Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
MAHIRA HOMES 63A REVENUE ESTATE VILLAGE BEHRAMPUR SECTOR 63A GURUGRAM Wazirabad ST CZAR BUILDWELL PRIVATE LIMITED
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/388/120/2020/04 DATED 20.01.2020 RERA-GRG-377-2019 12-Dec-2019 09-Dec-2019 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 19-Dec-2019 by hand 1st deficiency notice
1st deficiency notice sent to the promoter View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/388/120/2020/04 DATED 20.01.2020 25-Jan-2020 RC uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
16-Jan-2020 The authority directed the promoter to submit the affidavit regarding submission of deficit document. After submission of affidavit RC may be granted with subject to following conditions: Further, the promoter shall submit Fire Scheme approval, Approved service plan and estimates, Environment clearance within 3 months otherwise penal proceedings may initiated. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS ---
13-Jan-2020 The matter is Adjourned to 16.01.2020. OBJECTION ---
30-Dec-2019 No one appeared on behalf of the promoter. Further, the case is fixed for next date on 13.01.2020. EXAMINATION BY AUTHORITY ---
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
07-Jan-2020 No one appeared on behalf of the promoter. Further, the case is fixed for next date on 13.01.2020. Not Yet