| Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
|---|---|---|---|---|
| SAAN VERDANTE | SECTOR-95 | GURUGRAM | Gurgaon | SAAN Procon Pvt. Ltd. |
| Project Registration Number | Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks | Details of Project(Form A-H) |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| GGM/361/93/2019/55 DATED 01.10.2019 | RERA-GRG-262-2019 | 14-Aug-2019 | 19-Jun-2019 | Extension Certificate Uploaded | NOT REQUIRED | Not Yet | -- | Deficiency hearing | View Form(A-H) |
| Date of Hearing | Proceedings of the day | Status | Order |
|---|---|---|---|
| 06-Sep-2019 | RC Approved dated 06-09-20 | APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS | --- |
| 06-Sep-2019 | OBJECTION | --- | |
| 30-Aug-2019 | Deficiencies conveyed | OBJECTION | --- |
| 21-Aug-2019 | Deficiencies conveyed | OBJECTION COMPLIANCE DONE | --- |
| 05-Aug-2019 | Deficiencies conveyed | OBJECTION COMPLIANCE DONE | --- |
| 19-Jul-2019 | Deficiencies conveyed | OBJECTION COMPLIANCE DONE | --- |
| 03-Jun-2019 | Deficiency notice conveyed | EXAMINATION BY AUTHORITY | --- |
| Deficiency Date | Deficiency Remarks | Online Compliance Done | Online Compliance Date | Online Compliance Remarks | Compliance Date | Compliance Remarks |
|---|---|---|---|---|---|---|
| 30-Aug-2019 | Deficiencies conveyed | Not Yet | ||||
| 28-Aug-2019 | Deficiencies conveyed | Not Yet | ||||
| 28-Aug-2019 | Deficiencies conveyed | Not Yet | 22-Aug-2019 | reply submitted | ||
| 28-Aug-2019 | Deficiencies conveyed | Not Yet | 05-Aug-2019 | Reply submitted | ||
| 28-Aug-2019 | Deficiency notice conveyed | Not Yet | 12-Jul-2019 | Reply submitted |