| 05-Nov-2026 |
Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the case.
Sh. Sanjeev Sharma (Director), Sh. Parveen Verma, Sh. Dr. Himanshu and
Ms. Renu are present on behalf of the promoter.
The Director of the promoter company submits that an application dated 14.10.2026
has been submitted in the Authority seeking registration of the project namely
“MVN Aero One Phase 2”. The license no. 59 of 2024 dated 07.06.2024
valid up to 06.06.2029 was issued by DTCP in favour of M/s Gova Realtors Pvt. Ltd., M/s MVN Tutorials Pvt. Ltd. and M/s MVN
Infrastructure Projects LLP in collaboration with M/s MVN Infrastructure
Projects LLP for the development of Mixed Land Use Colony over an area
admeasuring 6.775 acres.
The Director of the promoter company further submits that presently, Revised
Fire Scheme Approval and Revised Service plan and Estimates have not yet been
obtained as on date. Further, the director of the promoter company undertakes
to obtain and submit:
i.
Revised Fire Scheme within 6 months from the date of
grant of registration Certificate.
ii. Revised
Service Plans and Estimates within 6 months from the date of grant of
registration Certificate.
Further, he undertakes to submit two separate Demand Drafts/Bank
Guarantees amounting to Rs. 25 lakhs each as a security deposit for timely
compliance with the above requirement at point (i) and (ii). It is also
expressly undertaken that in the event of failure to obtain and submit the
aforesaid approvals within the stipulated time frames, the security amount
shall be liable to be forfeited by the Authority.
The Authority has taken note of the submissions made by the Director of
the promoter company regarding the non-availability of the aforesaid statutory
approvals as on date. In view of the above, and in the interest of regulatory
compliance, the Authority hereby directs that the promoter shall submit two separate
Demand Drafts/Bank Guarantees, amounting to Rs. 25,00,000/- (Rupees Twenty-Five
Lakhs only) each, in favour of the Authority, as security amount for timely
submission of the following approvals:
a.
Revised Fire Scheme: within 6 months from the date
of grant of registration Certificate.
b.
Revised Service Plans and Estimates: within 6 months
from the date of grant of registration Certificate.
Needless to say that in the event of non-submission of the above
approvals within the stipulated time frames as requested by the Promoter during
the course of hearing, the security amount shall stand forfeited by the
Authority, and such failure may also attract additional regulatory action as
permissible under the Act of 2016, rules and regulations made thereunder.
Approved as proposed subject to rectification of deficiencies mentioned
above at S. No 32.
The registration Certificate shall be issued after submission of
remaining deficiencies mentioned at S. No. 32 including correction in A-H form,
Online DPI and submission of two BG’s/DD’s of Rs. 25 lakhs each for submission
of revised Fire Scheme approval and revised Approved Service plan and Estimates
within the timeframe mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |