quarter | 76.21 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 64 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL PLOTS | 0 |
| Total Apartments in the colony | 66 |
| Apartments sold upto the date of Registration | 36 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 11554.29 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 893.33 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 893.33 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 12327.57 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 1992.65 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 14320.22 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 383.94 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 254.17 |
| 4 | Other costs including EDC, taxes, etc | 99.10 |
| Total | 737.20 | |
| Balance | 13583.02 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 1673.10 |
| 3 | Amount withdrawn during the quarter | 1673.10 |
| 4 | Balance at the end of the quarter | 0 |
| Total Apartments in the colony | 64 |
| Apartments sold upto the date of Registration | 36 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | INDUSTRIAL PLOTS | 1 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NA | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 254.17 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 99.10 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 13583.02 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 3364.63 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 16947.65 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | -0.55 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 58.74 |
| 4 | Other costs including EDC, taxes, etc | 0 |
| Total | 58.19 | |
| Balance | 16889.46 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 2218.78 |
| 3 | Amount withdrawn during the quarter | 2218.78 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 85 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL | 1 |
| 2 | COMMERCIAL | 0 |
| 3 | PARKING | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 58.74 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 16889.46 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 2223 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 19112.46 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 0 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 10007.61 |
| 4 | Other costs including EDC, taxes, etc | 0 |
| Total | 10007.61 | |
| Balance | 9104.85 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 1661.30 |
| 3 | Amount withdrawn during the quarter | 1661.30 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 85 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL | 1 |
| 2 | COMMERCIAL | 0 |
| 3 | PARKING | 0 |
| Total Apartments in the colony | 85 |
| Apartments sold upto the date of Registration | 36 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | INDUSTRIAL | 0 |
| 2 | COMMERCIAL | 0 |
| 3 | PARKING | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 10007.61 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 9104.85 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 432.37 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 9537.22 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | -1680.46 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | -173.29 |
| 4 | Other costs including EDC, taxes, etc | 23.62 |
| Total | -1830.13 | |
| Balance | 7707.09 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 469.06 |
| 3 | Amount withdrawn during the quarter | 469.06 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 121 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL | 1 |
| 2 | COMMERCIAL | 0 |
| 3 | PARKING | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NA | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NA | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | -173.29 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 23.62 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 7707.09 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 517.30 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 8224.39 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 0 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 213.65 |
| 4 | Other costs including EDC, taxes, etc | 419.41 |
| Total | 633.06 | |
| Balance | 7591.33 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 431.41 |
| 3 | Amount withdrawn during the quarter | 431.41 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 121 |
| Plots sold upto the date of Registration | 36 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL | 0 |
| 2 | COMMERCIAL | 0 |
| 3 | PARKING | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NA | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NA | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 213.65 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 419.41 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 7591.33 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 500.57 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 8091.90 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | -5.54 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 405.49 |
| 4 | Other costs including EDC, taxes, etc | 0.04 |
| Total | 399.98 | |
| Balance | 7691.92 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 476.95 |
| 3 | Amount withdrawn during the quarter | 476.95 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 121 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL | 6 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NOT APPLICABLE | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 405.49 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0.04 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 7691.92 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 1233.31 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 8925.23 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 0 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 558.04 |
| 4 | Other costs including EDC, taxes, etc | 0 |
| Total | 0 | |
| Balance | 8367.19 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 1001.42 |
| 3 | Amount withdrawn during the quarter | 1001.42 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 121 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL PLOT | 16 |
| Total Apartments in the colony | 121 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | INDUSTRIAL PLOT | 13 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 558.04 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 8367.19 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 3157.90 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 11525.09 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 0 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | -113.19 |
| 4 | Other costs including EDC, taxes, etc | 0 |
| Total | -113.19 | |
| Balance | 11638.28 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 3026.75 |
| 3 | Amount withdrawn during the quarter | 3026.75 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 121 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL PLOTS | 9 |
| Total Apartments in the colony | 121 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | INDUSTRIAL PLOTS | 9 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | -113.91 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 11638.28 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 1503.99 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 13142.27 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 0 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 122.38 |
| 4 | Other costs including EDC, taxes, etc | 0 |
| Total | 0 | |
| Balance | 13019.89 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 1824.83 |
| 3 | Amount withdrawn during the quarter | 1824.83 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 121 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL PLOTS | 0 |
| Total Apartments in the colony | 121 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | INDUSTRIAL PLOTS | 3 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 122.38 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 13019.89 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 880.66 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 13900.55 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 0 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 33.84 |
| 4 | Other costs including EDC, taxes, etc | 0 |
| Total | 33.84 | |
| Balance | 13866.71 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 1078.68 |
| 3 | Amount withdrawn during the quarter | 1058.67 |
| 4 | Balance at the end of the quarter | 20.01 |
| Total Plots in the colony | 67 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL | 0 |
| Total Apartments in the colony | 66 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | INDUSTRIAL | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NA | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 33.84 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 13866.71 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 298.48 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 14165.19 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 0.03 |
| 2 | Cost of construction of apartments | 36.56 |
| 3 | Cost of infrastructure & other structure | 0 |
| 4 | Other costs including EDC, taxes, etc | 0 |
| Total | 36.60 | |
| Balance | 14128.59 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 20.01 |
| 2 | Amount deposited in Escrow Account | 378.13 |
| 3 | Amount withdrawn during the quarter | 397.86 |
| 4 | Balance at the end of the quarter | 0.28 |
| Total Plots in the colony | 121 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL PLOT | 1 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 36.56 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 14128.59 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0.06 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 14128.65 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 0 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | -362.94 |
| 4 | Other costs including EDC, taxes, etc | 34.55 |
| Total | -328.39 | |
| Balance | 14457.04 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.28 |
| 2 | Amount deposited in Escrow Account | 133.87 |
| 3 | Amount withdrawn during the quarter | 132.56 |
| 4 | Balance at the end of the quarter | 1.60 |
| Total Plots in the colony | 121 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL | 0 |
| Total Apartments in the colony | 121 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | INDUSTRIAL | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | -362.94 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 34.55 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 14457.04 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 14457.04 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 0 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | 24.36 |
| 4 | Other costs including EDC, taxes, etc | 0 |
| Total | 24.36 | |
| Balance | 14432.68 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 1.60 |
| 2 | Amount deposited in Escrow Account | 111.34 |
| 3 | Amount withdrawn during the quarter | 112.94 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 66 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL P[LOT | 0 |
| Total Apartments in the colony | 66 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | INDUSTRIAL PLOT | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 24.36 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 14432.68 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 274.95 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 14707.63 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Land | 0 |
| 2 | Cost of construction of apartments | 0 |
| 3 | Cost of infrastructure & other structure | -121.25 |
| 4 | Other costs including EDC, taxes, etc | 3.53 |
| Total | -117.72 | |
| Balance | 14825.35 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 612.64 |
| 3 | Amount withdrawn during the quarter | 612.63 |
| 4 | Balance at the end of the quarter | 0.01 |
| Total Plots in the colony | 121 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | INDUSTRIAL PLOT | 5 |
| Total Apartments in the colony | 121 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | INDUSTRIAL PLOT | 5 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | -121.25 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 3.53 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||