23-Jun-2020 |
In the last meeting decision to register the
project was taken subject to condition that the license expiring in near future
shall be got renewed and service plan and estimates be submitted within three
months. DPI needs to be corrected particularly with reference to the transfer
of community facility/commercial facilities to be handed over to the
association of allottees. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |
22-Jun-2020 |
the matter is adjourned to 23.06.2020 |
OBJECTION |
--- |
09-Jun-2020 |
During
online hearing, Sh. Vikram is present on behalf of the builder authorized
through board resolution. It has come to the notice of the authority that the
promoter has not submitted the deficit documents which are as follows:
·
License
no. 44 of 2010 valid till 08.06.2020. ·
Service
plan estimates applied to DTCP, but final approval awaited. ·
List
of sold unsold inventory.
Part-C-Project Details ·
Details
of Encumbrance on land. Part-H-Details of
Separate Bank Account ·
Board resolution mentioning 100% Master, 70% RERA
& 30%-Free a/c. Part-I-Quarterly
Schedule of Physical & financial Progress ·
ROC
statement showing details of charges. ·
Statement
of quarterly estimated expenditure & source of funds along with net cash
flow statement in the format provided in DPI. The promoter is also directed
to give details of the account where the money of sold inventory has been
deposited. The promoter shall submit the affidavit regarding a deposit of 70% of
the sale proceeds in the RERA account. Also, the details of the loan taken against this project need to be submitted.
Next date of hearing is fixed for 22.06.2020 |
OBJECTION |
--- |
07-Apr-2020 |
the matter will be heard on 09.06.2020 |
OBJECTION |
--- |
03-Mar-2020 |
the matter will be heard o 07.04.2020 |
ADJOURNMENT |
--- |
17-Feb-2020 |
The Hearing is Adjourned for 03.03.2020 |
ADJOURNMENT |
--- |
27-Jan-2020 |
The authority
directed the promoter to submit the deficit documents which are mentioned
below:-
1)
Renewal of license no 44 of
2010.
2)
Approved Service plan and
estimates.
3)
Project report.
4)
Deficit Fee - Rs. 1,56,62,477/-.
5)
Non encumbrances certificate,
if encumbrances than the ROC form.
6)
Sale Deed for supporting land
cost.
7)
Interest on EDC INR 4377.64
lacs needs to be explained.
8)
Interest on loan INR 9854.22
lacs needs to be provided.
9)
Approved supporting documents.
10)Details of
financial resources of the project.
11)Details of
100%, 70% & 30% needs to be filled in DPI.
12)Board
resolution to be resubmitted.
13)Affidavit
of promoter regarding arrangement with bank of master account.
14)Undertaking
from bank regarding RERA compliance.
15)Repayment
schedule of bank loan.
16)ROC
Statement showing details of charges.
17)Loan
sanction letter from financial institutions.
18)Details of
assets mortgaged/charged to the bank.
19)Copy of
annual report of 2018-19.
20)CA
certificate for expenses incurred & inventory valuation.
21)DPI needs
to be submit after the corrections.
Next Date of
hearing be fixed on 17.02.2020. |
ADJOURNMENT |
--- |
30-Dec-2019 |
The matter is Adjourned for hearing on 27.01.2020. |
ADJOURNMENT |
--- |
16-Dec-2019 |
The matter is Adjourned for hearing on 30.12.2019. |
EXAMINATION BY AUTHORITY |
--- |